Research on Resilience Evaluation and Enhancement of Deep Foundation Pit Construction Safety System

1
Department of Construction Management, School of Civil Engineering, Sanjiang University, No.310, Longxi Road, Yuhuatai District, Nanjing 210012, China
2
Department of Smart Construction and Management, School of Civil Engineering, Nanjing Tech University, No.30, Puzhu South Road, Pukou District, Nanjing 211816, China
3
Department of Construction Management and Real Estate, School of Civil Engineering, Southeast University, Jiulonghu Campus, Nanjing 211102, China
*
Author to whom correspondence should be addressed.
Buildings 2022, 12(11), 1922; https://doi.org/10.3390/buildings12111922
Submission received: 9 October 2022 / Revised: 21 October 2022 / Accepted: 4 November 2022 / Published: 8 November 2022
(This article belongs to the Section Construction Management, and Computers & Digitization)

Abstract

:
Deep foundation pit (DFP) projects have been a high incidence area of safety accidents because of their own high danger and complexity. Therefore, it is necessary to study the resilience of their construction safety system. This paper systematically identifies the key factors affecting the resilience of deep foundation pit construction based on the analysis of the composition of the deep foundation pit construction safety system (DFPCTSS), the synergistic relationship of its subsystems in the face of the interference and impact of internal and external disaster-causing factors, and the causal mechanism of typical accidents in DFP accidents and the emergent process of system resilience. A resilience evaluation indicator system based on four capacity dimensions of prevention absorption, resistance, recovery, and learning adaptation was constructed by using the fuzzy Delphi method, which is characterized by the resilience emergence process. Then the correlation and weight of evaluation indexes were analyzed based on the DEMATEL–ANP method, the boundary cloud parameters of the resilience evaluation grade were set according to the normal extension cloud model, and the membership degree of the resilience evaluation level was calculated to complete the evaluation of the resilience level. Finally, taking a DFP project of a metro station as an example, the above model was used to evaluate the resilience level of its construction safety system, and suggestions for resilience enhancement were put forward. The results show that the evaluation results are consistent with the actual situation of the project, and the evaluation model is conducive to providing a systematic analysis method and improvement countermeasures for deep foundation pit construction safety management from the perspective of resilience.

1. Introduction

The deep foundation pit project, as the foundation or main project of underground rail transit station facilities and urban commercial complex and high-rise buildings, has been a high-frequency field of safety accidents due to its complex construction conditions, large environmental impact, and strong technical comprehensiveness. Scholars have been studying safety management for a long time, but they mainly focus on engineering risk assessment and monitoring from the perspective of safety risk management based on reliability theory [1,2]. For example, Finno and Bryson [3] evaluated the risk of deep foundation works and support stages with reference to parameters such as load values of the deep foundation support structure system, building settlement, and lateral displacement distance of soil, as well as based on damage characteristics such as width and depth of cracks in surrounding structures. Castaldo and Jalayer [4] evaluated the risk of groundwater seepage by considering construction defects and uncertainties in geological structures and construction parameters during the deep foundation works phase. Based on the fault tree analysis, Heravi and Taherkhani [1] applied fuzzy integrated analysis and Monte Carlo simulation to study the sensitivity and root causes of risk responses in deep foundation pit construction and proposed some useful suggestions to reduce reliability failures in deep foundation pits based on Bayesian network analysis.
In recent years, given that the traditional safety management research paradigm emphasizing results and causes and advocating accident prevention and accident analysis can no longer meet the needs of engineering safety management, engineering safety resilience research with the concept of resilience as the core and emphasizing continuous resistance and active recovery has been greatly developed, and scholars have begun to pay attention to engineering safety resilience research. However, the existing research mainly focuses on the safety resilience of urban infrastructure systems and lacks relevant research on deep foundation pit construction safety systems from the perspective of resilience. Therefore, this paper introduces the resilience theory to identify, measure, and evaluate the key indicators that affect the resilience level of DFPCTSS from the perspective of dynamic process based on the capability characterization of each stage of resilience emergence. This study aims to construct a set of evaluation index system and evaluation model that can objectively and truly reflect the resilience characteristics to provide a basis for the government construction safety management department to evaluate the resilience level of DFPCTSS. The study results can also provide a basis for contractors to improve construction safety system resilience and accident prevention and response capabilities.
The rest of this paper is structured as follows. Section 2 reviews the relevant literature, and the overall research methodology is given in Section 3. In Section 4, the evaluation indicator system for DFPCSS is constructed. The resilience evaluation model is proposed in Section 5. Then a numerical case study based on Metro Line 1 of a certain place is conducted in Section 6. Finally, Section 7 concludes this paper.

2. Literature Review

Since few studies have directly addressed the resilience of DFPCSS, this study expands the scope of the review to include studies on the resilience of other infrastructure engineering safety systems in the analysis to provide a reference for the study of deep foundation pit safety systems.

2.1. Research on Resilience Assessment of Engineering Safety System

Resilience-based assessments are critical for identifying preventive measures to mitigate the consequences of various disruptive events [5]. The resilience assessment index system and method have been studied extensively. Zhu and Manandhar [6] constructed a system including vulnerability, expectations, redundancy, adaptability, rapidity, intelligence, cross-scale interaction, and learning culture to assess the resilience of the power and water infrastructure systems. Mottahedi and Sereshki [7] proposed a quantitative assessment scheme for critical infrastructure system resilience based on expert judgment and fuzzy set theory, considering the limitations of lack of historical data and information sources in traditional system resilience assessment and described the process of identifying and quantifying the factors affecting resilience, thus improving the effectiveness of modeling based on the influencing factors. Heravi and Taherkhani [1] combined the dynamic Bayesian network with the functional resonance analysis method to provide a better method for the rigorous quantitative analysis of the resilience of complex process systems based on the level of technology–human–organization interaction. Using a dynamic network flow model, Goldbeck and Angeloudis [8] constructed a dynamic integrated modeling and simulation framework that combines the network and performance representation of infrastructure systems, compensating for the defect that current resilience-assessment methods ignore the interdependence of critical infrastructure systems. Guo and Shan [9] screened resilience evaluation indicators based on bibliometric and Delphi methods and constructed an ANP–Extended Cloud comprehensive evaluation model to evaluate the resilience of subway construction site safety systems. Qiang and Jiaqi [10] established a tunnel construction safety resilience evaluation index system based on the properties of resilience, such as resistance, adaptability, and recovery and constructed a tunnel construction safety resilience evaluation model based on ideal fuzzy matter–element. Dan et al. (2021) identified 24 resilience assessment frameworks from 24 high-quality papers; extracted and summarized 16 dimensions; and concluded that technical, organizational, social, and economic dimensions might be the four most basic assessment dimensions. He and Wang [11] established an employee relationship network based on the social network analysis and studied the measurement of resilience of construction projects from the perspective of employee behavior in terms of four characteristics: robustness, redundancy, rapidity, and intelligence.

