Estimating Construction Project Duration and Costs upon Completion Using Monte Carlo Simulations and Improved Earned Value Management
Abstract
:1. Introduction
- What are the limitations of the traditional EVM approach?
- How can traditional EVM be improved to address the limitations identified in question 1?
- How can the improved EVM be combined with CPM, PERT, and MCS to propose a comprehensive monitoring and estimation approach?
2. Literature Review
2.1. EVM
2.1.1. Problems of Traditional EVM
- (1)
- EVM does not consider engineering quality;
- (2)
- Unclear deviation sources ( and accuracy);
- (3)
- Inaccurate completion estimates;
- (4)
- EVM does not consider uncertainty or give a range of possible values;
2.1.2. Extension and Improvement of Traditional EVM
2.2. Combine Different Project Management Approaches
2.2.1. CPM and CCPM
2.2.2. PERT and MCS
3. Proposed Estimation Approach
3.1. Estimation Principle and Checkpoint Measurement Metrics
3.2. Schedule and Cost Measurement
3.3. Three-Point Estimation
3.4. Preliminary Project Estimation
3.5. MCS Process
4. Experimental Research
4.1. Project Overview
4.2. Checkpoint Schedule and Cost Analysis
4.3. Preliminary Estimation of Project Duration and Cost
4.4. MCS
4.5. Analysis and Discussion
5. Conclusions and Future Work
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
Abbreviations
actual cost | |
actual cost of finished activity | |
actual cost of ongoing activity | |
actual duration | |
actual duration of finished activity | |
actual duration of ongoing activity | |
actual duration of finished activity on path | |
activities that do not fall into any of the categories | |
checkpoint | |
checkpoint time | |
cost spent up to the checkpoint | |
cost performance index | |
cost performance index at the checkpoint | |
cost performance index of finished activity | |
cost performance index of ongoing activity | |
cost performance index of activity in category | |
cost variance | |
cost variance at the checkpoint | |
cost variance of finished activity | |
cost variance of ongoing activity | |
optimistic estimated cost of not started activity which is not in any categories | |
most likely estimated cost of not started activity which is not in any categories | |
pessimistic estimated cost of not started activity which is not in any categories | |
optimistic estimated cost of not started activity in category | |
most likely estimated cost of not started activity in category | |
pessimistic estimated cost of not started activity in category | |
optimistic estimated duration of not started activity which is not in any categories on path | |
most likely estimated duration of not started activity which is not in any categories on path | |
pessimistic estimated duration of not started activity which is not in any categories on path | |
estimated mean cost of not started activity which is not in any categories | |
estimated mean cost of not started activity in category | |
estimated mean duration of not started activity which is not in any categories on path | |
estimated mean duration of not started activity in category on path | |
optimistic estimated remaining cost of ongoing activity | |
most likely estimated remaining cost of ongoing activity | |
pessimistic estimated remaining cost of ongoing activity | |
optimistic estimated remaining duration of ongoing activity on path | |
most likely estimated remaining duration of ongoing activity on path | |
pessimistic estimated remaining duration of ongoing activity on path | |
