Double-Cycling AGV Scheduling Considering Uncertain Crane Operational Time at Container Terminals

1
College of Computer Science and Engineering, Shandong University of Science and Technology, Qingdao 266590, China
2
Qingdao New Qianwan Container Terminal Company Ltd., Qingdao 266500, China
*
Author to whom correspondence should be addressed.
Appl. Sci. 2022, 12(10), 4820; https://doi.org/10.3390/app12104820
Submission received: 1 April 2022 / Revised: 5 May 2022 / Accepted: 5 May 2022 / Published: 10 May 2022

Abstract

:
Container terminals (CTs) play an important role in the modern logistics and transportation industry. The utilization of automated guided vehicles (AGVs) can be effectively facilitated by reducing their empty running. The existing strategies cannot guarantee the full load of AGVs during their transportation because of the complex constraints of container scheduling. This work proposes a double-cycling AGV scheduling model that ensures a full load of AGVs between the quayside and the yard. The objective is to minimize the total waiting time of AGVs and ensure a high loading rate of AGVs by scheduling loading/unloading containers. Furthermore, it takes the randomness of the quay crane’s operational time into consideration. By assigning a time interval to AGVs’ arrival at a quayside, a container scheduling sequence is obtained based on a Hybrid Particle Swarm Optimization (HPSO) algorithm with a penalty function. Via experiments, it shows that the proposed model can obtain the least number of AGVs for container transportation, minimize AGVs’ total waiting time, and ensure the high loading rate of AGVs.

1. Introduction

Maritime transportation plays a vital role in the global economy, trade, and cultural exchanges as a basic logistic mode. Container terminals (CTs) were developed as one of the most critical components in logistic transportation systems. CTs consist of three major facilities: quay cranes (QCs), yard cranes (YCs), and automated guided vehicles (AGVs). AGVs cooperate with QC and YC operations. Effective task scheduling of AGVs is the key to reducing the operating cost of CTs. In the terminal’s traditional transportation mode, it is essential to ensure the working efficiency of the quay crane. Most terminals use more AGVs to avoid waiting for the quay crane. However, this will increase the waiting time of AGVs, thus reducing their utilization rate. Furthermore, the complex constraints among quay cranes, yard cranes, and AGVs further deteriorate the utilization of AGVs.
Many studies focused on the real-time scheduling of AGVs over the past few decades. For example, Mohammad and Saeed proposed a mathematical model composed of a job shop scheduling problem and a conflict-free routing problem [1]. The objective was to minimize AGVs’ delay time and achieve multi-AGV integrated scheduling. A two-stage ant colony algorithm was proposed to solve it. Angeloudis and Bell studied job assignments of AGVs in CTs under various uncertainty conditions [2]. A flexible algorithm for real-time AGV scheduling was proposed. Luo et al. designed an algorithm to prevent AGVs from collisions based on labeled Petri nets [3]. Ji et al. studied the combinatorial optimization of two problems in the synchronous loading and unloading operation mode of the automated container terminal. They designed two bi-level optimization algorithms based on a conflict resolution strategy [4]. Wang and Zeng investigated the AGV dispatching and routing problem with multiple bidirectional paths to generate conflict-free routes. A mixed-integer programming model was formulated to minimize the completion time of all jobs. A tailored branch-and-bound algorithm was developed to solve the problem [5]. Zhong et al. studied a conflict-free AGV path planning problem and rail-mounted gantry crane scheduling problem [6].
In terms of AGVs’ offline path planning, Graziana et al. showed how timed Petri nets can be efficiently used to solve problems related to resource planning in intermodal freight transport terminals. They considered a real case study and simulated it based on the timed Petri net model of the terminal [7]. Rashidi and Tsang formulated an AGV scheduling problem as a least-cost flow model [8]. They proposed an extended Network Simplex Algorithm (NSA+). Hu et al. analyzed a container-cluster operation and an optimal scheduling strategy of the yard truck [9]. A multi-objective mathematical programming model was established and then solved by a genetic algorithm. Niu et al. proposed a cooperative strategy for scheduling trucks to minimize the total delay time of requests and the travel time of yard trucks [10]. They applied a particle swarm optimization algorithm to solve the problem. The studies, as mentioned above, significantly improved the utilization of AGVs and the operational efficiency of CTs, but they cannot guarantee a full load and ensure the least total waiting time of AGVs during their transportation. Hence, we propose a double-cycling AGV route planning model in this work to maximize the loading rate and minimize the waiting time of AGVs during their transportation.
In CTs, AGVs cooperate with the working of QCs and YCs. The work efficiency of QCs directly affects the berth time, which is also an important research topic. Many studies focused on an efficient quay crane scheduling problem (QCSP) under various complex conditions. Huang and Li proposed a bounded two-level dynamic programming algorithm aiming at a QCSP [11]. A method was proposed to evaluate the practicability of the algorithm. Ji et al. considered optimizing a loading sequence in CTs [12]. A model was established to integrate the loading sequence and a rehandling strategy under parallel operations of multi-quay cranes. An improved genetic algorithm was proposed to solve the model. Zhang and Kim attempted to minimize the operational cycle time of a QC for unloading and loading containers in a ship bay [13]. They formulated a QCSP as a mixed-integer programming model and solved it using a hybrid heuristic approach. Nguyen and Kim compared various pooling strategies for constructing the pool [14]. Heuristic algorithms were evaluated in terms of the total delay time of QC operations and the total travel distance of AGVs. Zhen et al. studied an integrated optimization QCSP and yard truck scheduling problem (YTSP) in CTs [15]. A mixed-integer programming model was formulated and solved by a particle swarm optimization-based method. Zhang et al. extended the QCSP by considering the stability of containers and proposed a QCSP with stability constraints [16]. A bi-criteria evolutionary algorithm was proposed to solve it. Most of the above QC scheduling methods fail to consider the impact of uncertain factors, especially the tide fluctuation and manual operation, on QC transportation tasks, with a few exceptions (Zhen, 2014 [17]; Sheikholeslami and Ilati, 2018 [18]). Uncertainties can be good or bad for a transportation system (Wang and Wu, 2021 [19]), and we analyze uncertainties in our model.
The dispatch of YCs is another crucial part of CTs. Most researchers combine the scheduling of YCs and AGVs to formulate the model closer to reality. Zheng et al. investigated single YC scheduling to minimize the total tardiness of tasks and focus on the case with uncertain release times of retrieval tasks [20]. A two-stage stochastic programming model was proposed, and a genetic algorithm and a rule-based heuristic were developed to solve it, especially for large-scale instances. Ng and Mak studied the scheduling of a YC to perform a given set of loading and unloading tasks with different ready times, which minimizes the sum of the task waiting time [21]. A branch and bound algorithm was proposed to solve it. Some studies focus on a yard crane scheduling problem (YCSP) under various conditions. Javanshir et al. studied a YCSP among different blocks in CTs to minimize cranes’ total travel time and the total delayed workload [22]. It was formulated as a mixed-integer programming model and solved by a branch-bound method. He et al. addressed a YCSP with the uncertainty about the vessels’ arrival time and volumes [23]. It optimized the total delay to the estimated ending time of all task groups based on a genetic algorithm-based framework combined with a three-stage algorithm.
In CTs, a double-cycling scheduling model of QCs and YCs requires that a crane transports a container, unloads it, and returns by taking another container. Meanwhile, AGVs transport a container to its destination and bring another one back. At present, double-cycling strategies are used in QCSP, YCSP, YTSP, and sequencing the loading of the container (i.e., Container Sequencing Problem, CSP, which refers to sequencing the loading/unloading of the container in the yard [24]), as shown in Table 1. Most of these studies considering a double-cycling scheduling mode do not specifically consider the uncertainty of QC operation. Most of these studies do not obtain specific AGV scheduling, including which containers should be transported by each AGV and the sequence of transporting these containers by an AGV. In this work, a double-cycling model is proposed to realize the full load of AGVs by scheduling loading/unloading containers to minimize the waiting time of the AGVs. A hybrid particle swarm optimization (HPSO) algorithm with a penalty function is used to solve this issue.
The rest of this paper is organized as follows. Section 2 describes a double-cycling model and proposes a container scheduling sequence based on an HPSO algorithm. Section 3 shows experimental results. Section 4 concludes this paper and discusses the future work.