2.2. Research on Safety and Risk Assessment of Deep Excavations Construction System

The relevant studies were mainly conducted in terms of the construction of evaluation index system and the selection of evaluation methods. Zhang [12] determined the evaluation indexes through expert survey and combined ANP–fuzzy hierarchical fuzzy comprehensive evaluation method to evaluate the safety condition and engineering risk of deep foundation pit construction. Wang and Zhao [13] screened out the key hazard sources affecting the safety of DFP projects from three aspects, namely construction, management, and environment based on the temporal and functional attributes of system elasticity; constructed a risk evaluation index system; and realized the risk assessment of DFP construction based on the two-dimensional entropy power cloud model. Wu and Zhang [14] constructed an extension cloud risk assessment model based on the theory of extensibility and combined with the characteristics of DFP construction and realized the transformation from qualitative evaluation results to quantitative data presentation. Bo [15] constructed a construction safety evaluation index system from five aspects, namely management factors, equipment reasons, personnel factors, technical indicators, and environmental impact, combined with the actual construction of a subway deep-excavation project and expert advice, and used the BP neural network training model to train the output evaluation data to determine the safety evaluation level of the project site.
In conclusion, scholars have studied the construction of resilience evaluation index systems and evaluation methods for critical infrastructure systems and construction safety systems. However, there is no research on the construction of resilience evaluation index system and evaluation method for the DFPCSS. Therefore, this paper constructs the resilience evaluation index system of DFPCSS based on the systematic identification of key factors affecting the safety and resilience of DFP construction and according to the capacity characteristics of each stage of resilience emergence. Then the correlation and weights of evaluation indexes are analyzed based on the DEMATEL–ANP method. After that, the boundary cloud parameters of the resilience level are set according to the normal extended cloud model, the membership degree of the resilience evaluation level is calculated, and the evaluation of the resilience level is completed. This study realizes the process evaluation of DFPCSS resilience, which provides a basis for comprehensive improvement of DFP construction safety and accident response capability.

3. Methodology

3.1. Definition and Connotation of DFPCSS Resilience

The mainstream division of existing engineering systems is mainly based on the “4M1E” theory, that is, the five management elements of man, machine, material, method, and environments [16]. Based on the theory of engineering system safety resilience, this paper divides the DFPCSS into four major components, namely personnel organization, material, technology, and environmental system, according to the five safety management dimensions of “4M1E”. The four components of DFPCSS are explained in detail as follows:
(1)
Personnel organization system
The safety awareness of personnel, safety avoidance skills, and the organization’s emergency management capability are important representations of the resilience level of construction safety system. The personnel organization management system includes personnel composition and organization management mode. The personnel can be divided into operation personnel, supervisory personnel, and construction management personnel. Organizational management mode includes organizational structure, organizational division of labor, organizational management methods and systems, etc. Good organizational control has a positive effect on the resilience of material management system and technical management system.
(2)
Material system
In the theory of system safety and resilience, “material” often refers to the “hardware”, which is different from technology. It includes mechanical equipment and monitoring equipment, materials, safety protection materials, emergency facilities, etc., required for deep foundation pit construction. The material management system provides the necessary material foundation and safety guarantee for deep foundation pit construction and plays a very important role in all stages of construction safety system resilience.
(3)
Technology system
Technology is the “software” element, which is different from material. It includes all kinds of technologies in the construction process, such as support, drainage and precipitation, excavation and slope release, slope protection, and pit monitoring. The technical management system can eliminate the “unsafe state of objects” and “unsafe behavior of human” during DFP construction and provide the necessary safety technology guarantee. The role is especially significant in the early and middle stages of the system’s safety resilience.
(4)
Environmental system
The environmental system contains the construction environment, natural environment, and social environment. The environmental system is the place where energy, information and material are exchanged between the DFPCSS and the outside world, as well as the internal elements, and it is also the carrier guarantee for the smooth operation of each subsystem, which plays a fundamental role in the system safety resilience.
The disaster resistance of DFPCSS refers to the system’s ability to prevent, absorb, and resist adverse effects through the joint operation and synergy of internal subsystems when facing the interference and influence of internal and external disaster-causing factors (Figure 1); to maintain the safe state and basic functional operation of the construction site; to reduce casualties and structural damage losses; and to quickly return to the initial or better safety state until normal construction operations.

3.2. The Construction Process of Resilience Evaluation Index System

Firstly, the key influencing factors of resilience are determined based on the mechanism of typical accidents, the causes of typical accidents, and the process of resilience in accidents. Then, based on industry norms and the research from the literature, the index system was initially constructed. Finally, based on the fuzzy Delphi method, the key evaluation indicators of resilience were screened, and then the resilience evaluation index system was constructed. The construction process is shown in Figure 2.

3.3. The Construction Process of Resilience Evaluation Model

First, the influence relationship between indicators is determined based on the DEMATEL method, and the ANP network structure diagram is constructed. Then, on the basis of expert questionnaire and group discussion, the assignment of the relative dominance of indicators is completed, and the judgment matrix of the dominance of indicators is constructed, and the weights of indicators are determined. Finally, the extended cloud resilience evaluation model is constructed to determine the matter elements of evaluation, evaluation level boundary, membership degree, and security resilience level evaluation to complete the resilience evaluation.

4. Identification of Resilience Influencing Factors and Establishment of Evaluation Index System

4.1. Identification of Resilience Influencing Factors

(1)
Influencing factors identification based on disaster mechanism analysis
A Fault Tree Analysis (FTA) is a top-down deductive failure analysis method that uses Boolean logic to combine lower-order events to analyze undesired states in a system [17]. An FTA is primarily used in the fields of safety engineering and reliability engineering to understand the causes of system failure and to find the best way to reduce risk or to identify the incidence of a safety incident or a specific system failure. In this paper, based on the literature on typical deep foundation pit construction accidents and disasters, a fault tree analysis is conducted to study the disaster process for typical deep foundation pit projects such as slope collapse, water surge, pit bottom uplift, surface cracking, fall from height, and object strike. The key factors of the disaster are identified and sorted out (factor codes a1~a51). For example, the key factors causing slope collapse accidents are as follows: a1, improper excavation method; a2, inadequate slope protection measures; a3, improper slope rate setting; a4, improper drainage; a5, illegal piling on the slope; a6, external load disturbance; a7, inadequate soil investigation; a8, prolonged slope exposure; a9, poor soil bearing capacity; a47, poor personnel safety awareness; and a50, inadequate safety inspection.
(2)
Influencing factors identification based on multi-accident case analysis
According to the statistics of 70 DFP accidents from 1994 to 2021 from the website of the State Administration of Work Safety of China and the official website of the Ministry of Emergency Management of China, 36 typical safety accidents (accident codes A1~A36) are selected according to the research purpose of this paper. The accident causes are summarized based on the accident causation theory, and the factors affecting the resilience level in the process of accidents were identified based on the system resilience theory (factor codes b1~b35).
(1)
Analysis of the influencing factors based on the accident cause theory
The factors identified in the case study (b1~b35) are summarized into four dimensions, namely personnel organization management, material management, technology management, and environment, and the related accidents are listed accordingly (A1~A37). The results are shown in Table 1.
(2)
Influencing factors of resilience based on accident process analysis
Based on the theory of disaster dynamics [18], with reference to the complete description of the accident process in the investigation report of a typical accident case, the factors (c1–c28) affecting the resilience level in the resilience emergence process (prevention absorption, resistance, recovery, and learning adaptation) corresponding to the three stages of disaster conception, disaster formation, and post-disaster are organized, respectively, and the results are shown in Figure 3.

4.2. Construction of the Initial Index System

Taking the four capabilities of prevention absorption (A), resistance (R), recovery (r), and learning (L) adaptation characterized by the process of resilience as the guideline dimensions, Technical Specification for Construction Safety of Deep Foundation Pit Engineering (hereinafter referred to as “Technical Specification”) and the Specification for Construction Project Management (hereinafter referred to as “Management Specification”) are used as references. Combined with the relevant academic papers, the previous screened resilience influencing factors are analyzed, refined, summarized, and categorized through word frequency statistics, and the results of the initial evaluation indexes are shown in Table 2.

