Next Article in Journal
Sustainable Pavement Construction in Sensitive Environments: Low-Energy Asphalt with Local Waste Materials and Geomaterials
Previous Article in Journal
Exploring the Impact of Social Media Use on Team Feedback and Team Performance in Construction Projects: A Systematic Literature Review
Previous Article in Special Issue
A Dynamic Model for Effective and Optimal Planning of Formwork in Construction Projects
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Development of a Cost Normalization Framework for Healthcare Facilities Cost Elements

1
Nieri Department of Construction, Development and Planning, Clemson University, 2-135 Lee Hall, Clemson, SC 29634, USA
2
Maseeh Department of Civil, Architectural and Environmental Engineering, The University of Texas at Austin, 301 E. Dean Keeton St., ECJ 5.210, Austin, TX 78712-1700, USA
*
Author to whom correspondence should be addressed.
Buildings 2024, 14(2), 529; https://doi.org/10.3390/buildings14020529
Submission received: 31 October 2023 / Revised: 23 January 2024 / Accepted: 7 February 2024 / Published: 16 February 2024
(This article belongs to the Special Issue Costs and Cost Analysis in Construction Project Management)

Abstract

:
Healthcare facilities (HCFs) are complex building structures that are becoming more challenging with ever-changing codes and regulations. Previously completed projects become a basis for future guidance regarding costs and scope. A robust normalization framework to assess previously completed projects with today’s costs and location will benefit various stakeholders. The current study provides a complete picture for normalizing the overall project cost and phase cost by life cycle and HCF cost elements. This study aims to develop a cost normalization approach tailored to HCF-specific cost elements to extend the normalization framework for the overall project cost. Further, the researchers developed a distinct framework for normalizing the effect of shell space on the normalization of Total Installed Cost (TIC) to establish fixed cost adjustment rates for cold and warm shell spaces in HCFs, which can increase the accuracy of cost normalization of the overall project cost. This study identified an appropriate set of cost indices for normalizing HCF cost elements using publicly available indices. The cost elements identified for normalization included HCF-specific and Construction Specifications Institute Master Format (CSIMF) cost elements for assigning individual normalization procedures. This study provides individual and unique approaches for normalizing all identified cost elements, such as mechanical, concrete, etc. The initial framework was evaluated through a case study analysis that developed into the proposed approach built upon the collaborative efforts of academic researchers and industry experts. This study introduced shell space cost adjustment rates for warm and cold shell spaces to further develop a space normalization framework. This paper addresses the challenges of normalizing HCF project costs using the breakdown of HCF cost elements. Moreover, the paper provides the HCF’s overall cost normalization approach, emphasizing cost elements that allow accurate comparisons between various HCFs for early scope and cost guidance.

1. Introduction

“The healthcare sector is characterized by high capital investment, increasing technological sophistication, and a competitive marketplace” [1]. The scale, function, technology, and materials for construction require further improvements in the post-pandemic era, and the industrialization degree of the assembly and automation systems adopted has become much higher [2]. Furthermore, the healthcare industry’s Earnings Before Interest, Taxes, Depreciation, and Amortization (EBITDA) grew by 5% between 2017 and 2019; however, these earnings remained flat during 2020 and 2021. Further predictions expect a growth rate of 6% between the years 2021 and 2025, adding USD 31 billion in HCF profits [3]. These trends predict the healthcare and pharma sectors to be some of the fastest-growing sectors in the United States, suggesting a high demand for the construction of new healthcare facilities and renovation of existing facilities. According to [4], COVID-19 was a major driving force that brought change in healthcare facilities’ design, operations, and sustainability efforts.
Healthcare projects are complex to design, build, and operate in the industry [5], requiring extensive planning for successful delivery. Furthermore, the efficient delivery of healthcare projects requires managing a diverse set of data variables that influence the scope of the project and its estimated cost [6]. The timing of key decisions in the project life cycle can significantly affect costs; therefore, early identification of factors that influence overall project costs is extremely important to healthcare facility owners [1,6]. The complexities in design and facility planning often raise the need for flexible, adaptable, and multifunctional solutions to meet the rapidly changing demands of the industry [7]. Healthcare projects require extreme precision during the design and construction phases and, therefore, need a robust benchmarking program and a cost normalization framework. These analytics assist HCF owners and the construction management team in validating the normalized costs based on similar projects from peers [1].
As a part of the benchmarking program, [8,9] developed frameworks for normalizing the overall project cost and project cost by life-cycle phases, respectively; however, the challenges of extensive planning in healthcare necessitate a cost normalization framework for individual HCFs, specific cost elements to allow the comparison of different healthcare systems across the nations [1,10].
Benchmarking is “the process of establishing a standard of excellence and comparing a business function or activity, a product, or an enterprise as a whole with that standard” [11]. Benchmarking is a performance tool that compares similar projects that extrapolate data into useful comparative metrics. A normalization framework is at the heart of a benchmarking program, and its success depends on its customization to the program, facility type, and detailed cost elements of the facility. Internal benchmarking describes comparisons within an organization, while external benchmarking involves comparing the subject company or property to external organizations. External benchmarking is defined as “the process of identifying, understanding, and adapting outstanding practices from organizations anywhere in the world to help an organization improve its performance” [8,12]. External benchmarking builds a consortium of peers or like-minded organizations to support comparisons of similar facilities through various performance parameters. Therefore, facilities with different systems, locations, and costs need to be normalized to today’s costs at a common location for meaningful comparisons. The external benchmarking application allows one company to evaluate another company’s ideas, practices, or methods and, if possible, apply them to its own business [13,14].
Many factors impact cost benchmarking. For instance, a shell space in HCF affects cost comparisons, specifically the dollars per Building Gross Square Feet (USD /BGSF) metric. Shell space can be defined as the space constructed within the exterior building shell that is left unfinished to meet the future requirements of the facility [15]. Shell space is categorized into cold and warm shell space—wherein the cold shell is defined as an HCF’s non-habitable space with no finishes or walls, no flooring, no lighting, and no air conditioning. On the other hand, a warm shell is completed with fittings and air conditioning ducts, electrical distribution, and fire suppression [6]. The program of a facility planned with shell space is less than a wholly developed facility since the square footage of unfinished floors (because the cost of the shell space is less than the fully built space) is not added to the BGSF. Therefore, the current paper addresses the challenge of comparing a facility with shell space and another entirely built-out facility. Hence, without separate consideration for the shell space cost, the normalized Total Installed Cost (TIC) for the complete facility becomes inconsistent. A separate framework for normalizing shell space costs can lead to a more accurate cost normalization of the overall project cost. Therefore, this study addresses space normalization as a separate entity and develops different cost adjustment factors for warm and cold shell spaces.
This study has identifies HCF-specific and CSIMF cost elements and develops individual normalization methods adhering to the specificity of each cost element. Furthermore, this study develops a space normalization methodology validated through various case study examples. The objectives of this study are to:
  • Identify and recommend a set of indices that best suit the time and location adjustments.
  • Evaluate the applicability of the normalization framework for TIC towards phase costs and HCF-specific cost elements.
  • Develop/complete the overall normalization approach to healthcare facilities costs: the overall cost, cost elements, and an adjustment for shell space.
    • Specific normalization framework for CSIMF cost elements.
    • Identify adjustment rates to develop a prototype space normalization procedure.
Further, this study outlines the challenges and considerations associated with the cost indices applicable to cost normalization and discusses the limitations and the availability of future improvements for the framework.

2. Literature Review—Selection of Indices

In order to collect and record data for benchmarking across the healthcare sector, project costs from different times and locations need to be normalized to a comparable scale using different benchmarking frameworks developed through previous research. Previous studies on benchmarking have developed a unique framework for normalizing the overall project cost [8] and the project cost through different life-cycle phases [9]. Each framework developed a normalization approach for the program’s overall cost. This study, by extension, has studied construction cost elements specific to HCFs and developed a framework to normalize individual cost elements, including CSIMF cost elements.
According to [8], TIC is defined as “the total actual project cost (excluding the cost of land) from programming/front-end planning through commissioning, including capitalized amounts expended for in-house salaries, overhead, travel, etc.” The authors of [8] developed a normalization framework for TIC based on this definition. Furthermore, according to [16,17], construction costs for HCFs largely depend upon local conditions such as material/equipment costs, labor, and suppliers/contractors. The authors of [9] define construction costs as “all cost elements associated and included within the project phases.” Based on these findings, a benchmarking framework for healthcare projects measuring performance at the phase level has been developed by collecting data across all five construction phases—programming, engineering/design, procurement, construction, and commissioning of a project [18]. In extension, a framework to normalize HCF cost elements such as material, equipment, labor, contractor overhead, local taxes, project management costs, and other CSIMF cost elements is developed in this study.
The normalization framework will ultimately provide quantitative information to support decision making on the specific project scope and improvement of work processes used to execute healthcare projects. Benchmarking is impacted by cost normalization; therefore, selecting appropriate indices for normalization is necessary. As all the programs primarily use publicly available indices and each index is built differently, a brief understanding of the indices is essential for a normalization framework.

2.1. Cost Indices

Cost indices measure the fluctuation in prices of certain construction elements over time and/or location using a standard series of values [19]. Cost indices are primarily divided into input, output, and selling price indices. Various publicly available indices provide a variety of alternatives for adjusting time and location. According to [20], inaccurate selection and application of location adjustment indices (input or output) results in significant cost adjustment fluctuations. Therefore, a basic understanding is developed before selecting specific indices to normalize HCF cost elements.