2. Materials and Methods

2.1. AGV Double-Cycling

This section describes the double-cycling model. Relevant assumptions are made for QC, AGV, and YC. The related constraints are given.

2.1.1. Problem Description

In a CT, QCs, YCs, and AGVs are, respectively, responsible for loading/unloading containers on ships, loading/unloading containers in the yard, and transporting containers between the quayside and the yard. This work proposes a double-cycling scheduling model. An AGV carries a container at the quayside, drives to the yard to unload it, takes another one from the yard, and returns to the quayside for unloading. Such a process is repeated to finish the handling of containers at CTs. First, we present the following assumptions:
1)
Two QCs are used for loading and unloading containers on ships. One is responsible for loading containers from an AGV to a vessel, and another QC is responsible for unloading containers from a vessel to an AGV. After unloading at the first QC, AGVs run empty to the other QC for loading and finally drive to the yard. After unloading at the yard, AGVs run to the next yard for loading and eventually go to the quayside. Notice that more QCs can be divided into several pairs.
2)
Tidal fluctuation and other factors will cause ship instability, resulting in QC operations not being fully automated. At present, most QC operations need manual assistance, resulting in the uncertainty of QC operation time. Etsuko mentions that the QC operation time roughly conforms to Gaussian distribution [34]. The probability is that the distributed value in (μ − 2σ, μ + 2σ) is 0.9544, so we assume that QC completes the transportation of containers within the time (t + μ − 2σ, t + μ + 2σ), where t is the QC operation time.
3)
AGVs travel at a uniform speed during their transportation.
4)
When transporting a container, the YC and the YC’s spreader are required to reach the position of the container. To save time, YC can be prepared before the arrival of an AGV [35], adopted in our work.
We set up two fixed bays on the ship for storing containers that need to be unloaded and loaded, respectively. Notice that more bays can be divided into several pairs. AGVs are fully loaded in and out of the yard and quayside, thus realizing the double-cycling of AGVs. It is the basic constraint of the model. Figure 1 show the flow chart of this work.
The second constraint is that no delay of QCs should be guaranteed. QC operational uncertainty leads to an uncertain time when an AGV arrives at the quayside. The latest time required for an AGV to arrive at the quayside (LTQ) is considered. Because the time of QC transporting containers conforms to the Gaussian distribution with parameters (μ, σ2), LTQ is the moment when the QC finishes the transportation of the previous container.
To make the algorithm and model more concise, we chose task points to represent the transport of containers. A task point represents a container with its current position and destination information. We give a detailed definition of the task point in Section 2.1.2.