4.3. Establishment of Evaluation Index Based on Fuzzy Delphi Method

4.3.1. Overview of Fuzzy Delphi Method

(1)
Theoretical basis
The traditional Delphi method uses a non-meeting method to conduct opinion inquiry, which can make full use of the professional knowledge and experience reserves of the experts under investigation, while still maintaining the relative independence of the feedback questionnaire [27]. However, if the results of the questionnaire do not converge, it needs to be repeated. Survey feedback is very costly and time-consuming. Ishikawa et al. used the triangular fuzzy number to realize the combination of traditional Delphi method and fuzzy theory phase, forming the fuzzy Delphi method. The principle is to use triangular fuzzy numbers to judge the importance of indicators instead of discourse variables, thus transforming the subjective judgments of experts into figurative data values [14]. Referring to the research results of Reference [28] and other scholars, this paper uses the “double triangle fuzzy number method” to optimize the initial indicators.
(2)
Implementation steps
1.
Questionnaire distribution and opinion collection
The evaluation score of this questionnaire is an integer from 0 to 10. The selected research objects are mainly experts and professors in the fields of resilience, safety management, and project management; relevant staff of the quality supervision department of the construction industry, and those with deep foundation pits or building construction. For experienced technical management personnel, a total of 21 questionnaires were distributed in this survey, and 5 invalid questionnaires were excluded for reasons such as missing answers, poor consistency, and failure to answer according to the rules. Finally, 16 valid questionnaires were recovered. Since this method requires about 15 experts, this survey meets the data-capacity requirements.
According to the design of the initial index questionnaire, the surveyed experts scored 0–10 on the basis of “importance degree”. The data were counted according to the three evaluation dimensions of “single value of importance degree D i ”, “most pessimistic assignment of importance degree C i ”, and “most optimistic assignment of importance degree O i ”, and the invalid scoring data with double standard deviation were excluded.
2.
Calculation of double triangular fuzzy numbers
According to the results of data aggregation, the maximum value of “a single value of importance D i ”, the minimum value and geometric mean value of D L i , D U i , and D M i ; the maximum value of “most pessimistic assignment of importance C i ”; the minimum value and geometric mean value of C L i , C U i , and C M i ; the maximum value of “most optimistic assignment of importance O i ”, and the minimum value and geometric mean value of O L i , O U i , and O M i are calculated, respectively. Then the pessimistic assignment triangular fuzzy number, C i = ( C L i , C M i , C U i ) , and optimistic assignment triangular fuzzy number, O i = ( O L i , O M i , O U i ) , are thus established.
3.
Expert opinion convergence judgement
In this study, the convergence of indicators is judged based on the gray zone test, and if the indicators do not converge, it means that there is a difference in the recognition of the importance of the part of the indicators by the experts. When M i Z i > 0 and Z i > 0 , it indicates that the convergence of expert opinions; otherwise, it indicates that the expert opinions are not unified, and a second questionnaire is needed for the second opinion collection. Among them, M i = O M i C M i , and Z i = C U i O L i .
4.
Calculation of expert consensus
When the expert opinion converges, the index should be filtered and eliminated, mainly based on the expert consensus degree value, G i , with G i mainly based on D M i , C M i , and O M i of the geometric mean processing. If G i is larger, the higher the importance of the index, the stronger the relative priority. In order to eliminate the index according to importance, it is necessary to set the threshold value, S i . The calculation method is to process all of the G i geometric averages at a time, and if the consensus value of the index is greater than S i , it is retained; otherwise, it is eliminated, and then the final index evaluation system is constructed. The specific formula is as follows:
G i = D M i C M i D M i 3 S i = G 1 G 2 G 3 G n n

4.3.2. Questionnaire Consultation and Analysis

(1)
First round questionnaire
In addition to evaluating the importance of the primary screening indicators, this questionnaire also invites experts to provide opinions on the rationality of the indicator setting, which mainly includes the definition boundary of the indicator, the name of the indicator, the correlation degree of the indicator, etc.; deletes the indicators lacking rationality; and improves the indicators that need to be modified. According to expert opinion analysis, this questionnaire deleted the initial indicators Ac2, Ac5, Ac12, Ac18, Rc4, and Lc5; modified Ac4, Ac17, rc3, and Lc1; supplemented Rc1; and merged Ac17.
In this paper, SPASSAU was used to analyze the reliability of the questionnaire, and the Cronbach’s coefficient alpha was 0.864, which was greater than 0.7. In addition, by calculating the geometric averages of the three assignments and judging the convergence of the indexes according to the gray zone test method, it is found that seven indexes, namely Ac3, Ac9, Ac10, Ac12, Rc3, rc1, and rc3, do not meet the convergence requirements, thus indicating that there are differences in the recognition of the importance of these indexes by experts. According to the requirements of the fuzzy Delphi method, only when all indicators meet the convergence can the indicators be screened and eliminated according to the consensus degree value and the index system is finally constructed. Therefore, in the second questionnaire, with the exception that the indicator Ac12 is deleted after accepting experts’ opinions, the remaining six indicators need to be collected twice for the same group of experts through the questionnaire.
(2)
Second round questionnaire
The six indicators that did not reach the convergence in the first round of questionnaire were collected through the questionnaire form and combined with the results of the first data analysis, and the opinions of 16 experts were again consulted. Through the feedback of the second questionnaire results and data analysis, in terms of reliability analysis, the Cronbach’s coefficient alpha is 0.821, which is greater than 0.7 to meet the reliability requirements, and the six indicators Z i and M i Z i are greater than 0 to meet the convergence requirements. The consensus value, G i , of all indicators is calculated according to Formula (1) and the geometric average value of all consensus values is calculated to obtain the threshold value, S i , and finally S i = 5.91. Since the consensus values of Ac3, Ac9, rc1, and Lc6 are less than 5.91, they are eliminated.

4.3.3. Construction and Interpretation of Final Index System

Through two rounds of expert questionnaires, based on double triangular fuzzy numbers, the optimization and elimination of indicators were carried out to finally complete the construction of deep foundation pit construction safety system resilience evaluation index system, with 23 indicators in 4 dimensions. According to the meaning of the indexes, they were classified into the corresponding subsystems. We renumbered the final indexes and explained their meanings as shown in Table 3.

5. Construction of Resilience Evaluation Model for DFPCSS

5.1. Determine the Weight of the Resilience Evaluation Index

(1)
Determination of influence relationship among evaluation indexes and construction of ANP network structure diagram
Determine the impact relationship between indicators based on DEMATEL. By judging the degree of mutual influence between the indicators, the interviewed experts used the 0–3 scale method to assign the degree of influence, and the results were arithmetically averaged to obtain the direct impact matrix, T . Standardize T to obtain the normative influence matrix, T * ; use MATLAB software to find the limit of T * ; and multiply and accumulate T * continuously to obtain the comprehensive influence matrix, D . Set the threshold, λ , for the elements in D , and take 1 when the element value is greater than λ ; otherwise, take 0 to construct the reachable matrix, F . Based on the obtained reachability matrix, F , the ANP network structure diagram is constructed.
(2)
Judgment of the matrix construction
The correlation factors were compared in pairs, and based on expert questionnaires and group discussions, the relative dominance of indicators was assigned, and a judgment matrix of 54 indicators of dominance was constructed. The following shows only the judgment matrix of Rc1 under the dimension of preventive absorptivity and rc2 under the dimension of resistance, as shown in Table 4 and Table 5.
(3)
Determination of the index weight
Super Decisions software is used to calculate the related hyper-matrices. The unweighted hyper-matrices weighted hyper-matrices, and limit hyper-matrices are calculated based on the “Unweighted Super Matrix”, “Weighted Super Matrix” and “Limit Matrix” commands, respectively. The column vector of the limit hyper-matrices is the final comprehensive weight of each index. The specific results are shown in Table 6.