estimated remaining mean duration of ongoing activity on path | |
estimated remaining mean cost of ongoing activity | |
finished percentage | |
finished percentage of ongoing activity | |
maximum value of actual finished time for all previous activities of activity | |
planned duration | |
planned duration of finished activity | |
planned duration of ongoing activity | |
planned duration of finished activity on path | |
planned duration of ongoing activity on path | |
planned duration of not started activity which is not in any categories on path | |
planned duration of not started activity in category on path | |
quality factor | |
quality factor of finished activity | |
quality factor of ongoing activity | |
quality factor of finished activity on path | |
quality factor of ongoing activity on path | |
schedule performance index | |
schedule performance index of finished activity | |
schedule performance index of ongoing activity | |
schedule performance index of path | |
schedule variance | |
schedule variance of finished activity | |
schedule variance of ongoing activity | |
schedule variance of path | |
total estimated remaining mean duration of path | |
total estimated remaining mean duration | |
total estimated duration at completion | |
total estimated remaining mean cost | |
total estimated duration at completion | |
number of activities on path | |
number of finished activities on path | |
number of ongoing activities on path | |
number of not started activities on path | |
cost standard deviation of not started activity which is not in any categories | |
cost standard deviation of ongoing activity | |
cost standard deviation of not started activity in category | |
duration standard deviation of not started activity which is not in any categories on path | |
duration standard deviation of not started activity in category on path | |
duration standard deviation of ongoing activity on path |
References
- Assaf, S.A.; Al-Hejji, S. Causes of delay in large construction projects. Int. J. Proj. Manag. 2006, 30, 349–357. [Google Scholar] [CrossRef]
- Shehu, Z.; Endut, I.R.; Akintoye, A.; Holt, G.D. Cost overrun in the Malaysian construction industry projects: A deeper insight. Int. J. Proj. Manag. 2014, 32, 1471–1480. [Google Scholar] [CrossRef]
- Arantes, A.; Ferreira, L.M.D. Underlying causes and mitigation measures of delays in construction projects. J. Financ. Manag. Prop. 2020, 25, 165–181. [Google Scholar] [CrossRef]
- Shepperd, M.; MacDonell, S. Evaluating prediction systems in software project estimation. Inform. Softw. Techol. 2012, 54, 820–827. [Google Scholar] [CrossRef] [Green Version]
- Jayaraman, R. Project cost control: A new method to plan and control costs in large projects. Bus. Process. Manag. J. 2016, 22, 1247–1268. [Google Scholar] [CrossRef]
- Project Management Institute. A Guide to the Project Management Body of Knowledge (PMBOK GUIDE), 6th ed.; Project Management Institute (PMI): Newtown Square, PA, USA, 2017. [Google Scholar]
- Vargas, R.V. Earned Value Analysis in the Control of Projects: Success or Failure? AACE International Transactions: Morgantown, WV, USA, 2003. [Google Scholar]
- Joseph, A.; Lukas, P.E. Earned Value Analysis—Why It Doesn’t Work; AACE International Transactions: Morgantown, WV, USA, 2008. [Google Scholar]
- Lipke, W. Schedule is different. Meas. News 2003, 31, 31–34. [Google Scholar]
- Vandevoorde, S.; Vanhoucke, M. A comparison of different project duration forecasting methods using earned value metrics. Int. J. Proj. Manag. 2006, 24, 289–302. [Google Scholar] [CrossRef]