2.1.1. Input Price Indices

Input price indices focus on inputs to the construction processes, such as materials, equipment, and labor. The main objective of input indices is to track and reflect changing market conditions with respect to the costs of these components individually. Input indices help organizations track and understand the differences between material, equipment, and labor costs at different locations for construction cost comparisons [20]. This entails the compilation of weighted indices of wages and materials costs. Table 1 illustrates that the RSMeans [21], ENR (Engineering News-Record), and Marshal & Swift Building Cost Index (BCI) are input indices developed using the standard factor method. Based on the number of comparison cities, RSMeans is typically used for location adjustment in the normalization process for a case where the midpoint of the construction phase and locations are defined [8]. BCI derives an index specific to location without reference to time.
ENR’s Construction Cost Index (CCI) and the RSMeans Historical Cost Index (RSMHCI) represent the general trend of construction costs in reference to time. CCI provides an average of 20 cities, while RSMHCI reflects an average of 30 cities [22]. While the ENR BCI and ENR CCI apply to general construction costs, the main difference between BCI and CCI is consideration of the labor component. While CCI uses 200 h of common labor multiplied by the 20-city average rate for wages and fringe benefits, BCI uses 68.38 h of skilled labor multiplied by the 20-city wage-fringe-average for three trades—bricklayers, carpenters, and structural ironworkers. The BCI and CCI material components utilize 25 cwt (hundredweight; cwt = centum weight) of fabricated standard structural steel at the 20-city average price, 1.128 tons of bulk Portland cement priced locally, and 1088 board ft of 2 × 4 lumber priced locally [23]. Primarily, the ENR indices measure the costs to purchase this hypothetical package of goods compared to what it was in the base year.

2.1.2. Output Price Indices

Output price indices measure changes in the price of the output of specific activities in the construction processes [19]. These generally include materials, labor, equipment hires, land preparation costs, bathroom/kitchen fittings, overhead, profits, and trade margins [24]. Output price indices compare the change in construction costs of a proposed structure by time or location. They require a more wide-ranging data collection but are preferred since they capture the effects of productivity, profit margins, and labor tradeoffs on the overall project cost [20,25].
Three types of indices can help develop output-based price indices: the model price index, hedonic price index, and bid/unit price index [26]. These output indices include the cost of labor, materials, the use of fuel and equipment, job overhead, profit, taxes, etc. Under the model price index, the output-based indices compare the construction cost of a hypothetical structure by location and/or time [8]. The quality of the final product is used as a measure in constructing the hedonic price index [26]. Hedonic price indices are component pricing types using cross-section regression to estimate component prices. Based on the indices’ properties, the model price index under output-based price indices synchronizes effectively with the construction sector. A bid/unit price index estimates specific types of engineered construction costs based on their unit bid prices. Hence, this index has limited application to HCF construction.
As illustrated in Table 2, the Producer Price Index (PPI) measures the changes in prices paid for production sold outside the industry [27]. The PPI calculates the average change in selling prices for domestic producers’ output over time. The prices included in the PPI are from the first commercial transaction for many products and services. The PPI for new healthcare building construction (NAICS code 236224) from the Bureau of Labor Statistics (BLS) is based on the North American Industry Classification System (NAICS) [27]. By simulating multiple vernacular building types, the model price index allows for construction heterogeneity and is more sensitive to market shift situations. The Mortenson Construction Cost Index is calculated quarterly by pricing a representative non-residential construction project in geographies throughout the country. Similarly, the Turner Building Cost Index [28] measures costs in the non-residential construction market in the country. The Rider Levett Bucknall (RLB) Cost Relativity Index [29] calculates the construction cost differential between two selected cities worldwide.

2.1.3. Selling Price Index (SPI)

The Selling Price Index (SPI) evaluates the average variation in the building’s selling price over time. As a result, this index assesses the changes in construction output costs paid by the owner. The SPI measures the total cost of completed construction, including materials, labor, equipment, contractor’s margins, overhead expenses, land, direct and indirect selling expenses, and the seller’s profit margins. The SPI can be used to adjust construction project costs over time. One example of an SPI is the DoD (Department of Defense) Selling Price Index (DoD-SPI), which represents an average of three widely accepted construction price indices, namely, the RLB Construction Cost Index (output), Turner Construction Cost Index (output), and Saylor Subcontracting Index [30,31].
Saylor discontinued issuing their index in October 2009; therefore, the current third index utilized in the DoD calculation is the BLS PPI for NAICS 236223. The DoD created the SPI to precisely reflect actual (historical) market escalation as experienced by the DoD as the project owner for the construction type in the portfolio [31]. Previously, the DoD (Table 3) used the Engineering News-Record Building Cost Index (ENR BCI). The ENR BCI tracks the costs of three basic materials and one skilled labor type but does not account for other pricing influences (such as risk and competition) impacting the project owner’s total delivered price.
As discussed in the background study, selecting appropriate indices is vital to reflect cost normalization accurately. Due to the abundance of publicly available cost indices, it is a challenge to determine the most suitable indices for adjusting the detailed cost breakdown. Therefore, this study further evaluated the publicly available input and output indices to determine the most suitable indices for normalizing HCF-specific and CSIMF cost elements for location and time.

2.2. Cost Normalization

Cost normalization refers to adjusting total project costs from different times and locations to comparable standards by adjusting all cost data to a common time and location [32]. Absolute metrics require normalization since the measures are external and of different values; however, cost normalization is unnecessary for relative metrics due to internal measures of the same values using planned versus actual data [17]. Currency, time, and location adjustments are the three required steps of cost normalization to evaluate accurate project costs [16]. In order to analyze cost performance using absolute metrics, cost data must be normalized from the project location and time to the reference location and time [1,17]. According to [1], the HCF benchmarking program and the Hanscomb Means International Construction Cost Index use Chicago, IL, as a reference location. Furthermore, the normalization approach established for TIC also uses Chicago as a reference city for the currency, location, and time adjustment [8]. The detailed normalization procedure for TIC is illustrated in Table 4 for a hypothetical healthcare project in Indianapolis, with 2012 as the midpoint of construction.

2.2.1. Currency Conversion

Due to extensive globalization, many construction companies have entered international markets and delivered healthcare projects while paid in local currencies [16]. Therefore, currency conversion is the first crucial step in normalization when the costs of international projects are paid in the local currency. This step-in cost normalization is designed to accommodate the future expansion of healthcare benchmarking to include international healthcare owners and contractors. Currency conversion allows seamless expansion of the healthcare benchmarking program to include foreign projects. In this globalizing economy, multiple equilibrium structures and frameworks of currency exchange exist using trade links between countries [33]. Therefore, any cost data could be converted to a single currency unit of the United States (U.S.) dollar. Currency conversion can be applied to all cost elements of healthcare facilities.

2.2.2. Location Adjustment

Comparing two projects built at different locations requires adjusting cost elements that vary from one geographical location to another [16]. This allows the healthcare benchmarking program to expand to include healthcare projects located in different places with different aspects of local environments. According to [1], the design, Architectural/Engineering (A/E), Construction Manager (CM), and capital medical equipment costs remain the same across the nationwide markets or regional conditions and, therefore, do not need to be adjusted for location. Therefore, post currency conversion, the design, A/E, CM, and capital medical equipment costs are deducted from the total project cost, and the net cost is normalized for the location—Chicago, IL. For projects in the U.S., the TIC can be normalized for the location using Equation (1).
Equation (1): Location Adjustment Using the City Cost Indexes (RSMeans data, 2023):
I n d e x   f o r   C i t y   A I n d e x   f o r   C i t y   B × C o s t   i n   C i t y   B = C o s t   i n   C i t y   A
For projects outside of the U.S., TIC can be normalized for location using Equation (2).
Equation (2): Adjustment from the National Average (RSMeans data, 2023):
I n d e x   f o r   C i t y   A 100 × N a t i o n a l   A v e r a g e   C o s t = C o s t   i n   C i t y   A

2.2.3. Escalation/Time Adjustment

Because the cost of an item has a time value, it is essential to know the year in which funds were spent. For example, a cost element of USD 100 in 1990 is more expensive than the same cost element in 2005 based on inflation growth over 15 years, which means that the cost element in 1990 will cost more when converted to a 2005 equivalent cost [34]. Time adjustment is the third and final step of cost normalization, where the net cost after location adjustment is converted from the midpoint of construction in Chicago to the present cost of the project in Chicago [16]. At this stage, the design, A/E, CM, and capital medical equipment costs eliminated from the location adjustment are normalized separately for time to reach the final comparable normalized cost of a cost element or the total project cost. According to [16], the midpoint of the construction phase in the project life cycle is when the majority of project expenditures occur. The construction phase costs are also significantly affected by the local conditions, such as construction labor, equipment, suppliers, and material costs [16,17]. Therefore, location and time adjustments both use the midpoint of the construction phase for normalization. A more accurate result could be achieved by adjusting every project transaction, but extensive efforts are required.
Equation (3): Time Adjustment for the National Average Using the Historical Cost Index (RSMeans data, 2023):
I n d e x   f o r   Y e a r   A I n d e x   f o r   Y e a r   B × C o s t   i n   Y e a r   B = C o s t   i n   Y e a r   A

