3.2. Construction
Carried out complex researches allows formulating a methodology of the estimated monitoring for the tailing dam’s stability [
11]. The algorithm is shown in
Figure 5.
Along with the standard set of observations, the methodology of the estimated monitoring includes the tailing dam’s stability calculations under changing technological parameters of exploitation, observing geometric characteristics of construction and the properties of the inwashed tails [
11].
The technique includes a number of successive operations.
At the first stage after receiving the research data on the structure and the properties of the composing inwashed soils, the preliminary calculations for the most typical cross-section and average values of physical and mechanical properties are conducted. The result is accepted as the baseline.
As the initial data for the calculation, the following materials should be used [
11,
12]:
geology, geocryological and hydrogeological conditions, physical and mechanical properties of natural and artificial soils taken according to engineering studies, research and direct definitions and observations in the field and laboratory conditions;
geometrical parameters of structures defined by the direct geodetic works [
8].
At the second stage, while changing the values of soil characteristics, increasing and decreasing them, the influence of the physico-mechanical properties of soils on the construction stability is investigated.
At the third stage, the influence on the tailing dam’s stability of the design parameters of height of dam and of angle of the foundations under constant values of physical and mechanical properties are tested.
At the fourth stage, the changes of physico-mechanical properties of inwashed soils during alluvion and subsequent consolidation are tested. It is recommended to study the physical and mechanical characteristics by microstructural analysis and modeling.
At the final stage, the multivariate calculations of the dam’s stability are conducted using all the above-installed patterns. The calculations were carried out by means of the UniFos program. The UniFos program is a part of the UWay complex and it is intended for calculations of the stability of soil constructions. It is written in the object-oriented C++ language with the usage of optimising compiler Borland C++ Borland International v.5.02 with library OWL usage v.5.0 [
13].
The results are recorded in the database and can be replaced in the process of obtaining new data on the structure. The estimation of the maintenance of the tailing dam stability consists in comparing the information obtained as a result of standard monitoring of hydraulic structure safety with that of the existing database. And if at least one of the parameters varies from the normalized values, the calibration calculations must be carried out and engineering activities must be designed to eliminate deviations.
Thus, the idea of estimated monitoring the stability of hydrotechnical constructions is presented as a permanent model intended to quickly check the state of buildings when changing technology exploitation properties of alluvial soils, height of structures, length of the beach, water level in the body of the enclosing constructions, etc.
Taking into account the significant difference in the elevation between the dams of the first and second fields, which amounts to almost 20 m, it can be said that they form a cascading tailings storage facility.
The technology for dam inwashing considers various factors such as the height of the dam inwashed during one cycle and throughout the year, the width of the inwash front, the quantity of inwashed tails, and the schedule of operations, among others. The inwashing process is performed in sections, where after the formation of a layer of tails with a capacity of approximately 0.5 m, a hydraulic fill section is left for a period of “rest” lasting 10–15 days. This method of inwashing allows for the gradual growth of the dam.
Figure 6 and
Table 3 present the beach sectoring for determining the volume of inwashed tails and the order in which the sections of the tailing dump are inwashed [
8].
The schedule for the inwash works is planned for the entire year. This comprehensive planning approach enables the determination of the duration of dam operation until it reaches its intended design elevation.
The dam undergoes alternating washing in the first and second fields, taking into account an average daily air temperature above −5 °C [
1].
Through a series of experimental studies, a complex algorithm for the formation of the tailing dam was developed, as depicted in
Figure 7 [
14].
In the first stage of the study, it is necessary to prepare initial data for further calculations. This includes determining the geometric characteristics of the existing tailing dump, such as the areas involved, and obtaining the diameter of the main pipeline. Additionally, the number of outlets and their respective diameters need to be defined.
During the second stage, the volume of incoming tails must be determined, and the height of the annual alluvium layer should be calculated based on the actual areas of alluvium.
In the third stage, the required number of outlets, the width of the alluvium sector, and the total number of sectors for storing tailings must be determined based on the daily volume of tails and the throughput of each outlet.
In the fourth stage, the alluvium of the tailing dump needs to be performed, and it is necessary to indicate the total time of the inwash onto the beach (the number of days per year with a temperature above −5 °C), which can be determined according to the climatic conditions of the region [
1,
15].