- Nizam, A.; Elshannaway, A. Review of Earned Value Management (EVM) Methodology, its Limitations, and Applicable Extensions. JMEI 2019, 12, 59–70. Available online: https://www.proquest.com/scholarly-journals/review-earned-value-management-evmmethodology/docview/2382631105/se-2 (accessed on 17 January 2022).
- Project Management Institute. A Guide to the Project Management Book of Knowledge (PMBOK), 3rd ed.; Project Management Institute (PMI): Newton Square, PA, USA, 2004. [Google Scholar]
- Hsiau, H.J.; Lin, C.W.R. A Fuzzy PERT Approach to Evaluate Plant Construction Project Scheduling Risk Under Uncertain Resources Capacity. J. Ind. Eng. Manag. 2009, 2, 31–47. Available online: http://hdl.handle.net/2099/8217 (accessed on 17 January 2022). [CrossRef] [Green Version]
- Sutrisna, M.; Pellicer, E.; Torres-machi, C.; Picornell, M. Exploring earned value management in the Spanish construction industry as a pathway to competitive advantage. Int. J. Constr. Manag. 2018, 20, 1–12. [Google Scholar] [CrossRef]
- Proaño-Narváez, M.; Flores-Vázquez, C.; Vásquez Quiroz, P.; Avila-Calle, M. Earned Value Method (EVM) for Construction Projects: Current Application and Future Projections. Buildings 2022, 12, 301. [Google Scholar] [CrossRef]
- Tafazzoli, M.; Shrestha, P.P. Investigating Causes of Delay in US Construction Projects. In Proceedings of the 53rd Annual ASC International Conference, Seattle, WA, USA, 5–8 April 2017. [Google Scholar]
- Franz, B. Total Construction Management: Lean Quality in Construction Project Delivery. Eng. Constr. Archit. Manag. 2008, 25, 295–296. [Google Scholar] [CrossRef]
- Acebes, F.; Pajares, J.; Galán, J.M.; López-Paredes, A. A new approach for project control under uncertainty. Going back to the basics. Int. J. Proj. Manag. 2014, 32, 423–434. [Google Scholar] [CrossRef]
- Kim, B.C.; Reinschmidt, K.F. Probabilistic Forecasting of Project Duration Using Kalman Filter and the Earned Value Method. J. Constr. Eng. Manag. 2010, 136, 834–843. [Google Scholar] [CrossRef]
- Dodson, D.G.; de Carvalho, V. Quality: The Third Element of Earned Value Management. Procedia Comput. Sci. 2015, 64, 932–939. [Google Scholar] [CrossRef] [Green Version]
- Guo, S.H.; Zhi-Yuan, H.U.; Liu, P.F. Quality Earned Value Method Based on Delphi Method. J. Water Resour. Archit. Eng. 2011, 2, 44–47. [Google Scholar]
- Khesal, T.; Saghaei, A.; Khalilzadeh, M.; Rahiminezhad Galankashi, M.; Soltani, R. Integrated cost, quality, risk and schedule control through earned value management (EVM). J. Eng. Des. Technol. 2019, 17, 183–203. [Google Scholar] [CrossRef]
- Vanhoucke, M. Project Management with Dynamic Scheduling: Baseline Scheduling. Risk Analysis and Project Control, 2nd ed.; Springer: Berlin/Heidelberg, Germany, 2012. [Google Scholar]
- Cheng, P.; Fei, X. The Model of Improved Earned Value Based on Critical Path. Sci. Technol. Ind. 2013, 10, 156–160. [Google Scholar]
- Naeni, L.M.; Shadrokh, S.; Salehipour, A. A fuzzy approach for the earned value management. Int. J. Proj. Manag. 2014, 32, 709–716. [Google Scholar] [CrossRef]
- Ranasinghe, M. Quantification and management of uncertainty in activity duration networks. Constr. Manag. Econ. 1994, 12, 15–29. [Google Scholar] [CrossRef]
- Karabulut, M. Application of Monte Carlo simulation and PERT/CPM techniques in planning of construction projects: A Case Study. Period. Eng. Nat. Sci. 2017, 5, 408–420. [Google Scholar] [CrossRef]