2.1.2. Mathematical Model

Let N = {1, 2, … } represent the set of natural numbers, and Nm= {1, 2, …, m}. The related symbols and decision variables are defined as follows in Table 2, Table 3 and Table 4.
The double-cycling model considers not only the efficiency of the QC but also the waiting time of AGV. The objective function is the shortest waiting time for AGVs:
min 1 l T g
where Tg is the waiting time of ag.
The constraints are defined as follows:
χ i j = 1 ,               M i M + m e
χ i j = 1 ,               M i M + m b
χ x x = 0 ,             M x , M x X
χ y y = 0 ,             M y , M y Y
α k = 1 ,   k N m
β k = 1 ,   k N m
C 1 i = μ 2 σ + V Q / D i q + Δ t i
C 2 i = μ + 2 σ + V Q / D i q + Δ t i
C 1 i   <   T i q <   C 2 i
T i l =     D i 1 0 Y V Y + T G     ,     γ i w = 0 T G                                       ,     γ i w = 1
T i u l =   m a x D i 1 i Y V Y , D i 1 i y V y + 2 d i G y + max D i 0 Y V Y , D i 0 y V y + T G ,   γ i w = 0                                         T G                                                                                                                                 ,     γ i w = 1
T i = 0 i 2 T k q + C 2 i 1   ,     δ i = 1
T j i = T j q + D i q V Q  
T i q 1 = T i 1 q 1 + T i 1 q + D i q V Q
T i q 2 = T i 1 q 2 + T i 1 q + D i q V Q
T i 1 = 0                                                                                                                     , γ i w = 1                                 max T i 1 3 + T i 1 4 T , 0                                   , ε w i 1 = 1 , γ i w = 0 max T i 1 1 + T i 1 2 + D i 1 0 Y V y T , 0 , ε w i 1 = 0 , γ i w = 0
T i 2 = T G                                                                                                                     , γ i w = 1 T G                                                                                 , ε w i 1 = 1 , γ i w = 0 m a x D i 1 0 Y V Y , D i 1 0 y V y + T G , ε w i 1 = 0 , γ i w = 0
T i 3 = max D 0 i 1 Y V Y , D 0 i 1 y V y + d i G y + T G                                   , ϵ = 1 H i i 1                                                                                           , γ i w = 1 , ϵ = 0 max T j 3 + T j 4 P i j , 0 , ε w j = 1 , γ i w = 0 , ϵ = 0 max T j 1 + T j 2 P i j , 0 , ε w j = 0 , γ i w = 0 , ϵ = 0
T i 4 = m a x D i 1 i Y V Y , D i 1 i y V y + 2 d i G y + max D i 0 Y V Y , D i 0 y V y + T G                                       , ϵ = 1 T G                                                                                                                                                                                 , γ i w = 1 , ϵ = 0 max D 0 i Y V Y , D 0 i y V y + 2 d i G y + max D i 0 Y V Y , D i 0 y V y + T G , ε w j = 1 , γ i w = 0 , ϵ = 0 max D j i Y V Y , D j i y V y + 2 d i G y + max D i 0 Y V Y , D i 0 y V y + T G , ε w j = 0 , γ i w = 0 , ϵ = 0
Equations (2)–(5) describe the container transportation mode at CTs, where (2) denotes that all task points, including the virtual end task point, have only one prefix task point; (3) shows that all task points, including the virtual, begin task point, have only one suffix task point; and (4) indicates that all the unloading task points’ prefixes and suffixes are not unloading task points. Equation (5) suggests that all loading task points’ prefixes and suffixes are not loading task points. Equations (6) and (7) describe the double-cycling mode, indicating that all AGVs driving out of the yard and the quayside must be fully loaded, respectively. Equations (8) and (9) describe the minimum and maximum time for QC to transport container i. The minimum time is the average time needed by the QC transporting container i minus a time-interval conforming to the Gaussian distribution. The maximum time is the average time needed by the QC transporting container i plus a time-interval conforming to the Gaussian distribution. Equation (10) describes the uncertainty of the QC operation, indicating that no matter the loading operation or unloading operation, the QC completes the transportation of container i within the time interval [ C 1 i , C 2 i ]. Equations (11) and (12) describe the loading time and unloading time of a container in the yard. Equation (11) represents the loading time of a container: 1) if the YC cannot be prepared in advance, the YC must move from the position of the previous container to the I/O point to transport the container. Thus, the loading time of a container is the summation of the time that the YC moves to the I/O point plus the time that the spreader transports a container; and 2) if the YC can be prepared in advance, the loading time of a container is the time needed by the spreader transporting a container. Equation (12) represents the unloading time of a container: 1) if the YC cannot be prepared in advance, the YC moves from the position of the previous container to the position of the target container. Thus, the unloading time of a container is the total time needed by YC reaching the target container, the spreader grabbing the container, the YC moving to the I/O point, and the spreader transporting a container at the I/O point; 2) if the YC can be prepared in advance, the unloading time of a container is the time needed by the spreader transporting a container. Equation (13) describes LTQ. For container i, LTQ is the moment when the QC completes transporting container i − 1. Equations (14) and (15) describe the situation of AGVs entering and leaving the quayside. Equation (14) indicates the time span between two consecutive AGVs driving out of the quayside. The time interval is the loading time of the second AGV in the quayside. Equation (15) indicates the waiting time before task point i is unloaded at the quayside. The waiting time is the previous task point’s waiting time before unloading plus the unloading time of the previous task point. Equation (16) indicates the waiting time before task point i is loaded at the quayside. The waiting time is the previous task point’s waiting time plus the previous task point’s loading time. Equations (17)–(20) describe the situation of AGVs entering and leaving the yard. Equation (17) indicates the waiting time of task point i before it is unloaded in the yard. It describes two cases: 1) if the YC can be prepared in advance, the waiting time is 0; 2) if the YC cannot be prepared in advance, there are two situations: if the YC is loading a container, the waiting time is the previous task point’s waiting time plus the previous task point’s loading time minus the time interval between two consecutive AGVs driving out of the quayside. If the YC is unloading a container, the waiting time is the previous task point’s waiting time plus the previous task point’s unloading time minus the time interval from the arrival at the yard at the previous task point. Equation (18) depicts the time taken for task point i to be unloaded in the yard. Specifically, 1) if the YC can be prepared in advance, the unloading time is the time needed by the spreader transporting a container at the I/O point; 2) if the YC cannot be prepared in advance, there are two situations. If the YC’s previous operation is a loading operation, the YC stops at the I/O point after transportation, and the unloading time is the time the spreader transports the container. If the YC’s previous operation is an unloading operation, the unloading time is the time needed by YC moving to the I/O point plus the spreader transporting a container at the I/O point. Equation (19) describes the waiting time before task point i is loaded in the yard. Specifically, 1) if AGVs are loaded in the same yard, the waiting time is the time needed by YC moving to the I/O point after the unloading; 2) if the AGVs are loaded in another yard, there are two situations. When the next target yard’s YC can be prepared in advance, the waiting time is the time needed by the AGV running empty to the target yard. When the next target yard’s YC cannot be prepared in advance, there are also two situations: if the YC is loading a container, the waiting time is the previous task point’s waiting time plus the task point’s loading time minus the empty running time of AGV; if the YC is unloading a container, the waiting time is the previous task point’s waiting time plus the previous task point’s unloading time minus the empty running time of the AGV. Equation (20) depicts the time taken for task point i to be loaded in the yard. Specifically, 1) if the AGV is loaded in the same yard after unloading, the loading time is the time needed by the YC moving to the position of the container and transporting it, the YC moving to the I/O point, and the spreader transporting a container at the I/O point; 2) if the AGV needs to be loaded in other yards after unloading, there are two situations. If the YC can be prepared in advance, the loading time is the time needed by the spreader transporting a container at the I/O point. If the YC cannot be prepared in advance, there are two situations. If the YC is loading a container, the loading time is the time needed by the YC to move to the position of the target container and transport it. If the YC is unloading a container, the loading time is the time needed by the YC moving to the target container and transporting it, the YC moving to the I/O point, and the spreader transporting a container at the I/O point.

2.2. HPSO Algorithm with Penalty Function

This paper aims to find an appropriate container scheduling sequence. It minimizes the total waiting time of AGVs and satisfies the double-cycling constraint and the LTQ constraint. Obviously, it is an NP-hard problem. Hence, we propose a hybrid particle swarm optimization (HPSO) algorithm with a penalty function. According to the traditional particle swarm optimization (PSO) algorithm, HPSO updates particle position by tracking the extreme value. It introduces crossover and mutation operations. The HPSO algorithm searches for the optimal solution using crossover, global crossover, and mutation operations [36].

2.2.1. Individual Coding

The algorithm adopts a single chromosome encoding method. Each particle includes a coding scheme. First, Z denotes a set of segmentation numbers, |Z| = l − 1, where |Z| represents the number of elements in set Z. A chromosome is denoted as S = <x1, …, xi, …, y1, , yj, …, z1, , zo>, where x1xiX are the indexes of unloading task points, y1yjY are the indexes of loading task points, and z1zoZ are the segmentation numbers. The segmentation numbers are used to segment the chromosome to obtain scheduling sequences of AGVs.
For example, we assume that an unloading task point set is {x1, x2, x3, x4, x5}, a loading task points set is {y1, y2, y3, y4, y5}, and a segmentation number set is {z1, z2, z3}. The chromosome is S = <x1, x2, x3, x4, x5, y1, y2, y3, y4, y5, z1, z2, z3>. The three segmentation numbers divide the chromosome into four parts, as shown in Figure 2. Each part represents a scheduling sequence of an AGV, denoted by S1S4, respectively. S1’s scheduling sequence is <x4, y2>, S2’s scheduling sequence is <x5, y4>, S3’s scheduling sequence is <x1, y1, x3, y3>, and S4’s scheduling sequence is <x2, y5>. The AGVs’ scheduling sequence is shown in Figure 3.