Furthermore, it is important to set a limit on the height of the annual inwash, especially for dumps located in the cryolithozone. The maximum permissible height of alluvium per year should ensure the freezing conditions of the alluvial mass, and it depends on the climate, chemical composition, and physical and mechanical properties of the tails. To determine the value of the maximum permissible height of annual alluvium, separate studies should be conducted for each specific case.
In the fifth stage, the physical and mechanical properties of the tails need to be determined. This involves conducting a series of individual soil tests for compaction, with a gradual increase in moisture content. The results of these tests should be presented in the form of a graph, which shows the dependency of the soil’s skeleton density on its moisture content. It is recommended to conduct at least six individual tests, or a sufficient number to identify the maximum value of the soil’s skeleton density [
15].
Moreover, it is necessary to determine the plasticity limits of the tails. The ratio of filtration and rheological phenomena in the process of soil consolidation varies depending on factors such as density, humidity, characteristics of the soil structure, and the magnitude of the load. The upper limit of humidity is the moisture at the yield point [
15].
The process of consolidation is typically divided into two phases: primary or seepage consolidation and secondary consolidation due to the creep of the soil skeleton. The completion time of the seepage consolidation stage (
Cv) can be determined using consolidation curves constructed in the coordinates of displacement (
s) and the logarithm of time (
lgt) according to the Casagrande method. The consolidation curves provide valuable information about the settlement and time-dependent behavior of the soil, allowing for the prediction of consolidation settlement over time [
15].
Furthermore, the coefficient of secondary consolidation (
Cα) needs to be determined. This can be achieved by measuring the tangent of the angle between the linear segment of the consolidation curve in the secondary consolidation area and a straight line parallel to the abscissa axis [
8,
14,
15,
16,
17].
It is possible to determine the consolidation time by altering the geometric properties of the samples in controlled laboratory conditions [
8,
14,
15,
16,
17]:
where
t is the consolidation time, min;
F is the cross-sectional area of the sample, cm
2;
Cv is the consolidation coefficient, cm
2/min;
h is the initial height of the layer, cm;
s is the displacement, cm.
In order to determine the time of tailing consolidation at known design values of humidity and density, it is necessary to prepare a regression polynomial Equation (2). This equation should be arranged in ascending powers of the studying factor while ensuring linearity for all coefficients [
14,
15,
16,
17].
The alluvium process for the storage area needs to be conducted in multiple stages. Additionally, there should be a technological break established between the completion of alluvium for one lower tier and the commencement of alluvium for the subsequent tier.
During the sixth stage, an analysis of the parameters of the alluvium structure is conducted. It is important to note that in the permafrost zone, increasing the annual capacity of the layer may not result in complete consolidation before freezing during the short spring–summer period. This incomplete consolidation could potentially reduce the stability of the structure.
Considering the operational conditions of alluvial storage in permafrost areas, it is important to note that increasing the annual capacity of the layer may not allow for complete consolidation within the short spring–summer period before freezing. This can compromise the stability of the structure. To optimize the inwash technology of the tailing dam in such conditions, it is crucial to accurately determine the time required for tailings consolidation. This factor plays a crucial role in optimizing the inwash technology in the permafrost zone.
In order to guarantee sufficient time for the tailings consolidation process, it is necessary to establish the sequence of all-in sectors.
During the seventh stage, the network planning method needs to be employed to meet the regulatory requirements for optimizing the inwash process. This method helps in organizing and coordinating the various activities involved in the process, ensuring efficient and effective execution.
Upon construction and calculation of the network plan, the duration of the critical path is determined in terms of days. This critical path duration provides insight into whether the entire volume of all inwashed tails can be completed within the required time frame. By assessing the duration of the critical path, it becomes possible to evaluate whether the project timeline aligns with the necessary timeframe for placing the entire volume of the inwashed tails [
18].
In the final stage, it is crucial to verify whether the obtained number of days required for tailings inwash is compliant with the established standards. If the obtained duration does not meet the requirements, it is necessary to revisit the stage of determining the initial data.
The objective of our technological operations is to create a uniform and homogeneous mass of material. To achieve this goal, knowledge about the structure of tailings and the technological characteristics of their placement within the dam body is necessary. Studying the structure of tailings will help us understand their physical and geometric properties, such as particle size, particle size distribution, density and moisture content [
19,
20].