- Dashkov, R.Y.; Komkov, N.I. Integrated Approach to Large-Scale Project Management at Sakhalin Energy. Stud. Russ. Econ. Dev. 2022, 33, 74–83. [Google Scholar] [CrossRef]
- Olivieri, H.; Seppänen, O.; Alves, T.D.C.; Scala, N.M.; Schiavone, V.; Liu, M.; Granja, A.D. Survey Comparing Critical Path Method, Last Planner System, and Location-Based Techniques. J. Constr. Eng. Manag. 2019, 145, 04019077. [Google Scholar] [CrossRef] [Green Version]
- Kelley, J.E.; Walker, M. Critical path planning and scheduling. In Proceedings of the Eastern Joint IRE-AIEE-ACM Computer Conference, Boston, MA, USA, 1–3 December 1959; pp. 160–173. [Google Scholar]
- Laufer, A.; Tucker, R.L. Is construction project planning really doing its job? A critical examination of focus, role and process. Constr. Manag. Econ. 1987, 5, 243–266. [Google Scholar] [CrossRef]
- Koskela, L.; Howell, G. The underlying theory of project management is obsolete. In Proceedings of the PMI Research Conference, Seattle, WA, USA, 14–17 July 2002; pp. 293–302. [Google Scholar]
- Hamzeh, F.; Ballard, G.; Tommelein, I.D. Rethinking look ahead planning to optimize construction workflow. Lean Constr. J. 2012, 1, 15–34. [Google Scholar]
- Aliverdi, R.; Moslemi Naeni, L.; Salehipour, A. Monitoring project duration and cost in a construction project by applying statistical quality control charts. Int. J. Proj. Manag. 2013, 31, 411–423. [Google Scholar] [CrossRef]
- Darmawan, J.; Wijaya, A.H.; Hakim, L.; Tannady, H. Comparing Freeman Chain Code 4 Adjacency Algorithm and LZMA Algorithm in Binary Image Compression. J. Phys. Conf. Ser. 2020, 1783, 012045. [Google Scholar] [CrossRef]
- Petroutsatou, K. A proposal of project management practices in public institutions through a comparative analyses of critical path method and critical chain. Int. J. Constr. Manag. 2019, 22, 242–251. [Google Scholar] [CrossRef]
- Zhang, J.; Song, X.; Díaz, E. Critical chain project buffer sizing based on resource constraints. Int. J. Prod. Res. 2019, 55, 671–683. [Google Scholar] [CrossRef]
- Yakhchali, S.H. Program Evaluation and Review Techniques II (PERT II). Eng. Lett. 2011, 19, 137–149. [Google Scholar]
- Uher, T.E.; Zantis, A.S. Programming and Scheduling Techniques, 2nd ed.; Routledge: Oxfordshire, UK, 2012; pp. 1–281. [Google Scholar] [CrossRef]
- Premachandra, I. An approximation of the activity duration distribution in PERT. J. Comput. Oper. Res. 2001, 28, 443–452. [Google Scholar] [CrossRef]
- Tokdemir, O.B.; Erol, H.; Dikmen, I. Delay risk assessment of repetitive construction projects using line-of-balance scheduling and Monte Carlo simulation. J. Constr. Eng. Manag. 2019, 145, 04018132. [Google Scholar] [CrossRef]
- Korn, R.; Korn, E.; Kroisandt, G. Monte Carlo Methods and Models in Economics and Finance; CRC Press: London, UK, 2010. [Google Scholar]
- Hendradewa, A.P. Schedule Risk Analysis by Different Phases of Construction Project Using CPM-PERT and Monte-Carlo Simulation. IOP Conf. Ser. Mater. Sci. Eng. 2019, 528, 12035. [Google Scholar] [CrossRef] [Green Version]
- Chang, C.Y.; Ko, J.W. New approach to estimating the standard deviations of lognormal cost variables in the Monte Carlo analysis of construction risks. J. Constr. Eng. Manag. 2018, 143, 06016006. [Google Scholar] [CrossRef]
- Xu, J.; Zhang, H.; Li, F. Project integrated management based on quality earned value. In Proceedings of the 2nd International Conference on Information Science and Engineering, Hangzhou, China, 4–6 December 2010; pp. 432–435. [Google Scholar] [CrossRef]