2.2.2. Particle Fitness

The particle fitness is denoted by P. A penalty function is used to calculate P for searching for the problem’s optimal solution. We have:
P = a P q + T   ,   k = 0 k P u   , k > 0
where k represents the number of task points that do not conform to double-cycling, a represents the number of task points that do not conform to LTQ, Pq denotes a penalty coefficient for the LTQ, and Pu denotes a penalty coefficient for the double-cycling.
Particle fitness P includes 1) all AGVs’ waiting time and 2) the penalty value of task points in the scheduling sequence that do not conform to the LTQ. A solution may not meet the basic constraint of double-cycling, so before calculating P, the scheduling sequence should be judged whether it meets the basic constraint of double-cycling. If not, the particle fitness P is adjusted to the kPu. The smaller the particle fitness, the better the scheduling sequence. We present an algorithm to solve the double-cycling model based on the HPSO algorithm in Algorithm 1. A flow chart of the algorithm is shown in Figure 4.
Algorithm 1 AGV double-cycling algorithm
Procedure HPSO
Input: Unloading task point set X, loading task point set Y, AGV number l, population size q, maximum iteration number tmax, the LTQ penalty coefficient Pq, the double-cycling penalty coefficient is Pu, particle fitness P, personal best position pBest, and global best particle gBest.
Output:gBest
for each particle i
 Randomly Initialize a coding scheme Si for particle i
 Calculate the fitness of particle i and set pBesti = Si
end for
gBest = min {pBesti}
while t < tmax
  for I = 1 to q
   Perform individual crossover, global crossover, and mutation operations to update the coding scheme of particle i
   Calculate the fitness of particle i 
   if fitness (Si) < fitness (pBesti)
   pBesti = Si;
   if fitness (pBesti) < fitness (gBest)
   gBest = pBesti;
  end for
  t = t + 1;
end while
 print gBest
end procedure

3. Results

Matlab_R2019a was used to solve the double-cycling model. First, we randomly generated a container scheduling sequence. In this work, a queue was formulated for each QC or YC. The task points were arranged in queues according to the container’s transportation order of the container scheduling sequence. The waiting time of the task points and the number of task points that did not meet the LTQ were calculated according to the relationship among the task points in the queue. Then, the scheduling sequence with the least number of task points that did not meet the LTQ and the least AGV waiting time were obtained using an HPSO algorithm. We then analyzed some critical parameters.
Corresponding waiting areas were set up at the quayside and the yard for storing AGVs that needed to wait. AGVs in the waiting area could turn off the engine or keep the engine on for waiting according to the estimated waiting time. The waiting time of the AGV that remained after starting the engine was a key to be considered in the double-cycling model. Table 5 show the data obtained in Qingdao Port from our field investigation.
Table 6 show experimental results considering the total waiting time of the AGVs (Total Waiting Time), the number of task points that did not conform to LTQ (Not-Conform LTQ), the number of task points that did not conform to double-cycling (Not-Conform Double-cycling), and the fitness value.
First, a time disturbance that conformed to the Gaussian distribution was added to the QC operation time. We randomized the assignment according to the Gaussian distribution, so the results were not the same each time. In the double-cycling model, the experimental results showed that most scheduling sequences satisfy both double-cycling and LTQ. This work simulated the time disturbance existing in the QC operation, so a few experimental results failed to satisfy LTQ at all task points on the basic constraint of double-cycling. The number of task points that did not conform to LTQ was significantly higher in the last experiment than in other experiments. This situation was generally caused by the significant difference in the QC operation time in the last experiment and other experiments’ QC operation time, resulting in a severe phenomenon of AGV delays. The QC operator caused the time disturbance of QC operating time. Therefore, we think that the AGV could not reach the quayside in time due to the operator’s operation error. This part of the data should be discarded or recalculated. However, according to the experimental results in Table 6, there exists the phenomenon that some AGVs’ scheduling sequence was empty in the optimal scheduling sequence, which led to resource waste. To further improve the efficiency of the double-cycling system, this work continued to consider the influence of the number of AGVs on the efficiency of the double-cycling system. Table 7, Table 8, Table 9, Table 10 and Table 11 show the experimental results of changing the number of AGVs under a different number of task points on the base constraint of double-cycling, including the total waiting time of AGV and the number of task points that do not conform to LTQ. We selected three experimental results for each number of AGVs.
For the different number of task points, we set different numbers of AGVs to transport them. The number of AGVs was gradually reduced until the constraint of conforming to LTQ could not be satisfied at all task points in most experiments, and the number of AGVs was set as the lower bound to transport the number of task points successfully. The number of AGVs was gradually increased until some AGVs’ scheduling sequence was still empty in most experiments, and the number of AGVs was set as the upper bound under the number of task points. Table 7, Table 8, Table 9, Table 10 and Table 11 show that for different numbers of task points, there was a corresponding number of AGVs to ensure that all task points met LTQ and had the minimum waiting time. For the number of task points in Table 7, Table 8, Table 9, Table 10 and Table 11, the appropriate AGVs were 3, 4, 5, 5, and 6, respectively. Too few AGVs will increase the number of task points that do not conform to LTQ, and too many AGVs will result in an increase in the waiting time of AGVs. Therefore, only an appropriate number of AGVs can improve the efficiency of the double-cycling model and make full use of transportation resources. In the real world, we can deal with containers on a ship layer by layer to break down a significant problem into more minor ones, and our model can then be applied. As mentioned above, the time disturbance of QC operation obeys different Gaussian distributions. This work discusses the influence of QC operations conforming to different Gaussian distribution models on the double-cycling system. Table 12 show the experimental results under different Gaussian distributions with 30 task points and five AGVs.
The smaller the μ and σ mean QC operator’s operation experience more affluent, and the smaller the time disturbance of the QC operation is. When μ = 4, σ = 4, the AGV’s waiting time fluctuates around 1814 s, with almost no QC delay. With the increase of μ and σ, the AGV waiting time fluctuates, and the QC delay becomes more and more frequent. The rise of σ leads to the increase of the time disturbance of QC operation, resulting in the AGV waiting time and the number of task points that do not conform to LTQ fluctuating significantly. The increase of μ postpones the time disturbance interval of QC operation, resulting in the AGV waiting time being longer. The experimental results show that the more experienced the QC operator is, the lower the AGV waiting time and QC delay times.
According to the model presented and relevant experimental results in this work, as long as the information of the task points set can be obtained, the iterative calculation of the task points set can be carried out in advance. The optimal container scheduling sequence is selected by adjusting the relevant factors, which proves the feasibility of the double-cycling model in practical situations. In the real world, we only need to consider the top layer of containers in the ship to break down the large problem into several small sub-problems. The sizes of the experiments conform to the real situation.
To ensure that the HPSO algorithm is excellent, the Simulated Annealing (SA) algorithm and Genetic Algorithm (GA) are designed for comparison in this work. It assumes that the success rate is S and the total number of experiments is E, where the number of successfully obtaining scheduling sequences that satisfy both LTQ and double-cycling constraints is e. The algorithm’s success rate is:
S = e E × 100 %
Table 13, Table 14 and Table 15 show that the three algorithms are compared with the success rate under the different number of task points and the success rate under the different numbers of μ and σ. Table 15 show the average execution time of the algorithm under the different number of task points.
Table 13 show that HPSO has the highest success rate in obtaining effective solutions. Table 14 show that HPSO has the most stable performance under different time disturbances. Table 15 show the HPSO algorithm takes the least time.
Meanwhile, Table 13, Table 14 and Table 15 show when the values of the μ and σ are small, the success rate is high. With the increase of the values of μ and σ, the algorithms’ success rate gradually declines, and the average execution time of the algorithms is more extended. Only the HPSO algorithm maintains a 90% success rate and a short average execution time. The reason for this result is the uncertainty of the QC operation. If the number of task points or the value of μ and σ increases, the transportation uncertainty on the quayside increases, resulting in an increasing number of task point sequences that cannot satisfy LTQ and double-cycling constraints.