2.3. Space Normalization

Space normalization works through dimensional metrics for a shell space. Two types of shell space are prevalent in healthcare institutions. The first is the cold shell space, which is unfit for occupancy and does not include finishes or walls. Fire separation requirements are based on the intended use and local regulations by the authority having jurisdiction. A cold-shell constructed space typically does not have plumbing, electrical, heating, ventilation, or air conditioning (HVAC) systems. Sometimes, the main mechanical unit(s) may be absent. The second is a warm shall space and is constructed with basic electrical, plumbing, and HVAC systems but does not include walls, flooring, or other finishes. However, the basic infrastructure provided makes it operational for occupancy and cost effective for tenants. In dimensional metrics, warm- and cold-shelled spaces are measured in terms of BGSF and Departmental Gross Square Footage (DGSF). Specific exterior envelope materials are also assessed in terms of their ratios to the exterior surface area. These spaces can be found in various facility types. They can significantly impact the cost per BGSF since they add square footage despite being unfinished, accounting for a substantial cost in constructing a new facility. The presence of a shell space—warm or cold—adds to the total square footage of the building despite the space being underdeveloped. Therefore, when calculating the BGSF, differences between the cost of a shell space and the built-out structure develop inconsistencies in the normalized BGSF for the total square footage of the building. This challenge can be mitigated by developing separate adjustment factors for warm and cold shell spaces, which copes with the inaccuracy in the total normalized BGSF. Since space adjustment for the final metric computations is distinctive to healthcare benchmarking methods, it is essential to study space-based adjustments for healthcare facilities.
Based on the background study, this paper is an extension to an approach to the normalization of the TIC and phase-based project cost; however, there is a gap in the research regarding normalizing cost elements of HCFs. Due to the complexity of HCFs, this paper proposes another possible approach for normalizing healthcare facility costs, i.e., by normalizing individual HCF cost elements. In addition, it is necessary to know how to normalize CSIMF cost elements (i.e., HVAC, foundations, etc.), which is the study’s focus. CSI UniFormat is a categorization system for various building components, systems, and assemblies, offering a structured approach for design and operational considerations throughout a building’s existence. This paper does not include procedures for normalizing cost elements based on CSI UniFormat. The previous benchmarking and normalization methods lack guidance on space adjustments for two identical building structures, while this study paves the ground for space normalization of healthcare facilities.

3. Methodology

3.1. Selection of Cost Indices

Multiple healthcare industry leaders, subject matter experts, and researchers (steering committee) within the National Healthcare Facilities Benchmarking Program (NHCFBP) developed standardized definitions for metrics relevant to HCFs and identified HCF-specific and CSIMF cost elements most relevant to HCFs. The Healthcare Facilities Benchmarking Program developed the metrics framework for the category costs, schedule, safety, rework, and changes unique to HCFs. Cost metrics included relative and absolute metrics, where absolute metrics like the dollar per square foot needed normalization for time and location for meaningful comparisons [1]. A comparative analysis of all the publicly available cost indices within the framework was conducted. This study presents a cost normalization framework for construction cost elements, adhering to the previously established guidelines of a normalization framework for TIC and phase-based approaches. The cost indices reviewed in the background study were first compared based on their use in the healthcare sector, designated purpose, public availability, representation of market conditions, and consideration of construction cost elements. Appropriate indices for normalization by HCF-specific and CSIMF cost elements with respect to location and time adjustment were established through this study.
During the steering committee discussions, certain criteria were established before reviewing the available cost indices for an appropriate selection. First, the indices were reviewed for their particular use in the healthcare sector, as many cost indices have been created to suit a particular industry or establish cost adjustment in a certain way [35]. Selection of the most suitable cost index is critical to developing preliminary cost estimates with an accuracy of +/−20% [36]. Second, they were reviewed for their designated purpose, i.e., for location and/or time adjustment. Third, the indices were reviewed to gauge their representation of the wide pool of identified cost elements, such as material, labor, equipment, contractor expenses, profit margins, local taxes, etc. Table 5 illustrates a detailed study of the available indices and their applicability to the cost elements. Lastly, the index values were reviewed based on their reflection of the economic trends and local market conditions to establish their reliable use for time adjustment (Figure 1). Due to the wide availability of input and output indices, all the available cost indices were compared over time to examine the impact of the 2008 economic downturn (Figure 1).
As a result, RSMeans CCI, ENR—CCI, ENR—BCI, Turner Cost Index, RLB, and BLS-PPI NAICS 236224 (BLS, 2016) were observed to have a specific use in the healthcare sector. Further, RSMeans CCI and RLB were observed to have been designed for location adjustment; therefore, their public availability was considered. RSMeans CCI collects data in over 970 cities in the U.S. In contrast, RLB collects data in over 12 cities in the U.S., as illustrated in Table 5. Both RSMeans and RLB track cost data for specific cost elements, indicating that both indices reflect changing market conditions. However, when compared based on their stability post-2008 economic downturn, the RSMeans CCI was observed to have shown more stability in terms of economic growth than RLB. After carefully analyzing the above-mentioned decision criteria, the RSMeans CCI was chosen for location adjustment of the HCF-specific and CSIMF cost elements. The Hanscomb Means International Cost Index was chosen for international projects, as the previous cost normalization frameworks used the same index for location adjustment [1,8,9]. For validation, the RSMeans CCI and RLB were compared using a hypothetical example to calculate the difference between the initial and normalized value using both indices (Table 6). As the normalized cost using RSMeans was closer to the initial value than the normalized value using RLB, the RSMeans CCI was chosen for location adjustment within the United States. For time adjustment, the RSMeans HCI, ENR-BCI, ENR-CCI, Turner Cost Index, RLB, and BLS-PPI were considered for further comparison. Indices, namely Turner, RLB, and BLS-PPI, were observed to track cost data beyond the material, labor, and equipment costs as opposed to the RSMeans HCI, ENR-CCI, and ENR-BCI. Furthermore, RLB and BLS-PPI represented cost elements beyond material and labor productivity as opposed to the Turner cost index. However, compared to their reflection of the changing market conditions and stability post-2008 economic downturn, the Turner cost index demonstrated the highest fluctuation, whereas the RSMeans HCI and BLS-PPI showed great stability (Figure 1). In Figure 1, the sources for the comparison of cost indices were, RSMeans data, 2023; Turner Construction Company, 2023; ENR, 2022; DoD, 2023; RLB, 2022; BLS, 2016. Also, all the available index values were normalized to the reference year 2008 with an index value of 100 to understand the stability of the index values.
Since BLS-PPI was a relatively new cost index—developed in 2012, it was not affected by the 2008 economic downturn. Since RLB represented a Global Construction Cost Relativity Index, as opposed to BLS-PPI, which was focused on the market conditions in the U.S., this study chose a similar approach as the normalization framework for TIC [8] by ultimately choosing a hybrid index of RLB and BLS-PPI [26] for time adjustment for projects before 2012. For normalizing cost elements of projects after 2012, BLS-PPI’s new healthcare building construction with the base year of 2012 was chosen for normalization. This analysis was validated using a hypothetical example to calculate the difference between the initial and normalized values using both indices, as shown in Table 6.

3.2. Normalization Framework for CSIMF Cost Elements

The normalization framework developed in this study adheres explicitly to CSIMF cost elements. This framework follows a similar approach to the normalization procedures for each identified cost element, as proposed by [8], for the overall project cost (Appendix A); however, it is altered to cater to MasterFormat cost elements (Figure 2). The three key elements critically influencing cost normalization for project benchmarking are (1) project currency, (2) project location, and (3) the point in time considered for cost normalization, which were the basis of designing this framework (Figure 2).
Currency conversion is proposed as a first step for projects outside of the U.S., with respect to the appropriate market exchange rate to U.S. dollars at the midpoint of construction. As [8] established, the next two steps in normalization consider the project location and the time at the midpoint of the construction phase. However, in the absence of the midpoint of the construction phase, the entire normalization process is advised to be aborted altogether. As a first step, an appropriate set of cost indices was identified through a complete evaluation of publicly available cost indices. Since RSMeans represented the most stability, including changing market conditions, and a set of indices tailored to the CSI MasterFormat (MF) cost elements, it was chosen as the most suitable cost index for normalization. Therefore, the framework proposed by the RSMeans MasterFormat (MF) index for location adjustment at the midpoint of the construction phase. An inconsistency was observed while developing this framework concerning the CSIMF divisions. Differences in the division I.D.s and descriptions of cost elements were observed in the CSIMF before and after 2005. Due to the lack of a previous study based on the normalization of CSIMF cost elements, this challenge has yet to be addressed. Therefore, Appendix C outlines a detailed mapping of each cost element conducted to cope with these differences. Each question I.D., MF division, and the question name referring to each CSI division were considered during this process to gauge the appropriate steps to be followed for normalization.
The Hanscomb Means International Cost Index should be used for location adjustment for international projects. Depending upon the availability of the project location, the process either continues for location adjustment using the RSMeans MasterFormat index or proceeds for time adjustment using the RLB/BLS-PPI index in the most recent year. Similarly, suppose the breakdown of MasterFormat costs is unavailable. In that case, this framework proposes that the available costs should be normalized for time using the RSMeans MasterFormat index at the midpoint of the construction phase. Both location and time adjustment should use the standard normalization equations. If a shell space, either warm or cold, exists within a structure, the framework proposes shell cost adjustment at this stage. The cost adjustment for the shell space cost is discussed in the next section. This initial framework (Figure 2) was validated using a case study illustrated in Appendix B and established post-discussion with the steering committee.