- Kwak, Y.H.; Ingall, L. Exploring Monte Carlo simulation applications for project management. IEEE Eng. Manag. Rev. 2009, 37, 83. [Google Scholar] [CrossRef]
- Wang, Y.; Qian, Y.; Zhang, L.; Qiong, X.U. Method of Project Schedule and Cost Management Based on Activity Performance Analysis. Sci. Technol. Manag. Res. 2016, 36, 207–212. [Google Scholar]
- Chen, X.; Cheng, L.; Deng, G.; Guan, S.; Hu, L. Project duration-cost-quality prediction model based on Monte Carlo simulation. J. Phys. Conf. Ser. 2021, 1978, 012048. [Google Scholar] [CrossRef]
- Colin, J.; Vanhoucke, M. A comparison of the performance of various project control methods using earned value management systems. Expert. Syst. Appl. 2015, 42, 3159–3175. [Google Scholar] [CrossRef]
- Wauters, M.; Vanhoucke, M. Support vector machine regression for project control forecasting. Autom. Constr. 2014, 47, 92–106. [Google Scholar] [CrossRef] [Green Version]
- Bonato, F.K.; Albuquerque, A.; Paixo, M. An application of Earned Value Management (EVM) with Monte Carlo simulation in engineering project management. Gestão Produção 2019, 26, e4641. [Google Scholar] [CrossRef] [Green Version]
- Johnson, D. The triangular distribution as a proxy for the beta distribution in risk analysis. J. R. Stat. Soc. Ser. D 1997, 46, 387–398. [Google Scholar] [CrossRef]
- Kuhl, M.E.; Steiger, N.M.; Lada, E.K.; Wagner, M.A.; Wilson, J.R. Introduction to modeling and generating probabilistic input processes for simulation. In Proceedings of the IEEE 2006 Winter Simulation Conference, Monterey, CA, USA, 3–6 December 2006; pp. 19–35. [Google Scholar] [CrossRef]
- Hong, K.; Yu, J.; Liu, Z.; Zhao, M.; Bi, L. Construction schedule risk analysis of diversion tunnel based on improved PERT. J. Tianjin Univ. 2015, 17, 122–128. [Google Scholar]
- Burciu, Z. Determination of the Risk Function for Survivors Using Beta Pert Method. J. Konbin 2007, 3, 17–26. [Google Scholar] [CrossRef]
- Lake, R.J.; Cressey, P.J.; Campbell, D.M.; Oakley, E. Risk ranking for foodborne microbial hazards in New Zealand: Burden of disease estimates. Risk Anal. 2010, 30, 743–752. [Google Scholar] [CrossRef] [PubMed]
- Jing, L.; Chen, B.; Zhang, B.; Li, P.; Zheng, J. Monte Carlo Simulation–Aided Analytic Hierarchy Process Approach: Case Study of Assessing Preferred Non-Point-Source Pollution Control Best Management Practices. J. Environ. Eng. 2013, 139, 618–626. [Google Scholar] [CrossRef]
- Votto, R.; Lee Ho, L.; Berssaneti, F. Applying and Assessing Performance of Earned Duration Management Control Charts for EPC Project Duration Monitoring. J. Constr. Eng. Manag. 2020, 146, 04020001. [Google Scholar] [CrossRef]
Measured Metrics | Finished Activities (FP = 100%) | Ongoing Activities (0% < FP < 100%) |
---|---|---|
and | Record to the facts | |
and | Record to the facts | Record to the facts |
and | Review confirmed | Review confirmed |
Activity | A | B | C | D | E | F | G | H | I | J | K |
---|---|---|---|---|---|---|---|---|---|---|---|
(Month) | 3 | 4 | 8 | 10 | 6 | 12 | 8 | 10 | 6 | 10 | 7 |
(CNY ten thousand) | 4 | 6 | 14 | 12 | 7 | 10 | 11 | 15 | 9 | 12 | 8 |
Activity | A | B | C | D | E |
---|---|---|---|---|---|
(%) | 100 | 100 | 75 | 65 | 90 |
1.1 | 0.9 | 1.0 | 1.1 | 0.9 | |
3.5 | 3.7 | 6.5 | 6.3 | 6.3 | |
5 | 5.8 | 12 | 8.26 | 6.8 |
Activity | A | B | C | D | E |
---|---|---|---|---|---|
(Month) | −0.20 | −0.10 | −0.50 | 0.85 | −1.44 |
(%) | 94.29 | 97.30 | 92.31 | 113.49 | 77.14 |
(CNY ten thousand) | −0.60 | −0.40 | −1.50 | 0.32 | −1.13 |
(%) | 88.00 | 93.10 | 87.50 | 103.87 | 83.38 |