4. Conclusions

To improve the utilization rate of AGVs in the process of CTs, this work proposes a double-cycling AGV scheduling model, which specifies that AGVs should enter and exit the yard and quayside with the full load during transportation. It reduces the empty running and minimizes the total waiting time of AGVs. The uncertainty of QC’s operation time is also considered. The container scheduling sequence is obtained by arranging the loading and unloading of containers based on the HPSO algorithm with a penalty function. The double-cycling mode can be adopted whenever containers need to be loaded and unloaded simultaneously. If the numbers of loading task points and unloading task points are not equal, we can choose some of the task points and use the double-cycling mode. We can adopt a multi-QC transportation mode for other complicated cases, and the QCs are divided into groups by the divide-and-conquer strategy. Each group has two quayside cranes for loading and unloading, respectively. The proposed model and algorithm are still key to realizing double cycling. More heuristic algorithms [37,38,39,40,41,42,43,44,45,46,47] will be used to solve the proposed problem in our future work.

Author Contributions

Conceptualization, H.Z. and L.Q.; methodology, H.Z.; software, H.Z.; validation, H.Z., L.Q. and W.L.; formal analysis, H.Z.; investigation, H.Z.; resources, W.L.; data curation, H.Z.; writing—original draft preparation, H.Z.; writing—review and editing, L.Q.; visualization, H.Z.; supervision, L.Q.; project administration, H.M.; funding acquisition, L.Q. All authors have read and agreed to the published version of the manuscript.