5.2. Construction of Extension Cloud Resilience Evaluation Model

(1)
Determine the matter element to be evaluated
Combining the extension theory and cloud theory, the eigenvalue ( E x , E n , H e ) is used to replace the eigenvalue in the traditional matter–element model to construct the cloud matter–element to be evaluated. The main form is shown in Formula (2):
R = ( N , C , V ) = N C 1 V 1 C 2 V 2 C n V n = N C 1 ( E x 1 , E n 1 , H e 1 ) C 2 ( E x 2 , E n 2 , H e 2 ) C n E x n , E n n , H e n
where ( E x i , E n i , H e i ) is the cloud representation of the matter–element eigenvalue, V , to be evaluated.
(2)
Determine the boundary of the evaluation level
Based on the resilience connotation of deep excavations construction safety system, and according to the resilience evaluation indicators screened above, the disaster prevention and disaster relief performance and safety control level of construction site before, during, and after disasters in each accident case are analyzed. On the basis of ensuring the rationality and balance of the grading gradient of the resilience evaluation level, the resilience evaluation level of the safety system is divided into five levels, namely excellent (corresponding Level 1), good (corresponding Level 2), medium (corresponding Level 3), passing (corresponding Level 4), and poor (corresponding Level 5). According to the relevant literature research and expert opinions, the boundary value of the evaluation index grade constructed above is set. Each grade interval contains the corresponding boundary threshold and numerical span, as shown in Table 7.
The hierarchical boundaries of safety system resilience are treated as a dual constraint space c max , c min , and the hierarchical boundary cloud parameters are set according to Formula (3), where S is a constant, which can be fine-tuned according to the actual situation and the dual uncertainty of the corresponding index. This paper takes 0.1:
E x n = c max + c min 2 , E n n = c max c min 6 , H e n = S = 0.1
(3)
Determination of membership and evaluation of safety resilience
1.
Build a comprehensive evaluation matrix
Referring to the operation rules of the normal cloud generator, the score value of each index is regarded as a cloud droplet, and the cloud droplet is calculated according to the three characteristic values ( E x , E n , H e ) obtained by the double-constrained space processing of the previous grades and boundaries, according to Formula (4). For the correlation degree of the resilience evaluation level, the cloud membership degree of each cloud droplet is obtained:
k i l = exp x i E x 2 2 E n 2
In order to reduce the influence of sample randomness on the evaluation results, based on MATLAB programming software, the above calculation steps are repeated N times to take the average value of each index, and finally the comprehensive evaluation matrix, K, is established by summary, as shown in Formula (5):
k = k 11 k 12 k 15 k 21 k 22 k 25 k n 1 k n 2 k n 5
2.
Determination of membership matrix of resilience grade of first-level evaluation index
By weighting the membership degree of the secondary index corresponding to the dimension index in the comprehensive evaluation matrix, K, the membership degree matrix of the dimension index can be obtained (refer to Formula (6)):
M = w 1 l , w 2 l , w 3 l w n l k 11 k 12 k 15 k 21 k 22 k 25 k n 1 k n 2 k n 5 = m 1 1 m 1 2 m 1 3 m 1 4 m 1 5 m 2 1 m 2 2 m 2 3 m 2 4 m 2 5 m 3 1 m 3 2 m 3 3 m 3 4 m 3 5 m 4 1 m 4 2 m 4 3 m 4 4 m 4 5
w n l means the nth secondary index under dimension index l , and m i l represents the membership under dimension index L under resilience level i .
3.
Resilience grade evaluation vector calculation
By weighting the membership degree of the resilience grade of the first-level evaluation index, the evaluation vector, P , of the resilience grade can be obtained, as shown in Formula (7):
P = W 1 , W 2 , W 3 , W 4 M = p 1 , p 2 , p 3 , p 4 , p 5
4.
Determination of the resilience evaluation level
When the resilience evaluation result has a higher membership degree than a resilience grade, it indicates that the actual resilience level matches the grade. According to the calculated resilience grade evaluation vector, the maximum membership degree principle is adopted to judge the resilience membership grade of the deep excavations construction safety system. The specific formula is as follows:
p J = max ( p 1 , p 2 , p 3 , p 4 , p 5 ) Resilience   affiliation   grade   is   J
r = i = 1 5 z i p i i = 1 5 p i , E r x = r 1 ( x ) + r 2 ( x ) + r 3 ( x ) + + r n ( x ) n
where P J is the maximum membership of five evaluation grades of resilience; z i is the score that corresponds to the membership grade, i.e., from the first level to the fifth level are 1~5 points; r is the comprehensive resilience evaluation score; E x r is the expected score for comprehensive resilience evaluation; and r n ( x ) is the comprehensive resilience evaluation score for the first operation.
Combined with the expected value and the subordinate level of the comprehensive evaluation of the resilience of the deep excavations construction safety system, the safety resilience level can be judged.
5.
Reliability test
Since the expected score, E x r , of resilience comprehensive evaluation is the result of multiple calculations, it is necessary to introduce the index reflecting the discrete degree of multiple calculation results and the reliability factor, θ , to test the evaluation results. If the θ value is larger, the credibility is lower. Conversely, if the θ value is smaller, the credibility is higher. Formula (9) shows the specific formula:
E r n = 1 n i = 1 n ( r i ( x ) E r x ) 2

6. Case Study

6.1. Project Overview

The No. 01 civil construction project of the first phase of Metro Line 1 in a Chinese city is located in Tongzhou District and Gangzha District of the city. The main project includes two stations and three sections. There are two groups of wind pavilions and four entrances and exits in the study station, of which the No. 4 entrance and the No. 2 wind pavilion are jointly constructed. According to the overall technical requirements, the excavation depth of the auxiliary foundation pit of the station is 9~12 m, the safety grade of the auxiliary foundation pit is secondary, and the environmental protection grade is secondary. The requirements for the protection level of foundation pit deformation control are the maximum subsidence of the ground is ≤0.2%H, and the maximum horizontal displacement of the enclosure structure is ≤0.3%H.

6.2. Determination of Evaluation Grade Boundary Cloud Parameters

According to the boundary threshold and numerical span of each grade interval, Formula (6) is used to determine the boundary cloud parameters of evaluation grade. Take the evaluation index Ac1, the dimensional index Ac and the total target resilience index as examples and use MATLAB to draw the standard cloud diagram, as shown in Figure 4, Figure 5, Figure 6 and Figure 7.

6.3. Affiliation Calculation

This study refers to the project unit’s construction survey, safety management, emergency response, safety training, daily safety inspection records, and construction monitoring and then asks relevant questions of construction managers and site operators from the perspectives of personnel emergency organization capability, general knowledge of safety avoidance, and post-disaster dispatch and cleanup capability. Combined with expert recommendations and group discussions, the city’s Metro Line 1 Phase I project study stations were scored and evaluated based on the deep foundation pit construction safety system resilience evaluation index system. Then the judging results were weighted average according to the expert level and substituted into the cloud model. Multiple calculations were performed by using MATLAB software to obtain the secondary resilience evaluation index level affiliation. The dimensional index affiliation was obtained by weighting, and the specific results are shown in Table 8.

6.4. Resilience Level Determination and Reliability Test

According to the membership degree of the secondary index, the membership degree of the dimension index is obtained by weighted calculation according to Formula (8). The membership grade is determined according to the principle of maximum membership degree, as shown in Table 9.
According to Formula (8), the dimensional index evaluation level affiliation is weighted to obtain the target resilience evaluation level affiliation: p j = max ( p 1 , p 2 , p 3 , p 4 , p 5 ) = m a x ( 0.0014 , 0.546 , 0.0258 , 0.0088 , 0.0001 ) = p 2 . According to the principle of maximum affiliation, we know that the affiliation level of the resilience target is Level 2, as shown in Table 10.
According to the formula, E x r = 3.5589, E r n = 0.0190, and θ = 0.0054 can be calculated by MATLAB programming. It is generally believed that θ < 0.01 indicates that the results are credible [29]. Therefore, the evaluation results of this paper meet the reliability requirements. Based on the subordinate level of the resilience target and the expectation of the evaluation score, the resilience level of the deep foundation pit project of the first-stage research station of Metro Line 1 in the city is finally determined to be Level 2 (good). After the three eigenvalues of the corresponding evaluation results are returned by the reverse cloud generator, the forward cloud generator is used to generate the cloud picture of the total target resilience evaluation level of the corresponding evaluation results. It can be seen from Figure 4 that the cloud droplet distribution on the normal cloud model is between the second level and the third level, but it is more inclined to the second level. Therefore, it can be explained that the cloud droplet distribution of the normal cloud model and the comprehensive evaluation results of the resilience evaluation results of the deep foundation pit construction safety system of the station are highly consistent.