In the laboratory, the research of technogenic soils–tails was carried out according to the methodical scheme developed in the laboratory of soil science of the Institute of Earth Crust of the Russian Academy of Sciences by Ryashchenko T.G. [
21] and including the definition of a set of indicators that are divided into four groups:
structural (characterizing structural elements, type of structural connections and types of structures);
chemical (indicators of chemical composition and physical–chemical properties);
physical (indicators of physical condition and properties);
mechanical (indicators of deformation and strength properties).
Air-dry samples of tails of the disturbed build were used. The selected samples were gray samples, stain hands; small aggregates and clay fractions (clay sand) were clearly present.
Granulometric analysis was carried out in three ways of sample preparation: microaggregate (shaking in water), standard (boiling with ammonia), and dispersed (boiling with sodium pyrophosphate).
Table 4 and
Table 5 shows the accepted indices of indicators with their decoding.
When determining the parameters of the microstructure, the number of aggregates (A) and primary particles (M), their size distribution (Ai, Mi) and the coefficients of freedom of fractions (Fi) representing the share (%) of primary particles in their total amount (primary plus those in aggregates) special calculations were performed.
The type of the soil structural model was set on the size of the prevailing elements (
Ai +
Mi) and special factor G according to the classification [
21]. Coefficient
G—the share of primary particles in the total sum of structural elements (primary particles plus aggregates), %;
x—the size of primary particles and aggregates, microns.
The method proposed by A.K. Larionov [
22] and expanded by T.G. Ryashchenko [
23,
24] was used for the microagregency ratio calculation. These coefficients represent the difference between the fraction contents determined during dispersed sample preparation and microaggregate preparation. They are used to assess the degree of aggregation and determine the size of aggregates and their structure, i.e., it is possible to find out what smaller particles they consist of. In addition, the degree of freedom of fine-grained particles (less than 0.001 mm) particles in the size of
is determined.
Micro-aggregate ratios are defined as follows:
where (d)—the content of the relevant faction in a dispersed way of sample preparation, %; (ma)—the same with microaggregate mode of preparation, %.
The lower this coefficient, the greater the degree of freedom, that is, clay particles are not part of aggregates, but are primary. When all fine clay particles are free, they do not participate in the formation of aggregates greater than or equal to zero. is always negative if coarse-grained particles are aggregates and is zero if all of them are primary. The other four coefficients can have arbitrary values.
When determining the parameters of the microstructure, the number of aggregates (
A) and primary particles (
M), their size distribution (
Ai,
Mi) and the coefficients of freedom of fractions (
Fi), representing the share (%) of primary particles in their total amount (primary plus those in aggregates), special calculations were performed [
24,
25]. Depending on the number of aggregates, the type of microstructure was determined according to the classification
Table 6.
The type of the structural model of the soil was set on the size of the prevailing elements (
Ai +
Mi) and special factor
G according to the classification
Table 7 [
24].
Coefficient G—the share of primary particles in the total sum of structural elements (primary particles plus aggregates), %; x—the size of primary particles and aggregates, mm.
Strength indicators were determined on specially prepared samples with humidity varying in the range from 2% to 40%. Such humidity regime is due to a small difference (5.2%) between the limits of plasticity and fluidity; it is needed to assess the strength at low humidity, which corresponds to the humidity of the soil during the rest of the beach.
Tests were conducted on the automated test complex “ASIS” (
Figure 8) which is intended for carrying out the mechanical tests of natural and industrial building materials at various sorts of a stress condition and loading paths. Special software ASIS was applied to the management of the test process. The software exercises in the automated mode administration of the test process, recording and transfer of results of the test to other software packages for further processing [
26].
When the structure of the tailings is determined, the technological process for laying a homogeneous and dense structure of the massif needs to be simulated. For this, model tests were performed on a specially designed installation. The study of the influence of the technological parameters of the alluvium on the formation of a stable tailings dam was carried out using physical modeling.
For research, a laboratory stand was developed and manufactured [
27] consisting of a tray, organic glass, with the possibility of changing the slope, a slurry distribution sump (distribution slurry pipeline), and distribution outlets through which alluvium is carried out (
Figure 9). When designing the alluvium model for the tailing dam in accordance with the conditions of the theory of similarity, the chosen geometric scale was 1:100.