Funding

This work was supported in part by the National Natural Science Foundation of China under Grant 61903229, in part by the Natural Science Foundation of Shandong Province under Grants ZR2019BF004 and ZR2019BF0041, and in part by Jingying Program of Shandong University of Science and Technology under Grant skr19-D-049.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Not applicable.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Saidi-Mehrabad, M.; Dehnavi-Arani, S.; Evazabadian, F.; Mahmoodian, V. An Ant Colony Algorithm (ACA) for solving the new integrated model of job shop scheduling and conflict-free routing of AGVs. Comput. Ind. Eng. 2015, 86, 2–13. [Google Scholar] [CrossRef]
  2. Angeloudis, P.; Bell, M.G.H. An uncertainty-aware AGV assignment algorithm for automated container terminals. Transp. Res. Part E Logist. Transp. Rev. 2010, 46, 354–366. [Google Scholar] [CrossRef]
  3. Luo, J.; Wan, Y.; Wu, W.; Li, Z. Optimal Petri-Net Controller for Avoiding Collisions in a Class of Automated Guided Vehicle Systems. IEEE Trans. Intell. Transp. Syst. 2020, 21, 4526–4537. [Google Scholar] [CrossRef]
  4. Ji, S.; Luan, D.; Chen, Z.; Guo, D. Integrated scheduling in automated container terminals considering AGV conflict-free routing. Transp. lett. 2020, 13, 510–513. [Google Scholar]
  5. Wang, Z.; Zeng, Q. A branch-and-bound approach for AGV dispatching and routing problems in automated container terminals. Comput. Ind. Eng. 2022, 166, 100968. [Google Scholar] [CrossRef]
  6. Zhong, M.; Yang, Y.; Dessouky, Y.; Postolache, O. Multi-AGV scheduling for conflict-free path planning in automated container terminals. Comput. Ind. Eng. 2020, 142, 106371. [Google Scholar] [CrossRef]
  7. Cavone, G.; Dotoli, M.; Seatzu, C. Resource planning of intermodal terminals using timed Petri nets. In Proceedings of the 2016 13th International Workshop on Discrete Event Systems (WODES), Xi’an, China, 30 May–1 June 2016; pp. 44–50. [Google Scholar]
  8. Rashidi, H.; Tsang, E.P.K. A complete and an incomplete algorithm for automated guided vehicle scheduling in container terminals. Comput. Math. Appl. 2011, 61, 630–641. [Google Scholar] [CrossRef]
  9. Hu, X.; Guo, J.; Zhang, Y. Optimal strategies for the yard truck scheduling in container terminal with the consideration of container clusters. Comput. Ind. Eng. 2019, 137, 106083. [Google Scholar] [CrossRef]
  10. Niu, B.; Zhang, F.; Li, L.; Wu, L. Particle swarm optimization for yard truck scheduling in container terminal with a cooperative strategy. Intell. Evol. Syst. 2017, 8, 333–346. [Google Scholar]
  11. Huang, S.Y.; Li, Y. A Bounded Two-Level Dynamic Programming Algorithm for Quay Crane Scheduling in Container Terminals. Comput. Ind. Eng. 2018, 123, 303–313. [Google Scholar] [CrossRef]
  12. Ji, M.; Guo, W.; Zhu, H.; Yang, Y. Optimization of loading sequence and rehandling strategy for multi-quay crane operations in container terminals. Transp. Res. Part E Logist. Transp. Rev. 2015, 80, 1–19. [Google Scholar] [CrossRef]
  13. Zhang, H.; Kim, K.H. Maximizing the number of dual-cycle operations of quay cranes in container terminals. Comput. Ind. Eng. 2009, 56, 979–992. [Google Scholar] [CrossRef]
  14. Nguyen, V.D.; Kim, K.H. Heuristic Algorithms for Constructing Transporter Pools in Container Terminals. IEEE Trans. Intell. Transp. Syst. 2012, 14, 517–526. [Google Scholar] [CrossRef]
  15. Zhen, L.; Yu, S.; Wang, S.; Sun, Z. Scheduling quay cranes and yard trucks for unloading operations in container ports. Ann. Oper. Res. 2019, 273, 455–478. [Google Scholar]
  16. Zhang, Z.; Liu, M.; Lee, C.; Wang, J. The Quay Crane Scheduling Problem with Stability Constraints. IEEE Trans. Autom. Sci. Eng. 2018, 15, 1399–1412. [Google Scholar] [CrossRef]
  17. Zhen, L. Container yard template planning under uncertain maritime market. Transp. Res. Part E Logist. Transp. Rev. 2014, 69, 199–217. [Google Scholar] [CrossRef]
  18. Sheikholeslami, A.; Ilati, R. A sample average approximation approach to the berth allocation problem with uncertain tides. Eng. Optim. 2018, 50, 1772–1788. [Google Scholar] [CrossRef]
  19. Wang, W.; Wu, Y. Is uncertainty always bad for the performance of transportation systems? Commun. Transp. Res. 2021, 1, 100021. [Google Scholar]
  20. Zheng, F.; Man, X.; Chu, F.; Liu, M.; Chu, C. A two-stage stochastic programming for single yard crane scheduling with uncertain release times of retrieval tasks. Int. J. Prod. Econ. 2019, 57, 4132–4147. [Google Scholar] [CrossRef]
  21. Ng, W.C.; Mak, K.L. Yard crane scheduling in port container terminals. Appl. Math. Model. 2005, 29, 263–276. [Google Scholar] [CrossRef] [Green Version]
  22. Javanshir, H.; Ghomi, S.M.T.F.; Ghomi, M.F. Investigating transportation system in container terminals and developing a yard crane scheduling model. Manag. Sci. Lett. 2012, 2, 171–180. [Google Scholar] [CrossRef]
  23. Diabat, A.; Theodorou, E. An Integrated Quay Crane Assignment and Scheduling Problem. Comput. Ind. Eng. 2014, 73, 115–123. [Google Scholar] [CrossRef]
  24. He, J.; Tana, C.; Zhang, Y. Yard crane scheduling problem in a container terminal considering risk caused by uncertainty. Adv. Eng. Inform. 2019, 39, 14–24. [Google Scholar] [CrossRef]
  25. Luo, J.; Wu, Y. Modelling of dual-cycle strategy for container storage and vehicle scheduling problems at automated container terminals. Transp. Res. Part E Logist. Transp. Rev. 2015, 79, 49–64. [Google Scholar] [CrossRef]
  26. Zheng, F.; Pang, Y.; Liu, M.; Xu, Y. Dynamic programming algorithms for the general quay crane double-cycling problem with internal-reshuffles. J. Comb. Optim. 2020, 39, 708–724. [Google Scholar] [CrossRef]
  27. Cao, J.X.; Shang, X.; Yao, X. Integrated quay crane and yard truck schedule for the dual-cycling strategies. In Proceedings of the CICTP 2017: Transportation Reform and Change—Equity, Inclusiveness, Sharing, and Innovation, Shanghai, China, 7–9 July 2017; pp. 1346–1357. [Google Scholar]
  28. Liu, M.; Chu, F.; Zhang, Z.; Chu, C. A polynomial-time heuristic for the quay crane double cycling problem with internal-reshuffling operations. Transp. Res. Part E Logist. Transp. Rev. 2015, 81, 52–74. [Google Scholar] [CrossRef]
  29. Wang, D.; Li, X. Quay crane scheduling with dual cycling. Engineering Optimization. Eng. Optim. 2015, 47, 1343–1360. [Google Scholar] [CrossRef]
  30. Nguyen, V.D.; Kim, K.H. Minimizing empty trips of yard trucks in container terminals by dual cycle operations. Ind. Eng. Manag. Syst. 2010, 9, 28–40. [Google Scholar] [CrossRef]
  31. Meisel, F.; Wichmann, M. Container sequencing for quay cranes with internal reshuffles. OR Spectr. 2010, 32, 569–591. [Google Scholar] [CrossRef]
  32. Goodchild, A.V.; Daganzo, C.F. Double-cycling strategies for container ships and their effect on ship loading and unloading operations. Transp. Sci. 2016, 40, 473–483. [Google Scholar] [CrossRef]
  33. Ahmed, E.; El-Abbasy, M.S.; Zayed, T.; Alfalah, G.; Alkass, S. Synchronized scheduling model for container terminals using simulated double-cycling strategy. Comput. Ind. Eng. 2021, 154, 107118. [Google Scholar] [CrossRef]