6.5. Resilience Enhancement Strategies

(1)
Preventive absorption capacity dimension
Attention needs to be paid to the safety training of the whole construction process and conduct post-job education and training for personnel with professional and technical requirements or more dangerous positions before and after entry, explain the consequences of illegal operations, help operators to clarify the safety situation, and improve safety literacy and awareness. The safety monitoring of deep foundation pit should pay attention to the application of intelligent and information technology, build an integrated intelligent monitoring platform and 3D visualization warning mechanism, share the monitoring data in real time, grasp the safety status of the main structure in time and accurately, and provide the basis for emergency management and hazard disposal.
(2)
Resistance dimension
In daily emergency drills, focus on the targeted training of operators’ escape ability to ensure their familiarity with safe escape paths and escape locations and mastery of emergency self-rescue skills is needed. Furthermore, the construction site should improve the resource allocation and investment of emergency equipment and facilities to meet the needs of personnel evacuation.
(3)
Recovery ability dimension
Attention needs to be paid to the post-disaster recovery work and the organizational efficiency of the aftermath measures and the proper handling of the emotional comfort of the operators.
(4)
Learning adaptation ability dimension
Based on the results of the accident investigation and feedback from emergency drills, optimize the deployment of material, machinery, and human resources in a timely manner. Modify ineffective regulations, improve site management organization structure, and make up for omissions and deficiencies in emergency management and resource input. Replace or repair protective equipment and facilities with low applicability and availability in a timely manner and clarify the emergency responsibilities and work content of each management personnel after the accident to meet the needs of emergency management and accident response.

7. Conclusions

With the change of safety management concept and the depth of theoretical research, the Safety-II system safety research paradigm with the concept of resilience as the core provides new ideas for the response to engineering disasters from the perspective of dynamics and development. In order to solve the problem of frequent safety accidents in deep foundation pit construction, it is necessary to establish a construction safety system resilience evaluation index system and evaluation model to evaluate the site safety condition and accident response capability.
Through theoretical and empirical analysis, this paper obtained the following research conclusions:
(1)
The resilience evaluation index system should be based on the key factors affecting the resilience of deep foundation pit construction safety system play process, from the prevention of absorption, resistance, recovery, and learning adaptive capacity four dimensions systematically constructed.
(2)
The evaluation of resilience should consider the objective correlation between evaluation indicators and the randomness and fuzzy characteristics of resilience evaluation itself. Using DEMATEL–ANP to calculate and analyze the relative weights of indicators can better circumvent the limitations and unreasonableness of conventional methods such as AHP. The resilience evaluation based on extension cloud model can better solve the problem of transforming the evaluation index from qualitative to quantitative, and also adapt to the characteristics of resilience evaluation.
(3)
Resistance capability is the most significant capability representation that reflects the level of system resilience and has the highest importance and core degree compared to other dimensions. Therefore, maintaining the basic functions of the system in the face of disaster perturbations is the most critical stage of resilience emergence in the process of accident response; the weighting of prevention and absorption capability is also significant, indicating that successful prevention of safety accidents is a better state expression of the system, and paying attention to pre-safety risk identification can reduce the reliance on resistance and recovery capability in the late stage of accidents; post-disaster recovery and applicability learning capability can achieve internal safety system “evolutionary” enhancement.
Based on the proposed resilience evaluation index system and evaluation model, contractors or government construction safety management departments can evaluate the resilience of the safety systems of different deep foundation pit construction projects, thus providing a basis for ex ante prevention and ex post response to construction accidents.

Author Contributions

Conceptualization, L.S.; methodology, L.S.; software, Z.X.; validation, L.T. and H.G.; formal analysis, L.T. and H.G.; investigation, L.S. and Z.X.; resources, L.S.; data curation, L.S. and Z.X.; writing—original draft preparation, Z.X. and L.T.; writing—review and editing, L.T.; visualization, Z.X.; supervision, L.S.; project administration, L.S.; funding acquisition, L.S. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