3.3. Space-Based Normalization Framework for TIC

To complete the normalization approach for healthcare facility costs, the effects of shell spaces on overall project costs were studied through background study. A shell space in a healthcare facility was observed to be crucial in normalizing the project cost per BGSF due to the additional square footage, irrespective of the finishes. A cold shell is a non-habitable space within a building with no finishes or mechanical systems, whereas a warm shell includes heating, ventilation, and air conditioning. A need for a separate normalization of shell space costs was established through background study, as inconsistencies were observed in the normalized cost per BGSF of healthcare projects with warm or cold shell spaces present. Two healthcare projects cannot be compared appropriately if one includes a shell space while the other does not. To be comparable, the shell space in one structure must be separated from the total square footage. Once separated, both the structures have a similar built-out program and finished spaces, and a more accurately comparable cost per BGSF can be evaluated.
This study conducted a detailed discussion with the steering committee and healthcare sector experts to understand the impact of shell space on the overall cost per BGSF. Dollar per square foot values for a 100,000-square-foot facility that is completely built out compared to another 100,000-square-foot facility with a 20,000-square-foot shell space will be distinct. Researchers populated similar examples of HCFs and normalized ratios by dividing the square footage of such spaces to calculate the overall impact on the BGSF. The steering committee was presented with the range of ratios resulting from the calculations for validation. Based on the feedback, to adjust the square footage or cost of such facilities for meaningful comparison, fixed cost adjustment rates of 0.35 for warm shell and 0.50 for cold shell were identified. The proposed cost adjustment factors were validated by implementing the adjustment rates into a case study. As shown in Table 7, a hypothetical healthcare project (MOB) is normalized for a shell space using a fixed adjustment rate of 0.5 or 0.35, depending upon the type of the shell space. This case study demonstrates the adjustment of total BGSF by deducting the adjusted square footage for a cold shell space using 0.5 as an adjustment factor. For a warm shell space, 0.35 would be used as the adjustment rate.
As the first step, the total square footage—BGSF–of the cold shell space was multiplied by the adjustment rate 0.5 to evaluate the cost of equivalent square footage due to shell space. This value is then deducted from the total project BGSF to evaluate the final equivalent square footage of a building—BGSF. The resulting value for the BGSF excludes unfinished shell spaces and will provide a more accurate and comparable BGSF for evaluating the cost per BGSF. A similar approach for other areas of space in healthcare facilities can be used to identify newer crosswalks for a better parametric assessment of cost and space.

4. Case Study—Methodology Demonstration and Validation—Normalization of CSIMF Cost Elements

This study proposed a tailored normalization framework for MasterFormat cost elements, as illustrated in Figure 2. This study conducted a detailed identification and assessment of individual cost elements to validate this framework. Further, depending on the data availability to ensure calculations for different scenarios, a healthcare project based in St. Louis, Missouri, was identified to implement the proposed framework. The project has been sourced from the Healthcare Facility Database (HCFD), which was developed as a resource for the healthcare community as part of the NHCFBP discussed in [1] to ensure reliability and accuracy in evaluations and generalization of findings. The identified HCF-specific and CSIMF cost elements were assigned individual steps in normalization, as the design, A/E, CM, and capital medical equipment costs would only require time adjustment. The previous framework for TIC was applied to individual phase costs and the HCF cost elements (Appendix A); however, a separate framework for CSIMF cost elements was applied as described in Appendix B based on Figure 2. From the summary of cost indices and the discussion with the steering team, the RSMeans CCI index was used for location adjustment, and BLS-PPI NAICS 236224 was used for time adjustment.

4.1. Normalization of CSIMF Cost Elements with Comparison to the Construction Phase Cost

Healthcare facilities are complex building structures that require flexible and adaptable solutions for effective facility management. Therefore, extra attention is required to the details of the design and project costs. The background study shows that this concern has been addressed before by proposing external benchmarking and cost normalization frameworks for HCFs. Previous research on the subject matter has established a normalization framework for TIC; however, it does not consider CSIMF cost elements.
The CSIMF cost element normalization did not require currency conversion, as the chosen case study was based in the U.S. For step 1—Location Adjustment (LA), RSMeans MasterFormat index for St. Louis (Missouri) at the midpoint of construction—2012 was used to normalize the cost of CSIMF cost elements to a baseline location—Chicago at the midpoint of construction—2012. As the location of this project was known and based in the U.S., RSMeans MasterFormat indices for 2012 and 2022 were chosen as appropriate indices for time adjustment.
Table 8 illustrates an example of CSIMF cost elements and their normalization procedure. A similar approach was utilized for normalizing all other CSIMF cost elements (Appendix C). Since CSIMF cost elements represent a breakdown of the construction phase cost, the combined normalized cost of CSIMF cost elements is compared to the normalized construction phase cost. As illustrated in Table 9, a delta of USD 2,774,361 (Δ) was observed between the final normalized costs. This delta was further normalized using the RSMeans MasterFormat cost indices and added to the normalized cost of CSIMF cost elements. As evident in Table 9, the normalized costs of CSIMF cost elements and the construction phase cost reached a comparable final value and were validated through the proposed framework. It should be noted that no design, A/E, CM, or capital medical equipment costs were deducted for normalization since CSIMF cost elements primarily represent the construction phase costs only. For example, CSIMF Division 11 represents a total equipment cost; however, it is not equivalent to the capital medical equipment cost, and therefore, it should be normalized for location.

4.2. Normalization of HCF-Specific Cost Elements with Comparison to Project Life-cycle Phase Costs

In previous studies, implementing the normalization framework established for TIC has not considered normalizing individual phase costs and HCF-specific cost elements. Therefore, this study established applicability by a separate normalization framework tailored to HCF-specific cost elements.
In Table 10 above, the framework for TIC normalizes the individual phase costs and HCF-specific cost elements, presenting a robust approach towards normalization. Comparing the almost equivalent values obtained from the total normalized phase (of project life cycle) costs, i.e., USD 13,411,825, and the total of normalized HCF-specific cost elements, i.e., USD 13,411,827, validates the framework’s approach (Table 10).

5. Results and Discussion

Healthcare projects require extreme precision during the design and construction phases. Therefore, a robust benchmarking program and a cost normalization framework are developed with the help of industry and real-life projects. The background study addresses a cost normalization framework for TIC but does not consider HCF-specific cost elements and CSIMF division costs. It suggests an alternative approach to normalizing healthcare cost elements such as medical equipment costs within HCF and CSIMF cost elements, such as HVAC and foundations, etc. Unlike previous benchmarking and normalization methods that lack guidance on adjusting space for two identical building structures, this research also establishes a foundation for the space normalization of healthcare facilities.

5.1. Selection of Cost Indices

The RSMeans CCI was selected for adjusting the location of HCF-specific and CSIMF cost elements. In evaluating their resilience following the 2008 economic downturn, it was observed that the RSMeans CCI demonstrated greater stability in economic growth compared to RLB. Additionally, it provided many cities (970) covering most of the US as options for normalization. For time adjustment, a hybrid index of RLB and BLS-PPI was selected for projects before 2012. Further, for projects after 2012, BLS-PPI NAICS 236224, with the base year of 2012, was chosen for normalization. BLS-PPI NAICS 236224 is designed specifically for healthcare projects with the added stability of the BLS index with expected permanence.

5.2. Normalization Framework for HCF-Specific Cost Elements and CSIMF Cost Elements

The study validated the proposed framework for TIC to normalize individual phase costs and HCF-specific cost elements. Further, the framework was tested by finding the values of normalized CSIMF cost elements and the construction phase cost comparable. The results indicated that 1) the final normalized cost of the healthcare facility remains the same irrespective of the approach used for normalization, i.e., using TIC, individual phase costs, or HCF-specific cost elements, and 2) the final normalized cost of the construction phase can be determined by normalizing the total construction phase cost or individual CSIMF cost elements (Table 9). However, a delta (Δ) difference, in Section 4.1, was observed between the final normalized construction phase cost and the total of individually normalized CSIMF cost elements. This delta was further normalized and added to the normalized cost of CSIMF cost elements to arrive at a comparable value.

5.3. Space-Based Normalization

In the case study analysis and with feedback from the steering committee, the adjustment cost factors were identified as follows:
(1)
Total BGSF modification is validated by subtracting the adjusted square footage for a cold shell space, employing a 0.5 adjustment factor.
(2)
In the case of a warm shell space, the adjustment rate was identified as 0.35.

6. Conclusions and Path Forward

In conclusion, this research study aimed to develop a comprehensive normalization framework for HCF costs.
(1) The study identified and recommended a set of indices best suited for time and location adjustments to achieve this goal: RSMeans CCI index and BLS-PPI NAICS 236224, along with the expected results via a case study. Selection of the most suitable cost index can assist various stakeholders, such as estimators, healthcare system facility managers, etc., with early estimates and condition assessments of the facilities.
(2) These adjustments were determined by building upon a previously established framework, revealing a shortfall in applying CSIMF cost elements. Therefore, evaluating the normalization framework applicable to TIC for phase costs and HCF-specific cost elements informed the development of a specific normalization framework for CSIMF cost elements. The case study analysis justified the presence of a cost accuracy gap limited to the construction phase of a project. Normalization of the construction phase cost and mapping to total normalized costs using CSIMF cost elements validated the framework developed for CSIMF costs.
The current study outlined HCF cost normalization approaches for overall project costs, individual phase costs, and individual cost elements. The overarching findings have significant implications for HCF owners seeking to improve the accuracy of cost projections and benchmarking procedures. The CSIMF framework capitalizes on cost elements that enable pre-construction stakeholders to understand the detailed factors affecting overall project costs. The benefit of early cost indicators promotes positive overall project health in terms of cost accuracy. Further metrics calculated using the normalized costs are intended to understand if the project phase has efficiently used financial or human resources.
(3) Additionally, establishing fixed cost adjustment rates for cold (0.5) and warm (0.35) shell spaces reveals significant impacts when included in the overall project costs. Therefore, cost adjustments for shell spaces must further consider time and location constraints separately in the overall project cost to improve normalization accuracy.
Looking to the future, the study identified combinations of input and output indices inclusive of factors such as escalation. To best understand escalation and its relationship to the input and output indices of the normalization framework, a sensitivity analysis is recommended for various scenarios. While this study does not provide an in-depth analysis of escalation, it does provide foundational elements that lead toward applications of indices affecting healthcare cost predictions for accuracy in determining overall project costs.

