1. Introduction
With the rapid development of tunnel construction technology, the number of large section tunnels is increasing to better meet the increasing traffic flow and traffic conditions. Large section tunnels significantly improve transport capacity, thus reducing traffic congestion and improving road safety [
1,
2,
3,
4,
5,
6,
7]. Large section tunnels have large excavation areas, lower stability of the face, higher requirements on the stability of the surrounding rock and lining, and a higher probability of construction risk compared with ordinary tunnels [
8,
9,
10,
11].
Scholars have conducted extensive research on the stability of the surrounding rock and lining structure of large section tunnels. Li et al. [
12] took Changsha Rail Transit Tunnel No. 2 as an example to analyze the construction characteristics of different excavation methods and conducted a numerical simulation analysis on the influence of a large cross-section tunnel disturbance on surrounding rock. Wu et al. [
13] established a unified plane partition optimization model based on the four parameters of horizontal layer number, transverse partition number, step height, and section width. Moreover, using the principle of dynamic programming, the optimal excavation sequence and construction parameters of large section tunnels were studied by solving the optimization model of plane partition. Through numerical analysis, Zhang et al. [
14] derived the calculation formula of the surrounding rock pressure of large section tunnel excavation and applied it to the calculation of the surrounding rock pressure of large section subway stations. Xu et al. [
15] proposed a new loose load calculation method for large section tunnels considering the influence of multi-step construction and the temporary support of the tunnel in view of the construction characteristics of large section tunnels and compared this with the traditional method. This method was closer to the actual situation of the site. The multi-micro shield tunneling method (MMST) developed by Mori et al. [
16] took a small section of the circumference of the whole tunnel as the unit of the tunnel, used a shield machine to excavate and line it in sections, and applied it to the large section tunnel. Wu et al. [
17] used ABAQUS to analyze the deformation law of the upper stratum and surrounding rock of a large-span variable section subway tunnel group under different construction processes.
Li et al. [
18] monitored and measured the surface subsidence and crown surface subsidence during shield construction and discussed the characteristics and distribution of the surrounding rock and surface deformation during shield construction with large sections. Liu et al. [
19] designed a large-scale shaking table test system to study the seismic characteristics of the tunnel crossing and found that the maximum acceleration and strain in the underpass tunnel’s cross center section were both located in the crown. Using the numerical analysis method, Zhou et al. [
20] analyzed the influence of core rock excavation and temporary support dismantling in a super large section tunnel and found that the stress change in the area above the inverted arch was greater than that in the invert area during core excavation and temporary support removal. Zhou et al. [
21] carried out field tests on a large section tunnel, and the tests showed that the excavation of the lower bench in the left drift and the bench in the core rock affected the deformation and stress of the support structure significantly. Liang et al. [
22] analyzed the acceleration response of the lining, the response of the first principal stress and the third principal stress, and the plastic development of a highway tunnel with a large section under seismic dynamics from static to dynamic. The analysis results showed that the secondary lining played an important role in vibration as a safety reserve. Chen et al. [
23] developed a fully closed I-steel support with arch superposition and bottom arch for high stress and a large section of broken surrounding rock roadway; this strong secondary support could effectively control the surrounding rock deformation of the roadway. Lu et al. [
24] studied the secondary lining timing of a large section loess tunnel with surrounding rock and the basic stability rate of the initial support as the timing index, with results showing that when the subsidence deformation rate of the vault was less than 0.55 mm/d and the absolute convergence rate of the lateral wall was less than 0.11 mm/d, the secondary lining can be carried out.
At present, the main excavation methods of large section tunnels include the step method, circular excavation with reserved core earth method, double-side heading method, center diaphragm (CD) method, and cross diagram (CRD) method. Jiang et al. [
25] used a numerical analysis method to analyze the surrounding rock deformation and stress variation rule in the construction of the double-side heading method and CRD method. The results showed that the double-side heading method had advantages over the CRD method in terms of the total amount of tunnel deformation and the surface settlement caused by the tunnel construction in the weak surrounding rock area. Sun et al. [
26] discussed the whole process of the simulated construction of the large section tunnel excavation method using the step method, CRD method, and double-side tunneling method and studied the surrounding rock deformation during tunnel excavation; the results showed that in the condition of large surface subsidence, the double-side heading method was preferred. Considering that the double-side heading method has the most prominent safety of all the excavation methods, it is often used in tunnel excavations with poor geological conditions [
27,
28]. Yang et al. [
29] studied the damage degree and scope of rock mass in the construction of the double-side heading method with a new large section adjacent to the existing tunnel. Subsequently, they optimized the construction parameters, such as the single-cycle footage and blasting parameters of the pilot tunnel. Taking Hongtudi station of Chongqing Rail Transit Line VI as the research object, Wang et al. [
30] calculated the surrounding rock stress, plastic strain, internal force of the supporting structure, and vault settlement under core columns of different widths. Cui [
31] analyzed the double-side heading method first and excavated the middle partition wall later, focusing on the stability and reinforcement measures of the rock pillar excavation of the middle partition wall.
Generally speaking, scholars have conducted numerous studies on large section tunnels, mainly focusing on the excavation and support methods of large section tunnels, and achieved fruitful results. However, few studies on the excavation steps of rock mass and support timing in the double-side heading method are commonly used in large section tunnels. Therefore, taking the large section tunnel of the Xiamen Haicang Evacuate-channel project as the research object, the influence of the excavation sequence, second primary lining support time, temporary support disassembly, and secondary lining support time of the double-side heading method on large section tunnel stability were studied.
2. Background
The Haicang Evacuate-channel tunnel is located in Xiamen, Fujian, China, which connects the Haixin interchange project in the west and extends to the east (
Figure 1a,b). Its 2# tunnel goes through Caijianwei Mountain. The total length of the tunnel route is 5.307 km, and the road grade is an urban expressway with six two-way lanes and a design speed of 80 km/h. The tunnel is buried deep in the mountains, with a buried depth of nearly 100 m.
Figure 1c shows that the mainline 2# tunnel of the evacuate-channel and the mainline tunnel of Luao Road set up the Lushu interchange at the node of Xinmei Road, and there are four ramps, namely, A, B, C, and D, at this interchange, which are semi-interconnecting. The plane distribution of the bifurcation section is shown in
Figure 1d. The research section is within the blue frame, and its pile number is ZK2 + 620 − ZK2 + 665. The research section mainly passes through the second intrusive granite strata, which is dominated by moderate weathering. It is distributed in grade III surrounding rock and belongs to relatively complete rock. The surface water in the research section is abundant, but it has little influence on tunnel construction.
In the study section, the double-side heading method was adopted to divide the large section tunnel into four parts: the left and right sidewall diversion tunnel, the upper core soil, and the lower steps. The research section was constructed by the double-side heading method, and the large section tunnel was divided into four parts: the left and right pilot tunnel, the upper core soil, and the lower bench. The maximum excavation span of the large section tunnel was 30.52 m, and the large section tunnel was divided into nine parts and excavated step-by-step. The number of rock masses was 1–9 (
Figure 2). The plane coordinates of the boundary points of each excavation part are shown in
Figure 2 where the coordinate origin is (0, 0). The composite lining of the large section tunnel included the first primary lining support, the second primary lining support, the I-steel frame temporary support, and the second lining concrete layer of the arch wall and inverted arch. The parameters are shown in
Table 1.