The data that support the findings of this study are available from the corresponding author, Lingyi Tang, upon reasonable request.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Heravi, G.; Taherkhani, A.H.; Sobhkhiz, S.; Mashhadi, A.H.; Zahiri-Hashemi, R. Integrating risk management’s best practices to estimate deep excavation projects’ time and cost. Built Environ. Project Asset Manag. 2021, 12, 180–204. [Google Scholar] [CrossRef]
  2. Momeni, E.; Poormoosavian, M.; Tehrani, H.S.; Fakher, A. Reliability analysis and risk assessment of deep excavations using random-set finite element method and event tree technique. Transp. Geotech. 2021, 29, 100560. [Google Scholar] [CrossRef]
  3. Finno, R.J.; Bryson, L.S. Response of Building Adjacent to Stiff Excavation Support System in Soft Clay. J. Perform. Constr. Facil. 2002, 16, 10–20. [Google Scholar] [CrossRef]
  4. Castaldo, P.; Jalayer, F.; Palazzo, B. Probabilistic assessment of groundwater leakage in diaphragm wall joints for deep excavations. Tunn. Undergr. Space Technol. 2018, 71, 531–543. [Google Scholar] [CrossRef]
  5. Singhal, T.K.; Kwon, O.-S.; Bentz, E.C.; Christopoulos, C. Development of a civil infrastructure resilience assessment framework and its application to a nuclear power plant. Struct. Infrastruct. Eng. 2021, 18, 1–14. [Google Scholar] [CrossRef]
  6. Zhu, J.; Manandhar, B.; Truong, J.; Ganapati, N.E.; Pradhananga, N.; Davidson, R.A.; Mostafavi, A. Assessment of Infrastructure Resilience in the 2015 Gorkha, Nepal, Earthquake. Earthq. Spectra 2017, 33, 147–165. [Google Scholar] [CrossRef]
  7. Mottahedi, A.; Sereshki, F.; Ataei, M.; Qarahasanlou, A.N.; Barabadi, A. Resilience estimation of critical infrastructure systems: Application of expert judgment. Reliab. Eng. Syst. Saf. 2021, 215, 107849. [Google Scholar] [CrossRef]
  8. Goldbeck, N.; Angeloudis, P.; Ochieng, W.Y. Resilience assessment for interdependent urban infrastructure systems using dynamic network flow models. Reliab. Eng. Syst. Saf. 2019, 188, 62–79. [Google Scholar] [CrossRef]
  9. Guo, D.; Shan, M.; Owusu, E.K. Resilience Assessment Frameworks of Critical Infrastructures: State-of-the-Art Review. Buildings 2021, 11, 464. [Google Scholar] [CrossRef]
  10. Qiang, W.; Liu, J.; Wang, J.; Wang, P. Evaluation of safety resilience in tunnel construction based on ideal fuzzy matter element. China Saf. Sci. J. 2021, 31, 62–68. [Google Scholar]
  11. He, Z.; Wang, G.; Chen, H.; Zou, Z.; Yan, H.; Liu, L. Measuring the Construction Project Resilience from the Perspective of Employee Behaviors. Buildings 2022, 12, 56. [Google Scholar] [CrossRef]
  12. Zhang, J. Analytical Hierarchy Process Applied to Risk Analysis of Deep Excavation. Adv. Mater. Res. 2011, 250–253, 1646–1650. [Google Scholar] [CrossRef]
  13. Wang, J.; Zhao, F.; Wang, B.; He, X. Resilience evaluation for deep foundation pit of metro under influence of multiple factors. Chin. J. Saf. Sci. 2019, 29, 154–159. [Google Scholar]
  14. Wu, D.; Zhang, M.; Zhang, H.; Wu, L. On of the safety evaluation for the deep foundation pit of the subway stations based on the theory of extenics. J. Saf. Environ. 2019, 19, 761–766. [Google Scholar]
  15. Bo, S. Safety evaluation for deep foundation pit construction in metro station based on DEA-BP neural network. China Saf. Sci. J. 2019, 29, 91–96. [Google Scholar]
  16. Zhou, H.; Zhao, Y.; Shen, Q.; Yang, L.; Cai, H. Risk assessment and management via multi-source information fusion for undersea tunnel construction. Autom. Constr. 2020, 111, 103050. [Google Scholar] [CrossRef]
  17. Garcia Márquez, F.P.; Tobias, A.M.; Pérez, J.M.P.; Papaelias, M. Condition monitoring of wind turbines: Techniques and methods. Renew. Energy 2012, 46, 169–178. [Google Scholar] [CrossRef]
  18. Aerts, J.C.J.H.; Botzen, W.J.; Clarke, K.C.; Cutter, S.L.; Hall, J.W.; Merz, B.; Michel-Kerjan, E.; Mysiak, J.; Surminski, S.; Kunreuther, H. Integrating human behaviour dynamics into flood disaster risk assessment. Nat. Clim. Chang. 2018, 8, 193–199. [Google Scholar] [CrossRef] [Green Version]
  19. Zhao, Y.; Ma, W.; Wen, H. Toughness Evaluation of Tunnel Construction Emergency System. J. Civil Eng. Manag. 2021, 38, 167–172. [Google Scholar]
  20. Zhai, Y.; Wang, T.; Qu, L.; Wang, B.; Wang, K. Rise assessment for the deep foundation pit construction of underground complex based on the IFS-dynamic weighting. J. Saf. Environ. 2021, 21, 1389–1396. [Google Scholar]
  21. Guo, Q.; Hao, Q.; Wang, Y.; Wang, J. Subway System Resilience Evaluation in Based on ANP-Extension Cloud Model. J. Syst. Simul. 2021, 33, 943–950. [Google Scholar]
  22. Zhong, S. Study on Resilience Evaluation of Highway Tunnel Construction System. Master’s Thesis, Chongqing Jiaotong University, Xi’an, China, 2021. [Google Scholar]
  23. Sun, L.; Xie, H.; Xie, H.; Yu, Y.; Chen, Y.; Huang, T.; Lin, D. Influencing factors of engineering construction safety management based on resilience. J. Civil Eng. Manag. 2020, 37, 60–65. [Google Scholar]
  24. Hao, Q. Research on Resilience Evaluation of Safety System in Subway Construction Site. Master’s Thesis, Xi’an Technological University, Xi’an, China, 2019. [Google Scholar]
  25. Bi, W. Resilience Identification and Measurement of Urban Subway Station System to Fire Disaster. Master’s Thesis, Southeast University, Dhaka, Bangladesh, 2020. [Google Scholar]
  26. Zhao, Y. Evaluation Research on Resilience of Safety Management System of Construction Enterprise. Master’s Thesis, Lanzhou Jiaotong University, Lanzhou, China, 2021. [Google Scholar]
  27. Belton, I.; MacDonald, A.; Wright, G.; Hamlin, I. Improving the practical application of the Delphi method in group-based judgment: A six-step prescription for a well-founded and defensible process. Technol. Forecast. Soc. Chang. 2019, 147, 72–82. [Google Scholar] [CrossRef]
  28. Yang, S.; Knoke, D. Social Network Analysis: Methods and Examples; Social Sciences Academic Press: Beijing, China, 2019. [Google Scholar] [CrossRef]
  29. Yankui, L.; Ying, L. Recent advances in robust credibilistic optimization. J. Hebei Univ. Nat. Sci. Ed. 2021, 41, 457–462. [Google Scholar]
Figure 1. Composition and synergy diagram of deep excavations construction safety system.
Figure 1. Composition and synergy diagram of deep excavations construction safety system.
Buildings 12 01922 g001
Figure 2. Construction process of resilience evaluation index system.
Figure 2. Construction process of resilience evaluation index system.
Buildings 12 01922 g002
Figure 3. Impact factors of resilience based on accident process analysis.
Figure 3. Impact factors of resilience based on accident process analysis.
Buildings 12 01922 g003
Figure 4. AC1 index standard cloud chart.
Figure 4. AC1 index standard cloud chart.
Buildings 12 01922 g004
Figure 5. AC index standard cloud chart.
Figure 5. AC index standard cloud chart.
Buildings 12 01922 g005
Figure 6. Standard cloud chart of total target resilience.
Figure 6. Standard cloud chart of total target resilience.
Buildings 12 01922 g006
Figure 7. Cloud chart of overall target resilience evaluation level.
Figure 7. Cloud chart of overall target resilience evaluation level.
Buildings 12 01922 g007
Table 1. Resilience influencing factors based on the causal summary of typical accident cases.
Table 1. Resilience influencing factors based on the causal summary of typical accident cases.
Identify DimensionsIdentify FactorsAssociated Accident
Personnel
organization
management
b1 Security technology disclosure is missingA7/A10/A12/A15/A17/A23/A25/A30/A33
b2 Inadequate safety education and trainingA3/A7/A10/A11/A12/A15/A19/A20/A23/A25/A30
b3 Personnel not qualifiedA8/A14/A15/A22/A23/A30
b4 Personnel security awareness is weakA1/A12/A18/A19/A20/A32
b5 Personnel lack the ability to escape and avoid dangerA20
b6 Poor subcontract managementA7/A8/A10/A11/A22
b7 Inadequate project site safety managementA1/A2/A4/A5/A6/A7/A11/A13/A14/A17/A18/A19/
A20/A31/A35
b8 Unimplemented main security responsibilityA5/A10/A12/A17/A18/A19/A20/A22/A24/A35
b9 Inadequate security supervision inspectionsA2/A3/A4/A6/A7/A8/A10/A11/A12/A13/A17/A18
/A20/A21/A22/A25/A26/A29/A30/A32/A33/A34
b10 Inadequate security officersA7/A10/A17/A19/A22
b11 Lack of attention to potential hazardsA12/A14/A21/A27/A30/A32/A33/A34
b12 Inadequate emergency organizational
management measures
A10/A20/A23
b13 Inadequate management of security
managers
A8/A12/A33
b14 Violating commandA6/A8/A15/A25/A32
Material resource managementb15 Insufficient equipment for fire facilitiesA14/A19