Author Contributions

Conceptualization, V.S. and C.H.C.; Methodology, V.S.; Formal analysis, V.S. and P.B.; Investigation, V.S. and C.H.C.; Resources, V.S., C.H.C. and D.G.; Writing—original draft, V.S.; Writing—review & editing, V.S., C.H.C., D.G. and P.B.; Supervision, V.S., C.H.C. and D.G. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

Data is contained within the article and Appendix A, Appendix B and Appendix C. The data presented in this study are available in Appendix A, Appendix B and Appendix C.

Conflicts of Interest

The authors declare no conflicts of interest.

Appendix A

Figure A1 discusses the normalization procedure and framework for Total Installed Cost (TIC).
Figure A1. Normalization procedure and framework for TIC. (* refer to Section 2.2 for Cost normalization procedure and Table 4 for calculation).
Figure A1. Normalization procedure and framework for TIC. (* refer to Section 2.2 for Cost normalization procedure and Table 4 for calculation).
Buildings 14 00529 g0a1

Appendix B

This appendix tabulates the normalization of Phase costs, HCF-specific and CSIMF cost elements through a case study.
Table A1. Case study—Normalization of Phase costs 1.
Table A1. Case study—Normalization of Phase costs 1.
IDCost CategoryQuestion Name—
Revised
Cost (USD)Normalization MethodLocation
Adjustment 2
Time
Adjustment 3
Cost after LA (USD)Final
Normalized Cost (USD)
101Phase costFEP—Actual CostUSD 10,806LA and TA USD 12,345USD 18,202
103Phase costDetail Design (DD)—Actual Cost 1USD 437,253TA-USD 644,696
105Phase costProcurement—
Actual Cost 1
USD 1,740,773TA-USD 2,566,636
107Phase costConstruction—
Actual Cost 1
USD 6,013,294LA and TAUSD 6,869,733USD 10,128,894
113Phase costActivation/
Move-in—Actual Cost
USD 31,701LA and TAUSD 36,216USD 53,397
TOTALUSD 8,233,827 USD 6,918,294USD 13,411,825
1 Using normalization framework for TIC. 2 LA: RSMeans Missouri 2012 = 199.5; RSMeans Chicago 2012—226.9. 3 TA: BLS-PPI 2012 = 100; BLS-PPI 2021 = 132.7.
Table A2. Case study—Normalization of HCF-specific cost elements 1.
Table A2. Case study—Normalization of HCF-specific cost elements 1.
IDCost CategoryQuestion Name—
Revised
Cost (USD)Normalization MethodLocation
Adjustment 2
Time
Adjustment 3
Cost after LA (USD)Final
Normalized Cost (USD)
2147HC-specific costsTotal Site development on-site USD 348,781LA and TAUSD 398,456USD 587,493
2148HC-specific costsSite development
off-site
USD 258,009LA and TAUSD 294,756USD 434,595
2149HC-specific costsBuilding Construction (including excavation within 5′ of the
building)
USD 5,025,365LA and TAUSD 5,741,099USD 8,464,810
2155HC-specific costsFurnishingsUSD 13,001LA and TAUSD 14,853USD 21,899
2152HC-specific costsOwner’s miscellaneous USD 124,198LA and TAUSD 141,886USD 209,201
2156HC-specific costsArtwork and plantsUSD 26,417LA and TAUSD 30,179USD 44,497
2157HC-specific costsITUSD 108,822LA and TAUSD 124,321USD 183,302
2195HC-specific costsRoof gardenUSD 1,300LA and TAUSD 1,485USD 2,190
2197HC-specific costsMechanical tunnelUSD 118,208LA and TAUSD 135,044USD 199,112
2159HC-specific costsCommissioning costUSD 31,701LA and TAUSD 36,216USD 53,397
2151HC-specific costsCM Pre-construction feesUSD 35,194TA-USD 51,891
2158HC-specific costsProject management and agent feesUSD 178,589TA-USD 263,316
2150HC-specific costsProfessional fees (A/E and Consulting
Engineers)
USD 448,059TA-USD 660,629
2153HC-specific costsCapital Medical
equipment
USD 947,070TA-USD 1,396,381
2338Medical
equipment
Reused medical
equipment
USD 131,365TA-USD 193,687
2339Medical
equipment
Food service
equipment
USD 75,164TA-USD 110,824
2340Medical
equipment
Security SystemsUSD 37,269TA-USD 54,950
2341Medical
equipment
Scrub sinksUSD 4,419TA-USD 6,515
2342Medical
equipment
Sterilization
equipment
USD 45,750TA-USD 67,455
2343Medical
equipment
Cart washerUSD 3,997TA-USD 5,893
2344Medical
equipment
Laboratory or
pharmacy casework
USD 22,135TA-USD 32,636
2345Medical
equipment
Patient monitoring
system
USD 71,870TA-USD 105,967
2346Medical
equipment
Nurse Call SystemsUSD 5,712TA-USD 8,421
2347Medical
equipment
OR lightingUSD 34,627TA-USD 51,055
2348Medical
equipment
HeadwallsUSD 33,795TA-USD 49,828
2351Medical
equipment
Paper Towels, toilet
accessories, soap
dispensers
USD 13,413TA-USD 19,776
2352Medical
equipment
Equipment seismic bracingUSD 5,524TA-USD 8,145
2353Medical
equipment
OtherUSD 84,075TA-USD 123,962
TOTALUSD 8,233,829 USD 6,918,295USD 13,411,827
1 Using normalization framework for TIC. 2 LA: RSMeans Missouri 2012 = 199.5; RSMeans Chicago 2012—226.9. 3 TA: BLS-PPI 2012 = 100; BLS-PPI 2021 = 132.7.
Table A3. Case study—Normalization of CSIMF cost elements 1.
Table A3. Case study—Normalization of CSIMF cost elements 1.
IDCost CategoryQuestion Name—
Revised
Cost (USD)Normalization MethodLocation
Adjustment 2
Time
Adjustment 3
Cost after LA (USD)Final
Normalized Cost (USD)
2165MasterFormat costsDivision 01—Total
General Requirements
USD 172,907LA and TAUSD 196,692USD 209,681
2166MasterFormat costsDivision 03—Total
Concrete
USD 437,850LA and TAUSD 550,477USD 572,304
2167MasterFormat costsDivision 04—Total
Masonry
USD 372,291LA and TAUSD 461,599USD 529,893
2168MasterFormat costsDivision 05—Total MetalsUSD 340,158LA and TAUSD 338,903USD 326,677
2169MasterFormat costsDivision 06—Total Wood and PlasticsUSD 209,956LA and TAUSD 281,142USD 242,371
2170MasterFormat costsDivision 07—Total
Thermal and Moisture Protection
USD 324,250LA and TAUSD 369,136USD 415,592
2171MasterFormat costsDivision 08—Total Doors and WindowsUSD 350,859LA and TAUSD 391,892USD 422,840
2172MasterFormat costsDivision 09—Total
Finishes
USD 413,720LA and TAUSD 535,522USD 546,890
2173MasterFormat costsDivision 10—Total
Specialties
USD 1,713LA and TAUSD 1,790USD 1,875
2174MasterFormat costsDivision 11—Total
Equipment
USD 16,502LA and TAUSD 17,241USD 18,062
2175MasterFormat costsDivision 12—Total
furnishings
USD 13,001LA and TAUSD 13,583USD 14,230
2176MasterFormat costsDivision 13—Total Special ConstructionUSD 17,724LA and TAUSD 18,518USD 19,399
2177MasterFormat costsDivision 14—Total
conveying systems
USD 112,876LA and TAUSD 117,930USD 123,546
2178MasterFormat costsDivision 21—Total Fire SuppressionUSD 68,034LA and TAUSD 76,894USD 84,536
2179MasterFormat costsDivision 22—Total PlumbingUSD 284,185LA and TAUSD 321,191USD 353,112
2180MasterFormat costsDivision 23—Total HVACUSD 480,775LA and TAUSD 543,380USD 597,384
2182MasterFormat costsDivision 26—Total
Electrical
USD 564,130LA and TAUSD 616,096USD 721,636
2183MasterFormat costsDivision 27—Total
communications
USD 106,822LA and TAUSD 116,662USD 136,647
2184MasterFormat costsDivision 28—Total
electrical safety and
security
USD 52,287LA and TAUSD 54,628USD 57,230
2186MasterFormat costsDivision 31—Total
Earthwork
USD 606,790LA and TAUSD 627,648USD 699,704
2187MasterFormat costsDivision 32—Total
Exterior Improvements
USD 323,291LA and TAUSD 334,404USD 372,795
2188MasterFormat costsDivision 33—Total
Utilities
USD 112,766LA and TAUSD 116,642USD 130,033
2191MasterFormat costsDivision 007200—
Contractor’s General
Conditions
USD 323,223LA and TAUSD 367,685USD 391,967
2192MasterFormat costsDivision 008100—
Contractor’s Fee
USD 138,214LA and TAUSD 157,227USD 167,610
2193MasterFormat costsDivision 007316—
Insurance
USD 56,423LA and TAUSD 64,184USD 68,423
2602MasterFormat costsDivision 25—Total
integrated automation
USD 51,755LA and TAUSD 54,072USD 56,647
2603MasterFormat costsDivision 02—Total
Existing Conditions
(natural)
USD 4,396LA and TAUSD 4,547USD 5,069
2607MasterFormat costsDivision 007318—BondsUSD 56,388LA and TAUSD 64,144USD 68,380
TOTALUSD 6,013,286 USD 6,813,829USD 7,354,533
1 Using normalization framework for CSIMF cost elements. 2 LA: RSMeans CSIMF Missouri 2012; RSMeans CSIMF Chicago 2012. 3 TA: BLS-PPI 2012 = 100; BLS-PPI 2021 = 132.7.