  34. Nishimura, E. Yard and berth planning efficiency with estimated handling time. Marit. Bus. Rev. 2020, 5, 5–29. [Google Scholar] [CrossRef] [Green Version]
  35. Guo, X.; Huang, S.Y.; Hsu, W.J.; Low, M.Y.H. Yard crane dispatching based on real time data driven simulation for container terminals. In Proceedings of the 2008 Winter Simulation Conference, Winter Simulation Conference, Miami, FL, USA, 7–10 December 2008; pp. 2648–2655. [Google Scholar]
  36. Kennedy, J.; Eberhart, R. Particle Swarm Optimization. In Proceedings of the ICNN’95—International Conference on Neural Networks, Perth, Australia, 27 November–1 December 1995; Volume 4, pp. 1942–1948. [Google Scholar]
  37. Guo, X.; Zhang, Z.; Qi, L.; Liu, S.; Tang, Y.; Zhao, Z. Stochastic Hybrid Discrete Grey Wolf Optimizer for Multi-objective Disassembly Sequencing and Line Balancing Planning in Disassembling Multiple Products. IEEE Trans. Autom. Sci. Eng. 2021, 1–3. [Google Scholar] [CrossRef]
  38. Guo, X.; Zhou, M.; Alsokhiry, F.; Sedraoui, K. Disassembly sequence planning: A survey. IEEE/CAA J. Autom. Sin. 2021, 8, 1308–1324. [Google Scholar] [CrossRef]
  39. Guo, X.; Zhou, M.; Liu, S.; Qi, L. Multi-resource Constrained Selective Disassembly with Maximal Profit and Minimal Energy Consumption. IEEE Trans. Autom. Sci. Eng. 2021, 18, 804–816. [Google Scholar] [CrossRef]
  40. Guo, X.; Zhou, M.; Liu, S.; Qi, L. Lexicographic Multiobjective Scatter Search for the Optimization of Sequence-Dependent Selective Disassembly Subject to Multiresource Constraints. IEEE Trans. Cybern. 2020, 50, 3307–3317. [Google Scholar] [CrossRef]
  41. Guo, X.; Liu, S.; Zhou, M.; Tian, G. Dual-objective program and scatter search for the optimization of disassembly sequences subject to multi-resource constraints. IEEE Trans. Autom. Sci. Eng. 2018, 15, 1091–1103. [Google Scholar] [CrossRef]
  42. Guo, X.; Liu, S.; Zhou, M.; Qi, L. Disassembly sequence optimization for large-scale products with multiresource constraints using scatter search and Petri nets. IEEE Trans. Cybern. 2016, 46, 2435–2446. [Google Scholar] [CrossRef]
  43. Zhao, Z.; Liu, S.; Zhou, M.; Guo, X.; Qi, L. Decomposition method for new single-machine scheduling problems from steel production systems. IEEE Trans. Autom. Sci. Eng. 2020, 17, 1376–1387. [Google Scholar] [CrossRef]
  44. Zhao, J.; Liu, S.; Zhou, M.; Guo, X.; Qi, L. Modified cuckoo search algorithm to solve economic power dispatch optimization problems. IEEE/CAA J. Autom. Sin. 2018, 5, 794–806. [Google Scholar] [CrossRef]
  45. Wang, X.; Zhou, M.; Zhao, Q.; Liu, S.; Guo, X.; Qi, L. A Branch and Price Algorithm for Crane Assignment and Scheduling in Slab Yard. IEEE Trans. Autom. Sci. Eng. 2021, 18, 1122–1133. [Google Scholar] [CrossRef]
  46. Zhao, Z.; Zhou, H.; Qi, L.; Chang, L.; Zhou, M. Inductive Representation Learning via CNN for Partially-Unseen Attributed Networks. IEEE Trans. Netw. Sci. Eng. 2021, 8, 695–706. [Google Scholar] [CrossRef]
  47. Ji, S.; Zhang, Q.; Li, J.; Chiu, D.K.W.; Xu, S.; Yi, L.; Gong, M. A burst-based unsupervised method for detecting review spammer groups. Inf. Sci. 2020, 536, 454–469. [Google Scholar] [CrossRef]
Figure 1. A double-cycling AGV scheduling mode.
Figure 1. A double-cycling AGV scheduling mode.
Applsci 12 04820 g001
Figure 2. Individual coding mode.
Figure 2. Individual coding mode.
Applsci 12 04820 g002
Figure 3. AGVs’ scheduling sequence.
Figure 3. AGVs’ scheduling sequence.
Applsci 12 04820 g003
Figure 4. AGV double-cycling algorithm.
Figure 4. AGV double-cycling algorithm.
Applsci 12 04820 g004
Table 1. The problems solved by using double-cycling strategies.
Table 1. The problems solved by using double-cycling strategies.
StudiesScheduling ProblemUncertainty Considered?AGV Scheduling Sequence Obtained?
Luo and Wu, 2015 [25]QCSP with YCSPNoYes
Zheng, Pang, Liu, and Xu, 2019 [26]QCSP with CSPNoNo
Cao et al., 2018 [27]Integrated QCSP-YTSPNoYes
Liu et al., 2015 [28]QCSP with CSPNoNo
Wang and Li, 2015 [29]QCSP with CSPNoNo
Nguyen and Kim, 2010 [30]YTSPYesNo
Meisel and Wichmann, 2010 [31]QCSP with CSPNoNo
Goodchild and Daganzo, 2006 [32]QCSPYesNo
Ahmed, Mohammed, Zayed, Alfalah and Alkass, 2021 [33]Integrated QCSP-YTSP-YCSPYesNo
Our WorkIntegrated QCSP-YCSPYesYes
Table 2. The symbols and their definitions.
Table 2. The symbols and their definitions.
SymbolDefinition
M M = { m 1 ,   m 2 ,   ,   m n }   is   a   set   of   task   points ,   where   m i = P 1 i ,   w , P 2 i , T i ,   n   is   the   number   of   task   points .   For   containers   to   be   unloaded   from   ships ,   P 1 i   represents   the   position   of   container   i on   the   ship ,   w represents   that   container   i   will   be   loaded   at   yard   w ,   and   P 2 i   represents   the   destination   of   container   i   in   the   yard .   For   containers   to   be   loaded   onto   ships ,   P 1 i   represents   the   destination   of   the   container   in   the   ship ,   w represents   that   container   i   will   be   unloaded   at   yard   w ,   and   P 2 i   represents   the   position   of   container   i on   the   yard .   T i represents the LTQ of container i;
Xa set of unloading task points that represent unloading the containers in the ship onto the yard;
Ya set of loading task points that represent loading the containers in the yard onto the ship;
lthe number of AGVs;
agthe g-th AGV where 1 ≤ g ≤ l;
mba virtual begin task point;
mea virtual end task point;
VQaverage movement speed of QC;
Δ t i average time of QC spreader grasping container i;
D i q the distance that a QC moves to from the position of the AGV to the position of container i;
C i a   time - interval   conforming   to   the   Gaussian   distribution ,   including   the   minimum   and   maximum   time   taken   by   QC   to   transport   container   i ,   where   C i i = ( C 1 i ,   C 2 i ) ,   C 1 i   and   C 2 i are the minimum time and maximum time for QC to transport container i transportation, respectively;
VYmoving speed of YC;
D i j Y the moving distance of the YC from the position of container i to the position of container j. It represents the distance from the I/O point to the position of container j when i = 0; it represents the distance of the YC moved from the position of container i to the I/O point when j = 0;
Vymovement speed of spreader;
D i j y the moving distance of the YC’s spreader from the position of container i to the position of container j. It represents the distance of the spreader moving from the I/O point to the position of container j if i = 0; it represents the distance of the spreader moved from the position of container i to the I/O point if j = 0;
G y the speed at which the YC’s spreader moves up and down;
dithe distance of the YC’s spreader moves to grab the container i;
T i q time taken by QC to transport container i;
T y time required by the spreader to transport a container at the I/O point;
T i l time is taken by YC to load the container i;
T i u l time is taken by YC to unload the container i;
TgTg ={t1, t2, …, t|Z| + 1}, where tg is the waiting time of ag;