Path | Checkpoint | |||||
---|---|---|---|---|---|---|
(Month) | −0.7 | −0.7 | 0.75 | −1.54 | −1.54 | 0.46 |
(%) | 93 | 93 | 107.5 | 84.6 | 84.6 | 101.5 |
(CNY ten thousand) | NA | NA | NA | NA | NA | −3.31 |
(%) | NA | NA | NA | NA | NA | 91.26 |
Activity | C′ | D′ | E′ |
---|---|---|---|
2.00 | 2.51 | 1.14 | |
2.17 | 2.51 | 1.48 | |
2.48 | 2.51 | 1.77 | |
2.19 | 2.51 | 1.47 | |
0.079 | 0.000 | 0.105 | |
3.50 | 3.29 | 1.33 | |
4.00 | 3.29 | 1.60 | |
4.33 | 3.29 | 2.07 | |
3.97 | 3.29 | 1.63 | |
0.139 | 0.000 | 0.123 |
Activity | F | G | H | I | J | K |
---|---|---|---|---|---|---|
12.00 | 8.00 | 10.00 | 6.00 | 10.00 | 6.17 | |
12.64 | 8.67 | 10.61 | 6.17 | 12.96 | 6.17 | |
13.34 | 9.90 | 12.05 | 6.62 | 15.55 | 6.17 | |
12.72 | 8.76 | 10.75 | 6.22 | 12.90 | 6.17 | |
0.291 | 0.317 | 0.342 | 0.104 | 0.924 | 0.000 | |
10.00 | 11.00 | 15.00 | 9.00 | 12.00 | 7.70 | |
10.97 | 12.57 | 17.05 | 9.67 | 14.39 | 7.70 | |
11.45 | 13.62 | 18.08 | 9.94 | 18.66 | 7.70 | |
10.89 | 12.48 | 16.88 | 9.60 | 14.70 | 7.70 | |
0.242 | 0.437 | 0.513 | 0.156 | 1.109 | 0.000 |
Variables | Project | |||||
---|---|---|---|---|---|---|
(Month) | 30.98 | 33.80 | 34.14 | 35.05 | 28.26 | 35.05 |
(CNY ten thousand) | NA | NA | NA | NA | NA | 119.00 |
Statistical Variables | Duration | Cost | |||||
---|---|---|---|---|---|---|---|
Mean | 31.06 | 33.84 | 34.16 | 35.11 | 28.39 | 35.11 | 118.99 |
Std | 0.294 | 1.116 | 1.111 | 1.115 | 0.392 | 1.112 | 1.488 |
Min | 30.23 | 30.55 | 30.88 | 31.85 | 27.43 | 31.71 | 114.60 |
25% | 30.85 | 33.04 | 33.36 | 34.30 | 28.09 | 34.30 | 117.93 |
50% | 31.06 | 33.84 | 34.16 | 35.12 | 28.36 | 35.12 | 118.95 |
75% | 31.27 | 34.65 | 34.97 | 35.93 | 28.66 | 35.94 | 120.00 |
Max | 32.03 | 37.05 | 37.34 | 38.45 | 29.69 | 38.45 | 123.94 |
Percentage Point | Duration | Cost |
---|---|---|
0% | 31.70 | 114.60 |
10% | 33.65 | 117.10 |
20% | 34.11 | 117.72 |
30% | 34.48 | 118.18 |
40% | 34.83 | 118.58 |
50% | 35.12 | 118.96 |
60% | 35.44 | 119.36 |
70% | 35.77 | 119.83 |
80% | 36.12 | 120.33 |
90% | 36.60 | 121.01 |
100% | 38.47 | 124.00 |
Duration | Cost | |||||
---|---|---|---|---|---|---|
Number of Segments | Min | Max | Frequency | Min | Max | Frequency |
1 | 31.70 | 32.38 | 29 | 114.60 | 115.54 | 61 |
2 | 32.38 | 33.05 | 269 | 115.54 | 116.48 | 334 |
3 | 33.05 | 33.73 | 898 | 116.48 | 117.42 | 1071 |
4 | 33.73 | 34.41 | 1567 | 117.42 | 118.36 | 2036 |
5 | 34.41 | 35.08 | 2125 | 118.36 | 119.30 | 2311 |
6 | 35.08 | 35.76 | 2141 | 119.30 | 120.24 | 1993 |
7 | 35.76 | 36.44 | 1672 | 120.24 | 121.18 | 1365 |
8 | 36.44 | 37.11 | 987 | 121.18 | 122.12 | 620 |
9 | 37.11 | 37.79 | 285 | 122.12 | 123.06 | 177 |
10 | 37.79 | 38.47 | 27 | 123.06 | 124.00 | 32 |
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations. |
© 2022 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Deng, J.; Jian, W. Estimating Construction Project Duration and Costs upon Completion Using Monte Carlo Simulations and Improved Earned Value Management. Buildings 2022, 12, 2173. https://doi.org/10.3390/buildings12122173
Deng J, Jian W. Estimating Construction Project Duration and Costs upon Completion Using Monte Carlo Simulations and Improved Earned Value Management. Buildings. 2022; 12(12):2173. https://doi.org/10.3390/buildings12122173
Chicago/Turabian StyleDeng, Jie, and Wei Jian. 2022. "Estimating Construction Project Duration and Costs upon Completion Using Monte Carlo Simulations and Improved Earned Value Management" Buildings 12, no. 12: 2173. https://doi.org/10.3390/buildings12122173