Appendix C

This appendix tabulates the data mapping for the MasterFormat divisions prior to 2005 and after 2005.
Table A4. MasterFormat divisions—data mapping.
Table A4. MasterFormat divisions—data mapping.
RSMEANS
CSI DIVISIONS
(PRIOR TO 2005)
RSMEANS
CSI DIVISIONS (2005)
QUESTIONNAIRE
DESCRIPTION (16.2)
CSI
Division ID
01590Equipment Rental015433Contractor
Equipment
NoneNone1
02Site Construction0241, 31–34Site and Infrastructure, DemolitionDiv. 2Total Existing Conditions (natural)2
02Site Construction0241, 31–35Site and Infrastructure, DemolitionDiv. 31Total Earthwork2
02Site Construction0241, 31–36Site and Infrastructure, DemolitionDiv. 32Total Exterior
Improvements
2
02Site Construction0241, 31–37Site and Infrastructure, DemolitionDiv. 33Total Utilities2
02Site Construction0241, 31–38Site and Infrastructure, DemolitionDiv. 34Total Transportation2
03Concrete03ConcreteDiv. 3Total Concrete3
04Masonry04MasonryDiv. 4Total Masonry4
05Metals05MetalsDiv. 5Total Metals5
06Wood & Plastics06Wood, Plastics, and CompositesDiv. 6Total Wood and Plastics6
07Thermal and Moisture Protection07Thermal and Moisture ProtectionDiv. 7Total Thermal and
Moisture Protection
7
08Doors and Windows08OpeningsDiv. 8Total Doors and Windows8
09Finishes09FinishesDiv. 9Total Finishes9
10–14Divs. 10–14CoversDivs. 10–14, 25, 28, 41, 43, 44, 46Div. 10Total Specialties10
10–14Divs. 10–14CoversDivs. 10–14, 25, 28, 41, 43, 44, 47Div. 11Total Equipment10
10–14Divs. 10–14CoversDivs. 10–14, 25, 28, 41, 43, 44, 48Div. 12Total Furnishings10
10–14Divs. 10–14CoversDivs. 10–14, 25, 28, 41, 43, 44, 49Div. 13Total Special Construction10
10–14Divs. 10–14CoversDivs. 10–14, 25, 28, 41, 43, 44, 50Div. 14Total Conveying Systems10
10–14Divs. 10–14CoversDivs. 10–14, 25, 28, 41, 43, 44, 51Div. 25Total Integrated
Automation
10
10–14Divs. 10–14CoversDivs. 10–14, 25, 28, 41, 43, 44, 52Div. 28Total Electrical Safety and Security10
10–14Divs. 10–14CoversDivs. 10–14, 25, 28, 41, 43, 44, 53Div. 41Total Material Processing and Handling Equip10
10–14Divs. 10–14CoversDivs. 10–14, 25, 28, 41, 43, 44, 54Div. 44Total Pollution and Waste Control Equipment10
10–14Divs. 10–14CoversDivs. 10–14, 25, 28, 41, 43, 44, 55Div. 46Total Water and Wastewater Equip.10
15Mechanical21, 22, 23 Fire Suppression, Plumbing and HVACDiv. 21Total Fire Suppression11
15Mechanical21, 22, 24Fire Suppression, Plumbing and HVACDiv. 22Total Plumbing11
15Mechanical21, 22, 25Fire Suppression, Plumbing and HVACDiv. 23Total HVAC11
16Electrical26, 27, 3370 Electrical, Communications and Util.Divi. 26Total Electrical 12
16Electrical26, 27, 3371Electrical, Communications and Util.Div. 27Total Communications12
16Electrical26, 27, 3372Electrical, Communications and Util.Div. 48Total Electrical Power
Generation
12
0–16Weighted AverageMF2010Weighted AverageDiv. 01Total General
Requirements
13
0–16Weighted AverageMF2010Weighted AverageDiv. 008300Construction Contingency13
0–16Weighted AverageMF2010Weighted AverageDiv. 007200Contractor’s General
Conditions
13
0–16Weighted AverageMF2010Weighted AverageDiv. 007210Supervision Cost
0–16Weighted AverageMF2010Weighted AverageDiv. 008100Contractor’s Fee 13
0–16Weighted AverageMF2010Weighted AverageDiv. 007316Insurance13
0–16Weighted AverageMF2010Weighted AverageDiv. 007318Bonds13
0–16Weighted AverageMF2010Weighted AverageDiv. 008700Local Taxes13
0–17Weighted AverageMF2010Weighted AverageDiv. 00USD Subtotal Division 0 Cost13