b16 No special ladder is providedA15
b17 Illegal material stackingA2/A4/A7/A15/A28/A34
b18 Construction machinery, vehicle disturbancesA2/A23
b19 No cordon and safety signsA19
Technical managementb20 Inadequate geological environment surveyA1/A15/A16
b21 Irrational design schemeA6/A15/A18/A28/A34/A36
b22 No dynamic design methodologyA1
b23 Information construction not implementedA1
b24 Construction did not follow the design and construction schemeA2/A5/A6/A7/A18/A20/A21/A22/A26/A31/A33/A36
b25 Unreasonable special construction planA6/A23/A30
b26 Improper drainageA5/A11/A34
b27 Improper supporting measures for excavationA5/A6/A9/A12/A15/A17/A20/A21/A23A24/A26
/A27/A34
b28 Illegal excavationA2/A5/A6/A15/A10/A21/A23/A26/A28/A32
b29 Improper slope protection measuresA2/A4/A6/A25
b30 Improper setting of slope rateA2/A4/A9/A15/A16/A29/A32
b31 Inadequate monitoring and early warning measuresA23/A26
b32 Inadequate handling of hazardous source technologiesA10/A25/A33/A34/A36
Environmentb33 Extreme rainfall weatherA3/A5/A11/A13/A22/A23/A29/A32
b34 Inadequate supervision of construction administrative departmentsA2/A7/A13/A15/A16/A22/A23/A32
b35 Poor condition of foundation soilA1/A11/A12/A21/A22/A27/A28/A29/A30/A18
Table 2. Initial resilience evaluation index system of DFPCSS.
Table 2. Initial resilience evaluation index system of DFPCSS.
First-Level IndicatorSecondary Indicator
(Measurement Indicators)
SubsystemIndex SourceIncluding Influencing Factors
Preventive absorptive capacitySurvey of construction
environment Ac1
TechnologyTechnical specifications [2,19]a7/b20
Soil quality of foundation Ac2EnvironmentThe literature [2,20]a9/a25/a27/b35
Rationality of design and
construction scheme Ac3
TechnologyThe literature [1,20]a28/a29/a30/a43/a44/b22/b23/b21/b25
Safe and civilized
construction measures Ac4
Personnel organizationManagement specification The literature [21]a5/a16/a38/b19/b17
Construction behavior
compliance Ac5
TechnologyThe literature [1,22]a20/a46/b24/b14
Surface and ground
drainage measures Ac6
TechnologyTechnical specificationsa4/a10/a26/a33/b26/c6
Earth–rock excavation
measures Ac7
TechnologyTechnical specificationsa1/b28/a2/b29/a3/b30/a6/b18/a8/a11/c4/c2/c5
Supporting structure
construction measures Ac8
TechnologyTechnical specificationsa12/a31/a35/a36/a48/b27/c7
Reinforcement system
construction measures Ac9
TechnologyAccident processc3
Monitoring level of deep
excavations Ac10
TechnologyTechnical specifications
Technical standard
a32/b31
Safety resource input Ac11MaterialThe literature [13,21]a13/b15/a17/a22/a40/b10/a37
The perfection and
implementation of
construction safety
management system Ac12
Personnel organizationThe literature [1,19]a39/a45/b7/b6/b8/a19/b13
Safety supervision and
check Ac13
Personnel organizationTechnical specifications
The literature [21]
a49/a50/a51/b9/c8
Implementation of security
technology disclosure Ac14
TechnologyTechnical specifications
The literature [10,13,23]
b1/c1
Personnel safety awareness and literacy Ac15Personnel organizationThe literature [1]a15/a41/b4/a18/b11/c10
Personnel position
qualification Ac16
Personnel organizationThe literature [1,2,21]a14/a21/b3
Safety publicity and education Ac17Personnel organizationThe literature [1,23]b2
Supervision of construction
industry supervision
departments Ac18
EnvironmentAccident caseb34
Resistance
ability
Hazardous source
disposal measures Rc1
TechnologyTechnical specificationsb32/a23/a34/a42/b33/a24/c9/c13
Availability of emergency supplies Rc2MaterialThe literature [7,19,21]b16
Reasonableness of
emergency management
plan Rc3
Personnel organizationTechnical specifications
The literature [21]
c11/c12/c14/c16/b12
Access to social
firefighting medical
resources Rc4
EnvironmentThe literature [10,21]c15
Emergency management
and control capabilities of managers Rc5
Personnel organizationThe literature [2,10,23,24]/
Personnel escape ability
Rc6
Personnel organizationThe literature [21,25]b5
Recover
ability
Restoring resource-allocation capabilities rc1MaterialThe literature [21,25]/
Psychological recovery of personnel rc2Personnel organizationThe literature [13,24]The literature
Disposal of follow-up
work rc3
Personnel organizationThe literature [10,21]c17/c18
Construction element
redundancy rc4
MaterialThe literature [10,13,25]/
Learning and adapting capabilityIncreased security input
Lc1
MaterialThe literature [1,2,25,26]c27
Accident investigation and experience summary Lc2Personnel organizationThe literature [1,2,13,26]c21/c22
Improvement of safety and
emergency management
system Lc3
Personnel organizationThe literature [13,19]c20/c25
Safety education
training and drills Lc4
Personnel organizationThe literature [10,21]c19
Elimination of security
risks Lc5
Personnel organizationAccident
process
c23/c24/c26
Design and construction
level improvement Lc6
TechnologyThe literature [21]c28/d9
Table 3. Resilience evaluation index system of deep excavations construction safety system.
Table 3. Resilience evaluation index system of deep excavations construction safety system.
DimensionEvaluating IndicatorIndicator MeaningSubsystem
Prevent absorption capacityConstruction environment survey Ac1The ability to investigate the geological and hydrological natural conditions of the area where the deep foundation pit project is located, the layout of the underground water pipe network, and the condition of the surrounding existing buildings.Technique
Surface and ground drainage measures Ac2Power performance of drainage equipment, drainage ditch, dewatering well point arrangement, drainage settings, and reinjection water settings to meet water level control requirements.Technique
Earth–rock excavation measures Ac3Whether earth excavation is strictly prohibited from disorderly and irregular excavation, whether the slope caving rate is reasonable, whether the high slope is graded, and whether effective slope protection measures are taken.Technique
Support structure construction measures Ac4Whether the construction technology and procedure of supporting structure are complied with or not; and whether the control of dip angle, distortion, and displacement meet the requirements of structural stability and safety management.Technique
Monitoring level of deep excavations Ac5Whether the intelligent level of monitoring and data analysis can meet the needs of safety control, whether the monitoring scheme is reasonable, and whether the construction monitoring emergency plan is set up for complex environmental projects.Technique
Safe production protection measures Ac6Whether the safety measures for hazardous work are sound and reasonable.Personnel
Investment in security resources Ac7Resource inputs for on-site safety protection and safety civilized construction facilities, safety equipment for special operators, safety education and training, and emergency drills.Material
Safety supervision and inspection Ac8Supervision on the quality of construction materials and mechanical equipment, the degree of construction behavior norms, the perfection of site safety management mechanism, and the implementation of operational protection measures.Personnel
Implementation of security technology disclosure Ac9Completion of records, completeness of content, and normalization of process.Technique
Personnel safety awareness and literacy Ac10Safety awareness and literacy of field workers.Personnel
Personnel qualification management Ac11Construction management and field worker permits.Personnel
ResistanceTechnical disposal measures of hazard sources Rc1Whether the technical response measures to various emergencies are timely and reasonable.Technique
Availability of emergency supplies and facilities Rc2Emergency materials and facilities meet the emergency management level.Material
Reasonableness of emergency management plan Rc3Degree of emergency management plan meeting emergency control and accident response needs.Personnel
Emergency management and control capabilities of managers Rc4Reasonable evacuation, personnel resources organization and deployment, organization of rescue, and disaster relief work ability.Personnel
Personnel safety aversion and escape ability Rc5The operator’s mastery of emergency escape, protection and self-rescue skills, and the degree of escape possibility given by on-site emergency response.Personnel
Recovery capabilityPsychological recovery ability of the personnel rc1Worker’s ability of panic emotion regulation and stress response mitigation in the late accident period.Personnel