H i j the empty running time of an AGV loading task point mi after unloading task point mj at the yard;
T the time interval between two consecutive AGVs exiting the quayside;
T i q 1 the waiting time before task point i is unloaded at the quayside;
T i q 2 the waiting time before task point i is loaded at the quayside;
T i 1 the waiting time before task point i is unloaded in the yard;
T i 2 the time taken for task point i to be unloaded in the yard;
T i 3 the waiting time before task point i is loaded in the yard;
T i 4 the time taken for task point i to be loaded in the yard.
Table 3. The symbols used in the algorithm and their definitions.
Table 3. The symbols used in the algorithm and their definitions.
SymbolDefinition
Qparticle swarm size;
Tcurrent iteration index;
tmaxmaximum iteration;
Pparticle fitness;
pBestpersonal best position, a set of the coding schemes in our algorithm. The personal best position means the optimal scheduling sequence for each particle in the algorithm iteration process;
gBestglobal best particle.
Table 4. The decision variables and their definitions.
Table 4. The decision variables and their definitions.
χ j i = 1   ,   an   AGV   transports   task   point   j   after   task   point   i 0 ,   otherwise  
α g = 1 ,   a g   is   fully   loaded   to   drive   out   of   the   yard 0 ,   otherwise      
β g = 1 ,   a g   is   fully   loaded   to   drive   out   of   the   quayside 0 ,   otherwise  
γ i w = 0 ,   the   Y C   c a n n o t   b e   p r e p a r e d   i n   a d v a n c e   a t   y a r d   w 1 ,   t h e   Y C   c a n   b e   p r e p a r e d   i n   a d v a n c e   a t   y a r d   w      
δ i =   1 ,   t a s k   p o i n t   i   i s   t r a n s p o r t e d   t o   t h e   q u a y s i d e 0 ,   t a s k   p o i n t   i   i s   t r a n s p o r t e d   t o   t h e   y a r d              
ε w i = 1 ,   c o n t a i n e r   i     i s   l o a d e d   a t   y a r d   w         0 ,   c o n t a i n e r   i   i s   u n l o a d e d     a t   y a r d   w    
ϵ = 1 ,   a n   A G V   l o a d s   c o n t a i n e r s   a t   t h e   s a m e   y a r d   a f t e r   u n l o a d i n g       0 ,   a n   A G V   l o a d s   c o n t a i n e r s   a t   a   d i f f e r e n t   y a r d   a f t e r   u n l o a d i n g    
Table 5. The data obtained in Qingdao Port.
Table 5. The data obtained in Qingdao Port.
Speed of QC50 m/min
Speed of QC spreader240 m/min
Grasping speed of QC spreader180 m/min
Average time for QC to transport containers60 s
Average travel time from the quayside to the yard30 s
Speed of YC270 m/min
Speed of YC spreader180 m/min
Grasping speed of YC spreader60 m/min
Average time for YC to transport containers74 s
Speed of AGV3 m/s
AGV travel time between two YCs15 s
AGV travel time between two QCs15 s
Table 6. Results of multiple experiments in our double-cycle model.
Table 6. Results of multiple experiments in our double-cycle model.
Experiment RoundNot-Conform Doble-CyclingNot-Conform LTQFitness ValueTotal Waiting Time (s)
100944944
20010121012
300939939
400941941
500965965
60010201020
70010321032
80010551055
900960960
100010731073
11011989989
120441,0431043
Table 7. The experimental results of different number of AGVs at 10 task points.
Table 7. The experimental results of different number of AGVs at 10 task points.
Number of AGVsNumber of Task PointsExperiment RoundTotal Waiting Time (s)Not-Conform LTQ
21014284
24964
35575
31014490
24050
34780
41015110
24810
35270
Table 8. The experimental results of different number of AGVs at 20 task points.
Table 8. The experimental results of different number of AGVs at 20 task points.
Number of AGVsNumber of Task PointsExperiment RoundTotal Waiting Time (s)Not-Conform LTQ
320111224
211106
310865
420110050
210610
310040
52019730
29290
39440
620110860
211120
310610
Table 9. The experimental results of different number of AGVs at 30 task points.
Table 9. The experimental results of different number of AGVs at 30 task points.
Number of AGVsNumber of Task PointsExperiment RoundTotal Waiting Time (s)Not-Conform LTQ
430120140
220017
319552
530119030
218900
319100
630118180
218390
318290
730118470
218614
318230
830118430
218570
319280
Table 10. The experimental results of different number of AGVs at 40 task points.
Table 10. The experimental results of different number of AGVs at 40 task points.
Number of AGVsNumber of Task PointsExperiment RoundTotal Waiting Time (s)Not-Conform LTQ
440126890
227215
327171
540124980
224440
324000
640126790
226870
326240
740126340
226180
326220
840125840
226530
326780
Table 11. The experimental results of different number of AGVs at 50 task points.
Table 11. The experimental results of different number of AGVs at 50 task points.
Number of AGVsNumber of Task PointsExperiment RoundTotal Waiting Time (s)Not-Conform LTQ
550133870
234532
3350112
650133980
232960
334382
750134200
233690
334340
850133330
233080
336100
Table 12. The influence of QC conforms to different Gaussian distributions with 30 task points and 5 AGVs.
Table 12. The influence of QC conforms to different Gaussian distributions with 30 task points and 5 AGVs.
Experiment Round μ = 4 ,   σ = 4 μ = 4 ,   σ = 8 μ = 8 ,   σ = 8 μ = 8 ,   σ = 16
Total Waiting Time (s)Not-Conform LTQTotal Waiting Time (s)Not-Conform LTQTotal Waiting Time (s)Not-Conform LTQTotal Waiting Time (s)Not-Conform LTQ
118130168101871021200
217970177601845022652
316950174201876019690
417820191601947020710
518610179002067216630
618820184701914018700
718310194302221022604
818490173302020419770
918120184501851023092
1018210191202019019651
Table 13. The success rate of the algorithm under different number of task points.
Table 13. The success rate of the algorithm under different number of task points.
Number of Task PointsGAHPSOSA
1290.19%98.41%88.23%
1686.27%98.33%80.39%
2084.31%98.27%75.55%
2476.47%96.07%68.62%
Table 14. The success rate of the algorithm under different μ and σ.
Table 14. The success rate of the algorithm under different μ and σ.
(μ, σ)GAHPSOSA
(4, 4)88.46%98.38%87.23%
(4, 8)86.27%98.50%85.10%
(8, 8)82.35%98.30%82.22%
(8, 16)78.43%98.14%74.5%
Table 15. The average execution time of the algorithm under different number of task points.
Table 15. The average execution time of the algorithm under different number of task points.
Number of Task PointsGAHPSOSA
1225.96 s12.85 s32.76 s
1628.87 s14.82 s41.13 s
2042.65 s17.12 s69.50 s
2465.42 s18.24 s113.38 s
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Zhang, H.; Qi, L.; Luan, W.; Ma, H. Double-Cycling AGV Scheduling Considering Uncertain Crane Operational Time at Container Terminals. Appl. Sci. 2022, 12, 4820. https://doi.org/10.3390/app12104820

AMA Style

Zhang H, Qi L, Luan W, Ma H. Double-Cycling AGV Scheduling Considering Uncertain Crane Operational Time at Container Terminals. Applied Sciences. 2022; 12(10):4820. https://doi.org/10.3390/app12104820

Chicago/Turabian Style

Zhang, Hongchang, Liang Qi, Wenjing Luan, and Huijuan Ma. 2022. "Double-Cycling AGV Scheduling Considering Uncertain Crane Operational Time at Container Terminals" Applied Sciences 12, no. 10: 4820. https://doi.org/10.3390/app12104820