References

  1. Sharma, V.; Caldas, C.; Mulva, S. Development of metrics and an external benchmarking program for Healthcare Facilities. Int. J. Constr. Manag. 2021, 21, 615–630. Available online: https://www.tandfonline.com/doi/full/10.1080/15623599.2019.1573490 (accessed on 25 April 2023). [CrossRef]
  2. Maier, D. The Influence of the COVID-19 Pandemic on the Construction Technology Works. In Proceedings of the 37th IBIMA Conference, Cordoba, Spain, 30–31 May 2021; Available online: https://www.researchgate.net/publication/353394199_The_influence_of_the_COVID-19_Pandemic_on_the_Construction_Technology_works (accessed on 25 April 2023).
  3. Singhal, S.; Patel, N. The Future of US Healthcare: What’s Next for the Industry Post-COVID-19. McKinsey & Company, 2022. Available online: https://www.mckinsey.com/industries/healthcare/our-insights/the-future-of-us-healthcare-whats-next-for-the-industry-post-covid-19 (accessed on 25 April 2023).
  4. Little, J. Three Key Trends Guiding Healthcare Construction in 2022. Charlotte, NC. Available online: https://premierinc.com/newsroom/blog/three-key-trends-guiding-healthcare-construction-in-2022 (accessed on 25 April 2023).
  5. Enache-Pommer, E.; Horman, M.J.; Messner, J.I.; Riley, D. A Unified Process Approach to Healthcare Project Delivery: Synergies between Greening Strategies, Lean Principles, and BIM. ASCE Library, Construction Research Congress. 2010. Available online: https://ascelibrary.org/doi/10.1061/41109%28373%29138 (accessed on 25 April 2023).
  6. Sharma, V.; Caldas, C.H.; Mulva, S.P. Identification and Prioritization of Factors Affecting the Overall Project Cost of Healthcare Facilities. ASCE Libr. J. Constr. Eng. Manag. 2020, 146, 04019106. Available online: https://ascelibrary.org/doi/10.1061/%28ASCE%29CO.1943-7862.0001692 (accessed on 25 April 2023). [CrossRef]
  7. Lu, J.; Price, A. Dealing with Complexity Through More Robust Approaches to the Evidence-Based Design of Healthcare Facilities. Health Environ. Res. Des. J. 2011, 4, 3–7. Available online: https://journals.sagepub.com/doi/full/10.1177/193758671100400401 (accessed on 25 April 2023). [CrossRef] [PubMed]
  8. Sharma, V.; Yun, S.; Oliveira, D.P.; Mulva, S.P.; Caldas, C.H. Development of a cost normalization procedure for National Health Care Facility Benchmarking. In Proceedings of the 5th International Construction Specialty Conference of the Canadian Society for Civil Engineering (ICSC), Vancouver, BC, Canada, 7–10 June 2015; Available online: https://open.library.ubc.ca/soa/cIRcle/collections/52660/items/1.0076452 (accessed on 25 April 2023).
  9. Choi, J.; Yun, S.; de Oliveira, D.P. Developing a cost normalization framework for phase-based performance assessment of Construction Projects. Can. J. Civ. Eng. 2016, 43. Available online: https://cdnsciencepub.com/doi/abs/10.1139/cjce-2016-0223 (accessed on 25 April 2023). [CrossRef]
  10. Van Lent, W.A.; de Beer, R.D.; van Harten, W.H. International Benchmarking of specialty hospitals. A series of case studies on Comprehensive Cancer Centres. BMC Health Serv. Res. 2010, 10, 1–11. [Google Scholar] [CrossRef] [PubMed]
  11. Benson, H.R. An introduction to benchmarking in Healthcare. Radiol. Manag. 1994, 16, 35–39. Available online: https://pubmed.ncbi.nlm.nih.gov/10139084/ (accessed on 25 April 2023).
  12. Kumar, A.; Antony, J.; Dhakar, T.S. Integrating quality function deployment and benchmarking to achieve greater profitability. Benchmarking: Int. J. 2006, 13, 290–310. Available online: https://www.emerald.com/insight/content/doi/10.1108/14635770610668794/full/html (accessed on 25 April 2023). [CrossRef]
  13. Kozak, M.; Rimmington, M. Benchmarking: Destination attractiveness and small hospitality business performance. Int. J. Contemp. Hospit. Manag. 1998, 10. Available online: https://www.emerald.com/insight/content/doi/10.1108/09596119810227767/full/html (accessed on 25 April 2023). [CrossRef]
  14. Malec, H.A. Benchmarking barometers for products and Processes. Qual. Reliab. Eng. Int. 1994, 10, 455–465. [Google Scholar] [CrossRef]
  15. Roark, K.; Brooks, B.; Kilgore, K. Costs and benefits of shell space construction. Healthc. Financ. Manag. J. Healthc. Financ. Manag. Assoc. 1993, 47, 46–52. [Google Scholar]
  16. Dai, J.; Mulva, S.; Suk, S.-J.; Kang, Y. Cost Normalization for Global Capital Projects Benchmarking. Construction Research Congress. Available online: https://ascelibrary.org/doi/10.1061/9780784412329.241 (accessed on 25 April 2023).
  17. Hwang, B.G.; Thomas, S.R.; DeGezelle, D.; Caldas, C.H. Development of a benchmarking framework for Pharmaceutical Capital Projects. Constr. Manag. Econ. 2008, 26, 177–195. [Google Scholar] [CrossRef]
  18. Yun, S.; Choi, J.; de Oliveira, D.P.; Mulva, S.P. Development of performance metrics for phase-based Capital Project Benchmarking. Int. J. Proj. Manag. 2016, 34, 389–402. [Google Scholar] [CrossRef]
  19. Faithful Gould. Construction Cost Indices: Their Creation and Use. 2016. Available online: https://www.fgould.com/americas/articles/construction-cost-indices-their-creation-and-use/ (accessed on 19 February 2023).
  20. McCabe, B.Y.; O’Grady, J.; Walker, F. A Study of Construction Cost Sources. In Proceedings of the Annual Conference of the Canadian Society for Civil Engineering, Montréal, QC, Canada, 5–8 June 2002. [Google Scholar]
  21. RSMeans Data. City Cost Indexes. Gordian. 2023. Available online: https://www.rsmeansonline.com/ReferenceItems/DetailInfo/2 (accessed on 25 April 2023).
  22. Mulva, S.P.; Dai, J. Healthcare facility benchmarking. Health Environ. Res. Des. J. 2009, 3, 28–37. Available online: https://journals.sagepub.com/doi/10.1177/193758670900300104 (accessed on 25 April 2023). [CrossRef] [PubMed]
  23. Zevin, A. Cost Report—Indexes. 2022. Available online: https://digital.bnpmedia.com/publication/?i=742817&article_id=4244030&view=articleBrowser (accessed on 15 April 2023).
  24. Anon. Construction price indices: Sources and methods; Statistical Office of the European Communities, OECD: Paris, France, 1997. [Google Scholar]
  25. Sawhney, A.; Walsh, K.D.; Brown, A. International comparison of cost for the construction sector: Towards a conceptual model. Civ. Eng. Environ. Syst. 2004, 21, 151–167. [Google Scholar] [CrossRef]
  26. Mohammadian, R.; Seymour, S. An Analysis of Some Construction Price Index Methodologies. Statistics Canada, Analytical Series, Prices Division. 1997. Available online: https://www150.statcan.gc.ca/n1/en/pub/62f0014m/62f0014m1996002-eng.pdf?st=0k7CfUJ4 (accessed on 25 April 2023).
  27. U.S. Bureau of Labor Statistics. Producer Price Index for New Health Care Building Construction Sector, NAICS 236224. 2016. Available online: https://www.bls.gov/ppi/factsheets/producer-price-index-data-for-nonresidential-building-construction-sector-new-health-care-building-construction-naics-236224.htm (accessed on 25 April 2023).
  28. Turner Construction Company. Cost Index. Turner Construction Company, 2023. Available online: https://www.turnerconstruction.com/cost-index (accessed on 25 April 2023).
  29. RLB. North America Quarterly Construction Cost Report. Rider Levett Bucknall, 2022. Available online: https://www.rlb.com/americas/insight/rlb-construction-cost-report-north-america-q4-2022/ (accessed on 25 April 2023).
  30. Department of Defense. UFC 3-701-01 DOD Facilities Pricing Guide, with Change 2. National Institute of Building Sciences. 2023. Available online: https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-3-701-01 (accessed on 25 April 2023).
  31. NAVFAC. NAVFAC Building Cost Index (BCI) 2022-Q4. National Institute of Building Sciences. 2023. Available online: https://www.wbdg.org/FFC/NAVFAC/CEG/NAVFAC_BCI_2022_Q4.pdf (accessed on 25 April 2023).
  32. Ahn, J.; Ji, S.H.; Ahn, S.J.; Park, M.; Lee, H.S.; Kwon, N.; Lee, E.B.; Kim, Y. Performance evaluation of normalization-based CBR models for improving construction cost estimation. Autom. Construct. 2020, 119, 103329. [Google Scholar] [CrossRef]
  33. Rey, H. International Trade and Currency Exchange. Rev. Econ. Stud. 2001, 68, 443–464. Available online: http://www.helenerey.eu/AjaxRequestHandler.ashx?Function=GetSecuredDOC&DOCUrl=App_Data/helenerey_eu/Published-Papers_en-GB/_Documents_2012-13/71518040710_67186463733_restud.pdf (accessed on 25 April 2023). [CrossRef]
  34. United States Government Accountability Office. Gao Cost Estimating and Assessment Guide: Best Practices for Developing and Managing Capital Program Costs. GAO Applied Research and Applied Methods. United States Government Accountability Office: Washington, DC, USA, 2009. Available online: https://www.gao.gov/products/gao-09-3sp (accessed on 25 April 2023).
  35. Remer, D.S.; Lin, S.; Yu, N.; Hsin, K. An update on cost and scale-up factors, international inflation indexes and location factors. Int. J. Prod. Econ. 2008, 114, 333–346. [Google Scholar] [CrossRef]
  36. Choi, J.; Yun, S.; Oliveira, D.; Mulva, S.; Kang, Y. Cost Normalization Procedure for Phase-Based Performance Measurement. In Proceedings of the 6th International Conference on Construction Engineering and Project Management, Busan, Republic of Korea, 11–14 October 2015; pp. 72–76. Available online: https://koreascience.kr/article/CFKO201534159154275.pdf (accessed on 25 April 2023).
Figure 1. Comparison of Cost indices (Normalized to 2008 = 100).
Figure 1. Comparison of Cost indices (Normalized to 2008 = 100).
Buildings 14 00529 g001
Figure 2. Normalization framework for CSIMF cost elements. * If TIC is available, also calculate BGSF and consider the existence of cold/warm shell space. Adjust the BGSF using shell space adjustment factors and refer to space-based normalization.
Figure 2. Normalization framework for CSIMF cost elements. * If TIC is available, also calculate BGSF and consider the existence of cold/warm shell space. Adjust the BGSF using shell space adjustment factors and refer to space-based normalization.
Buildings 14 00529 g002
Table 1. Input Price Indices.
Table 1. Input Price Indices.
S. No.PublisherIndexPurposeApplicationStart YearPeriodicityPlaces
Available
1RSMeansCity Cost IndexLocation
Adjustment
BuildingCreated in 1942Quarterly296 cities
2RSMeansHistorical Cost indexTime AdjustmentBuildingCreated in 1942Quarterly30 cities
3ENR Building Cost IndexTime Adjustment
(Labor
component: 68.38 skilled labor hours)
Building1978Annually20 cities
4ENRConstruction