The validity of the aftermath rc2Disposal rate and overall arrangement ability of accident site cleaning, liability compensation, family pension of casualties, implementation of corrective measures, public opinion control, etc.Personnel
Redundancy of construction elements rc3Construction site emergency water supply and power supply facilities, spare construction materials and equipment, spare monitoring and early warning system, and other elements to meet the degree of construction recovery and subsequent safety control.Material
Learning and adapting capabilityOptimization of resource allocation Lc1Whether to improve the allocation of safety resources according to the accident investigation and summary, emergency drill situation.Material
Accident investigation and experience summary Lc2Post-disaster cause investigation, accident-related data collection, experience summary, and reflection on the development of work.Personnel
Improvement of safety and emergency management system Lc3Whether the daily safety management and emergency management deficiencies exposed in accident investigation and daily emergency drills should be effectively corrected and improvedPersonnel
Safety education training and drills Lc4Safety education and emergency drillsPersonnel
Table 4. Judgment matrix based on RC1 index.
Table 4. Judgment matrix based on RC1 index.
Rc1Ac1Ac2Ac3Ac4Ac5Ac9
Ac1132321/2
Ac2 11/211/21/3
Ac3 1211/2
Ac4 11/21/3
Ac5 11/2
Ac9 1
Table 5. Judgment matrix based on rc2 index.
Table 5. Judgment matrix based on rc2 index.
rc2Rc2Rc3Rc4Rc5
Rc21121
Rc3 121
Rc4 11/2
Rc5 1
Table 6. Evaluation index weight of resilience of deep foundation pit construction safety system.
Table 6. Evaluation index weight of resilience of deep foundation pit construction safety system.
Dimension IndexIndicator WeightSecondary IndicatorsIndicator WeightSecondary IndicatorsIndicator Weight
Prevention absorption capacity (Ac)0.296688Construction environment
survey Ac1
0.022060Investment in security
resources Ac7
0.077530
Surface and ground descent and drainage measures Ac20.002329Safety supervision and
inspection Ac8
0.107226
Earthwork excavation measures Ac30.021569Safety technology disclosure and implementation degree Ac90.046752
Construction measures of
supporting structure Ac4
0.002369Personnel safety awareness and literacy Ac100.075051
Monitoring level of deep
foundation pit Ac5
0.029576Post personnel qualification management Ac110.057738
Safety production protection
measures Ac6
0.014683
Resistance resilience (Rc)0.466884Technical disposal measures of hazard sources Rc10.012264Emergency control ability of management personnel Rc40.050809
Availability of emergency supplies and facilities Rc20.038983Personnel safety aversion and escape ability Rc50.034080
Rationality of emergency management plan Rc30.052287
Recovery capability (rc)0.138284Psychological recovery ability of the personnel rc10.019455Redundancy of construction elements rc30.064765
The validity of the aftermath rc20.058015
Learning and adapting capability (Lc)0.098143Optimization of resource allocation Lc10.031171Improvement of safety and emergency management system Lc30.051236
Accident investigation and experience summary Lc20.051921Safety education training and drills Lc40.078132
Table 7. Evaluation grade limit value of resilience index of deep foundation pit construction safety system.
Table 7. Evaluation grade limit value of resilience index of deep foundation pit construction safety system.
Evaluation IndicatorsResilience Evaluation Grade Limits
Level 1 (Excellent)Level 2 (Good)Level 3 (Medium)Level 4 (Pass)Level 5 (Poor)
Construction environment survey Ac1(100,90](90,80](80,70](70,60](60,0]
Surface and ground drainage measures Ac2(100,95](95,85](85,75](75,65](65,0]
Earthwork excavation measures Ac3(100,90](90,80](80,70](70,60](60,0]
Support structure construction measures Ac4(100,90](90,80](80,70](70,60](60,0]
Monitoring level of deep foundation pit Ac5(100,95](95,85](85,75](75,65](65,0]
Safety production protection measures Ac6(100,90](90,80](80,70](70,60](60,0]
Investment in security resources Ac7(100,95](95,85](85,75](75,65](65,0]
Safety supervision and inspection Ac8(100,95](95,85](85,75](75,65](65,0]
Safety technology disclosure and implementation degree Ac9(100,90](90,80](80,70](70,60](60,0]
Personnel safety awareness and literacy Ac10(100,95](95,85](85,75](75,65](65,0]
Post personnel qualification management Ac11(100,95](95,85](85,75](75,65](65,0]
Technical disposal measures of hazard sources Rc1(100,90](90,80](80,70](70,60](60,0]
Availability of emergency supplies facilities Rc2(100,90](90,80](80,70](70,60](60,0]
Rationality of emergency management plan Rc3(100,95](95,85](85,75](75,65](65,0]
Emergency control ability of management personnel Rc4(100,95](95,85](85,75](75,65](65,0]
Personnel escape ability Rc5(100,90](90,80](80,70](70,60](60,0]
Psychological recovery ability of personnel rc1(100,90](90,80](80,70](70,60](60,0]
validity of aftermath rc2(100,95](95,85](85,75](75,65](65,0]
Redundancy of construction elements rc3(100,95](95,85](85,75](75,65](65,0]
Optimization of resource allocation Lc1(100,90](90,80](80,70](70,60](60,0]
Accident investigation and experience summary Lc2(100,95](95,85](85,75](75,65](65,0]
Improvement of safety and emergency management system Lc3(100,95](95,85](85,75](75,65](65,0]
Safety education training and drills Lc4(100,95](95,85](85,75](75,65](65,0]
Table 8. Secondary index grade membership degree of resilience evaluation of deep foundation pit construction safety system.
Table 8. Secondary index grade membership degree of resilience evaluation of deep foundation pit construction safety system.
Evaluation IndicatorsWeightScoreGrade MembershipJudge
Level 1Level 2Level 3Level 4Level 5
Ac10.02206088.340.00050.13790.00000.00000.0000Good
Ac20.00232978.940.00000.00000.81560.00000.0001Medium
Ac30.02156975.690.00000.00000.91720.00000.0000Medium
Ac40.00236983.650.00000.72040.00000.00000.0000Good
Ac50.02957669.350.00000.00000.00000.92660.0031Pass
Ac60.01468374.200.00000.00000.89050.00000.0001Medium
Ac70.07753093.630.00010.09570.00000.00000.0000Good
Ac80.10722695.360.04320.00680.00000.00000.0000Excellent
Ac90.04675281.470.00000.10950.00070.00000.0000Good
Ac100.07505182.210.00000.00000.41360.00000.0000Medium
Ac110.05773890.650.00000.92620.00000.00000.0000Good
Rc10.01226482.370.00000.28970.00010.00000.0000Good
Rc20.03898382.120.00000.22510.00020.00000.0000Good
Rc30.05228787.880.00000.44510.00000.00000.0000Good
Rc40.05080986.390.00000.09810.00090.00000.0000Good
Rc50.03408071.620.00000.00000.12940.00050.0002Medium
rc10.01945584.440.00000.94500.00000.00000.0000Good
rc20.05801589.560.00000.96550.00000.00000.0000Good
rc30.06476585.570.00000.03130.00440.00000.0000Good
Lc10.03117176.310.00000.00000.73300.00000.0000Medium
Lc20.05192188.340.00000.78020.00000.00000.0000Good
Lc30.05123678.940.00000.00000.37940.00000.0002Medium
Lc40.07813275.690.00000.00000.00000.08250.0078Pass
Table 9. Deep foundation pit construction safety system resilience evaluation dimension index grade membership.
Table 9. Deep foundation pit construction safety system resilience evaluation dimension index grade membership.
Dimension IndicatorsWeightDimension Index Resilience Evaluation Grade MembershipJudge
Level 1Level 2Level 3Level 4Level 5
Ac0.2966880.00460.07140.06590.02740.0001Good
Rc0.4668840.00000.04050.00450.00000.0000Good
rc0.1382840.00000.07640.00030.00000.0000Good
Lc0.0981430.00000.04050.04240.00650.0006Medium
Table 10. Membership degree of overall objective resilience evaluation grade.
Table 10. Membership degree of overall objective resilience evaluation grade.
IndicatorsTotal Target Resilience Evaluation Grade MembershipJudge
Level 1Level 2Level 3Level 4Level 5
Total target0.00140.05460.02580.00880.0001Good
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Shen, L.; Xue, Z.; Tang, L.; Ge, H. Research on Resilience Evaluation and Enhancement of Deep Foundation Pit Construction Safety System. Buildings 2022, 12, 1922. https://doi.org/10.3390/buildings12111922

AMA Style

Shen L, Xue Z, Tang L, Ge H. Research on Resilience Evaluation and Enhancement of Deep Foundation Pit Construction Safety System. Buildings. 2022; 12(11):1922. https://doi.org/10.3390/buildings12111922

Chicago/Turabian Style

Shen, Ling, Zhijian Xue, Lingyi Tang, and Hongyan Ge. 2022. "Research on Resilience Evaluation and Enhancement of Deep Foundation Pit Construction Safety System" Buildings 12, no. 11: 1922. https://doi.org/10.3390/buildings12111922

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.