Cost Index
Time Adjustment
(Labor
component: 200 common labor hours)
Building—Structures1978Annually20 cities
5Marshal & SwiftEquipment
Cost Index
Time adjustmentConstruction1913AnnuallyNot
available
6Marshal & SwiftBuilding cost indexTime adjustmentBuilding1901Annually100 cities
Table 2. Output Price Indices.
Table 2. Output Price Indices.
S. No.PublisherIndexPurposeApplicationStart YearPeriodicityPlaces
Available
1Bureau of Labor StatisticsProducer Price Index—Non-Residential—New Warehouse Building ConstructionTime
Adjustment
Building—Warehouse2005MonthlyOECD Total countries
and OECD Europe countries
and G7 countries (Canada, the United States, Japan, France, Germany, Italy, and the United Kingdom)
2Bureau of Labor StatisticsProducer Price Index—Non-Residential—New Healthcare Building ConstructionTime
Adjustment
Building—Healthcare2013Monthly
3Bureau of Labor StatisticsProducer Price Index—Non-Residential—New School Building ConstructionTime
Adjustment
Building—School2006Monthly
4Bureau of Labor StatisticsProducer Price Index—Non-Residential—New Industrial Building ConstructionTime
Adjustment
Heavy
Industrial (Some), Light Industrial, and Infrastructure—Water/Waste
2008Monthly
5Bureau of Labor StatisticsProducer Price Index—Non-Residential—New Office Building ConstructionTime
Adjustment
Building–
Office
2007Monthly
6MortensonConstruction Cost IndexTime
Adjustment
Building—Non-
Residential
2009Quarterly-
7Rider Levett
Bucknall
Global Construction Cost Relativity IndexLocation
Adjustment
Building2008Quarterly12 cities
8TurnerBuilding Cost IndexTime
Adjustment
Building—Non-
Residential
2005Quarterly44 cities
Table 3. Selling Price Indices.
Table 3. Selling Price Indices.
S. No.PublisherIndexPurposeApplicationStart YearPeriodicityPlaces
Available
1Department of
Defense (DoD)
Area Cost FactorsLocation
Adjustment
Buildings-Healthcare/Residential1997Annually52 countries and the United States
Table 4. Standard Normalization procedure.
Table 4. Standard Normalization procedure.
Project Details:
Location: Indianapolis, IN, U.S.
Midpoint of Construction: 2012
(Note: Step 1—Currency Conversion
Is Not Required Since the Project is Based in the U.S.)
Step 2: Location
Adjustment (LA)
Step 3: Time
Adjustment (TA)
Normalization of
Total A/E and CM Cost
(Indianapolis to
Chicago in 2012)
(2012 to 2022 in
Chicago)
(2012 to 2022 in
Chicago)
Total Installed Cost = USD 50,000,000Intentionally left BlankIntentionally
left Blank
Intentionally left Blank
Total A/E + CM + Capital medical equipment cost = USD 15,000,000
Net cost to be normalized for location (USD 50,000,000–USD 15,000,000) = USD 35,000,000
RSMeans Indianapolis 2012 = 180.6(Refer to Equation (1) in Section 2.2.2 for location adjustment)
RSMeans Chicago 2012 = 225.2
Cost after location adjustment/Project TIC in Chicago 2012USD 43,643,411
BLS−PPI 2012 = 99.7Intentionally left Blank(Refer to Equation (3) in Section 2.2.3 for time adjustment)
BLS−PPI 2022 = 147.0B = B L S P P I 2022 B L S P P I 2012 × USD 15,000,000
Cost after location adjustment/Project TIC in Chicago 2022 (A)USD 64,348,861B = USD 22,116,349
Total normalized A/E + CM + Capital medical equipment cost using
BLS−PPI 2012 and 2022 (B)
USD 22,116,349
Final Normalized Cost (A+B) = USD 86,465,210
Table 5. Applicability of indices to construction cost elements.
Table 5. Applicability of indices to construction cost elements.
Index TypeIndex NamePurposeAvailabilityConstruction Cost Elements
(HCF and CSIMF)
INPUTRSMeansCity Cost IndexLocation
adjustment
970+ citiesYes
Material, labor, and equipment
Historical
Adjustment
Time
adjustment
30 citiesYes
Material, labor, and equipment
INPUTENRBuilding Cost
Index
Time
adjustment
20 citiesYes
Material and labor only
Construction Cost
Index
Time
adjustment
20 citiesYes
Material and labor only
INPUTMarshal & SwiftEquipment Cost
Index
Time
adjustment
-Yes
Major equipment only
Building Cost
Index
Time
adjustment
100
cities
Yes
Materials, equipment, and labor
Producer Price Index—Non-Residential—
New Warehouse Building Construction
Time
adjustment
-Yes
Material and installation.
Preconstruction site preparation work, postconstruction landscaping or reclamation work, architectural fees, and building design fees are not in scope.
Producer Price Index—Non-Residential—
New Healthcare Building Construction
Time
adjustment
-
OUTPUTBureau of
Labor
Statistics
Producer Price Index—Non-Residential—
New School Building Construction
Time
adjustment
-
Producer Price Index—Non-Residential—
New Industrial Building Construction
Time
adjustment
-
Producer Price Index—Non-Residential—
New Office Building Construction
Time
adjustment
-
OUTPUTMortensonConstruction Cost
Index
Time
adjustment
7 citiesYes
Labor, material, equipment, and
labor feedback
OUTPUTTurnerBuilding Cost IndexTime
adjustment
44 citiesYes
Material, labor rates, and
productivity, and market conditions only.
OUTPUTRider Levett BucknallGlobal Construction Cost Relativity IndexLocation adjustment12 citiesYes
Labor, materials, general contractor and sub-contractor overhead costs, fees, profit margins, applicable sales/use taxes.
OUTPUTRider Levett BucknallGlobal Construction Cost Relativity IndexTime adjustment12 citiesYes
Labor, materials, general contractor and sub-contractor overhead costs, fees, profit margins, applicable sales/use taxes.
SELLINGDepartment of DefenseArea Cost FactorsLocation
adjustment
--
Table 6. Comparison of Cost indices (Normalized to 2008 = 100).
Table 6. Comparison of Cost indices (Normalized to 2008 = 100).
Initial Value = USD 10,000,000Index @ 2012Index @ 2021Normalized ValueDifference (Δ)
RS Means CCI226.2286.4USD 12,661,362USD 2,661,362
RSMeans HCI194.0238.3USD 12,283,505USD 2,283,505
ENR-CCI112.5146.0USD 12,977,778USD 2,977,778
ENR-BCI110.3147.3USD 13,354,488USD 3,354,488
Turner91.4132.0USD 14,442,013USD 4,442,013
RLB97.0145.0USD 14,948,454USD 4,948,454
BLS-PPI99.7125.4USD 12,577,733USD 2,577,733
Table 7. Shell space adjustment.
Table 7. Shell space adjustment.
Line ItemValue
Project BGSF (SF) =250,000
TIC =USD 50,000,000
Total Capital Medical Equipment Cost =USD 10,000,000
Total A/E and Construction Management Cost =USD 5,000,000
Cold Shell (SF) =50,000
Adjust BGSF using the shell space adjustment factors—Cold shell (0.5) and warm shell (0.35)
Step 1—Cold shell adjustment
Equivalent Square Footage due to Shell (50,000 SF of cold shell × 0.5) =25,000.00
Step 2—Final BGSF to be considered to evaluate USD /BGSF
Final Equivalent SF of Building (250,000 SF–25,000 Equivalent SF) =225,000.00
Table 8. Normalization of CSIMF cost elements—Example.
Table 8. Normalization of CSIMF cost elements—Example.
Case Study: Mercy Clinic, Zumbehl Road, St. Louis, MO.
CSIMF Cost ElementCost to Be
Normalized
Year of
Midpoint of
Construction
Normalization Steps 1Location
Adjustment
Time
Adjustment
Division 03—Total ConcreteUSD 437,8502012LA and TAUSD 550,477USD 572,304
Division 21—Total Fire SuppressionUSD 68,0342012LA and TAUSD 76,894USD 84,536
Division 22—Total PlumbingUSD 284,1852012LA and TAUSD 321,191USD 353,112
Division 23—Total HVACUSD 480,7752012LA and TAUSD 543,380USD 597,384
Division 26—Total ElectricalUSD 564,1302012LA and TAUSD 616,096USD 721,636
Division 31—Total EarthworkUSD 606,7902012LA and TAUSD 627,648USD 699,704
1 Calculation details in Table A3Appendix B.
Table 9. Comparison of construction phase cost and CSIMF elements’ costs.
Table 9. Comparison of construction phase cost and CSIMF elements’ costs.
CategoryCost Normalization
TypeConstruction Phase Cost 1CSIMF Cost Elements 2
Cost to be normalizedUSD 6,013,294 1USD 6,013,286 2
Design/engineering, A/E, CM, medical equipment costNot ApplicableNot Applicable
Net cost to be normalized for locationUSD 6,013,294USD 6,013,286
Net cost after Location AdjustmentUSD 6,869,733USD 6,813,829
Net cost after Time adjustment (A)USD 10,128,894USD 7,354,533
Design/engineering, A/E, CM, medical equipment cost after time adjustment (B)Not ApplicableNot Applicable
Total Normalized cost (A + B)USD 10,128,894USD 7,354,533
Δ = (Normalized Construction phase cost − Normalized CSIMF elements’ cost)USD 2,774,361
Normalized ΔUSD 3,364,420
Normalized CSIMF elements cost + Normalized Δ =USD 10,718,953
1 Calculation details in Table A1Appendix B for construction phase cost. 2 Calculation details in Table A3Appendix B for the total of CSIMF cost elements.
Table 10. Application of framework for TIC towards phase cost and HCF-specific elements.
Table 10. Application of framework for TIC towards phase cost and HCF-specific elements.
Project Life-cycle Phase Costs 1
DescriptionCosts to be NormalizedCost after Normalization
Phase Costs normalized for Location and Time
FEP (Front-End Planning) CostUSD 10,806USD 18,202
Construction CostUSD 6,013,294USD 10,128,894
Activation/Move-in Actual CostUSD 31,701USD 53,397
Total for Phase Costs normalized for Location and Time (A)USD 6,055,801USD 10,200,493
Phase Costs normalized only for Time
Detailed Design CostUSD 437,253USD 644,696
Procurement CostUSD 1,740,773USD 2,566,636
Total for Phase Costs normalized for Time (B)USD 2,178,026USD 3,211,332
Total for Project Life-cycle Phase Costs (A + B)USD 8,233,827USD 13,411,825
HCF-specific cost elements 2
DescriptionCosts to be NormalizedCost after Normalization
HCF Cost elements normalized for Location and Time 2USD 6,055,802USD 10,200,496
HCF Cost elements normalized only for Time 2S2,178,027USD 3,211,331
Total for HCF-specific cost elementsUSD 8,233,829USD 13,411,827
1 Calculation details in Table A1Appendix B for the total of all project life-cycle phase costs. 2 Calculation details in Table A2Appendix B for the total of HCF-specific cost elements.
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Sharma, V.; Caldas, C.H.; Gajjar, D.; Bapat, P. Development of a Cost Normalization Framework for Healthcare Facilities Cost Elements. Buildings 2024, 14, 529. https://doi.org/10.3390/buildings14020529

AMA Style

Sharma V, Caldas CH, Gajjar D, Bapat P. Development of a Cost Normalization Framework for Healthcare Facilities Cost Elements. Buildings. 2024; 14(2):529. https://doi.org/10.3390/buildings14020529

Chicago/Turabian Style

Sharma, Vivek, Carlos H. Caldas, Dhaval Gajjar, and Prajakta Bapat. 2024. "Development of a Cost Normalization Framework for Healthcare Facilities Cost Elements" Buildings 14, no. 2: 529. https://doi.org/10.3390/buildings14020529

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop