Identification of Key Design Phase-Related Risks in DBB Projects in the UAE—Towards Developing a BIM Solution
Abstract
:1. Introduction
2. Literature Review
3. Research Methodology
3.1. Research Step 1
3.2. Research Step 2 and 3
4. Questionnaire Analysis Approach
- i = ordinal number of risks.
- i ∈ (1, m); m = total number of risks.
- k = ordinal number of the project objective.
- k ∈ (1, 5).
- j = ordinal number of valid feedbacks to risk i.
- j ∈ (1, n); = total number of valid feedbacks to risk i.
- = likelihood occurrence of risk i, assessed by respondent j.
- = level of the consequence of risk i on project objective k, assessed by respondent j.
5. Results and Discussion
5.1. Risk Significance Index Score
5.2. Mapping the Root Causes of High-Ranked Risks with BIM-Based Solutions
6. Building Information Modelling
7. Conclusions
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Conflicts of Interest
References
- Zou, Y.; Kiviniemi, A.; Jones, S.W. A review of risk management through BIM and BIM-related technologies. Saf. Sci. 2017, 97, 88–98. [Google Scholar] [CrossRef]
- Sacks, R.; Whyte, J.; Swissa, D.; Raviv, G.; Zhou, W.; Shapira, A. Safety by design: Dialogues between designers and builders using virtual reality. Constr. Manag. Econ. 2015, 33, 55–72. [Google Scholar] [CrossRef]
- Dharmapalan, V.; Gambatese, J.; Fradella, J.; Moghaddam Vahed, A. Quantification and assessment of safety risk in the design of multistory buildings. J. Constr. Eng. Manag. 2015, 141, 04014090. [Google Scholar] [CrossRef]
- Kamardeen, I. 8D BIM modelling tool for accident prevention through design. In Proceedings of the 26th Annual ARCOM Conference, Association of Researchers in Construction Management, Leeds, UK, 6–8 September 2010; pp. 281–289. [Google Scholar]
- Adafin, J.; Wilkinson, S.; Rotimi, J.; Odeyinka, H. Evaluating the budgetary reliability of the design stage elemental cost plan in building procurement. In Proceedings of the 9th cidbPostgraduate Conference, The River Club, Cape Town, South Africa, 2–4 February 2016. [Google Scholar]
- Venkatachalam, S.; Varghuese, K. Analysis of Workflow on Design Projects in India. Gestão Tecnol. Proj. 2010, 5, 86–103. [Google Scholar]
- Venkatachalam, S.; Varghuese, K. Case Study–Based Testing of Design Interface Management System. J. Manag. Eng. 2013, 29, 279–288. [Google Scholar]
- Dossick, C.; Neff, G. Messy talk and clean technology: Communication, problem-solving and collaboration using Building Information Modelling. Eng. Proj. Org. J. 2011, 1, 83–93. [Google Scholar] [CrossRef]
- Grilo, A.; Jardim-Goncalves, R. Value proposition on interoperability of BIM and collaborative working environments. Autom. Constr 2010, 19, 522–530. [Google Scholar] [CrossRef]
- Papachatzi, D.; Xenidis, Y. Risk management in construction projects using building information modelling. In Proceedings of the European Conference on Computing in Construction, Chania, Greece, 10–12 July 2019. [Google Scholar]
- Ahmad, Z.; Thaheema, M.J.; Maqsoom, A. Building information modelling as a risk transformer: An evolutionary insight into the project uncertainty. Autom. Constr. 2018, 92, 103–119. [Google Scholar] [CrossRef]
- Zou, Y.; Kiviniemi, A.; Jones, S.W. BIM and Knowledge Based Risk Management System: A Conceptual Model. In Proceedings of the CITA BIM Gathering 2015, Dublin, Ireland, 12–13 November 2015. [Google Scholar]
- Malvar, M.J.; Likhitruangsilp, V. A Framework of Designating Appropriate Building Information Modeling (BIM) Uses for Managing Design and Build Project Risks. In Proceedings of the Twenty-Seventh KKHTCNN Symposium on Civil Engineering, Shanghai, China, 10–12 November 2014. [Google Scholar]
- Yang, J.; Wei, P. Causes of Delay in the Planning and Design Phases for Construction Projects. J. Archit. Eng. 2010, 16, 80–83. [Google Scholar] [CrossRef]
- Malek, M.; El-Sayegh, S. Causes of claims in road construction projects in the UAE. Int. J. Constr. Manag. 2018, 18, 26–33. [Google Scholar]
- Al Hasani, M. Cultural and Economic Risks Factors in UAE Construction Projects. Int. J. Acad. Res. Bus. Soc. Sci. 2018, 8, 449–471. [Google Scholar] [CrossRef] [PubMed] [Green Version]
- Flanagan, R.; Norman, G. Risk Management and Construction; Blackwell Science Pty Ltd.: Milton, Australia, 1993. [Google Scholar]
- Akintoye, A.; MacLeod, M. Risk Analysis and Management in Construction. Int. J. Proj. Manag. 1997, 15, 31–38. [Google Scholar] [CrossRef]
- Smith, N. Appraisal, Risk and Uncertainty (Construction Management Series); Thomas Telford Ltd.: London, UK, 2003. [Google Scholar]
- Wu, H.; Sun, C.; Li, T. Study on the Structure of Risk Management Framework Based on BIM. In Proceedings of the ICCREM 2014: Smart Construction and Management in the Context of New Technology, Kunming, China, 27–28 September 2014; p. 15. [Google Scholar]
- Zou, P.X.; Zhang, G.; Wang, J. Understanding the Key Risks in Construction Projects in China. Int. J. Proj. Manag. 2007, 25, 601–614. [Google Scholar] [CrossRef]
- Monazam, N.H.; Hamidimonazam, H.; Hosseini, M.R. An Investigation into Design-Related Risks Affecting Iranian Construction Projects. Project Management Development—Practice and Perspectives. In Proceedings of the Fifth International Scientific Conference on Project Management in the Baltic Countries, Riga, Latvia, 16–17 April 2016. [Google Scholar]
- Assaf, S.; Al-Hejji, S. Causes of delay in large construction projects. Int. J. Proj. Manag. 2006, 24, 349–357. [Google Scholar] [CrossRef]
- Perera, B.A.K.S.; Dhanasinghe, I.; Rameezdeen, R. Risk management in road construction: The case of Sri Lanka. Int. J. Strateg. Prop. Manag. 2009, 13, 87–102. [Google Scholar] [CrossRef] [Green Version]
- Tang, W.; Qiang, M.; Duffield, C.F.; Young, D.M.; Lu, Y. Risk management in the Chinese construction industry. J. Constr. Eng. Manag. 2007, 133, 944–956. [Google Scholar] [CrossRef]
- Nguyen, T.P.; Chileshe, N. Revisiting the construction project failure factors in Vietnam. Built Environ. Proj. Asset Manag. 2015, 5, 398–416. [Google Scholar] [CrossRef]
- Le-Hoai, L.; Dai Lee, Y.; Lee, J.Y. Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries. KSCE J. Civ. Eng. 2008, 12, 367–377. [Google Scholar] [CrossRef]
- Larsen, J.K.; Shen, G.Q.; Lindhard, S.M.; Brunoe, T.D. Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. J. Manag. Eng. 2015, 32, 04015032. [Google Scholar] [CrossRef] [Green Version]
- Venkatachalam, S.; Varghese, K.; Shivaji, C.Y. Achieving Lean Design Using Design Interface Management Tool. In Proceedings of the 13th IGLC, Taipei, Taiwan, 13–15 July 2009; Volume 17. [Google Scholar]
- Lindemann, U.; Maurer, M.; Brau, T. Structural Complexity Management: An Approach for the Field of Product Design; Springer: Berlin/Heidelberg, Germany, 2008. [Google Scholar]
- Gerges, M.; Ahiakwo, O.; Jaeger, M.; Asaad, A. Building Information Modeling and Its Application in the State of Kuwait. Int. J. Civ. Environ. Struct. Constr. Archit. Eng. 2016, 10, 81–86. [Google Scholar]
- Zou, Y.; Kiviniemi, A.; Jones, S.W. Developing a Tailored RBS Linking to BIM for Risk Management of Bridge Projects. Eng. Constr. Archit. Manag. 2016, 23, 727–750. [Google Scholar] [CrossRef] [Green Version]
- Oh, M.; Lee, J.; Hong, S.W.; Jeong, Y. Integrated system for BIM-based collaborative design. Autom. Constr. 2015, 58, 196–206. [Google Scholar] [CrossRef]
- Smith, P. BIM and the 5D Project Cost Manager. Procedia Soc. Behav. Sci. 2014, 119, 475–484. [Google Scholar] [CrossRef] [Green Version]
- Sarkar, D.; Shah, H. Integration of BIM and Risk Management: A Review of Literature. Int. J. Manag. Technol. Eng. 2018, 8, 489. [Google Scholar]
- Johnson, R.M.; Babu, R.I.I. Time and cost overruns in the UAE construction industry: A critical analysis. Int. J. Constr. Manag. 2020, 20, 402–411. [Google Scholar] [CrossRef]
- Essam, K. Investigating the types, causes and severity of claims in construction projects in the UAE. Int. J. Constr. Manag. 2018, 20, 385–401. [Google Scholar] [CrossRef]
- Ghias, U. Causes of Delay in Construction Projects in Abu Dhabi. Master’s Thesis, British University in Dubai, Dubai, United Arab Emirates, 2015. [Google Scholar]
- Faridi, A.; El-Sayegh, S. Significant factors causing delay in the UAE construction industry. J. Constr. Manag. Econ. 2006, 24, 1167–1176. [Google Scholar] [CrossRef]
- Badran, D. Development of a Risk Management Framework in a Building Information Modelling-Enabled Design Process in the United Arab Emirates Projects. Ph.D. Thesis, University of Sharjah, Sharjah, United Arab Emirates, 2020. [Google Scholar]
- Odeh, A.M.; Battaineh, H.T. Causes of Construction Delay: Traditional Contracts. Int. J. Proj. Manag. 2002, 20, 67–73. [Google Scholar] [CrossRef]
- Sweis, G.; Sweis, R.; Abu Hammad, A.; Shboul, A. Delays in construction projects: The case of Jordan. Int. J. Proj. Manag. 2008, 26, 665–674. [Google Scholar] [CrossRef]
- Assaf, S.; Al-Khalil, M.; Al-Hazmi, M. Causes of delays in large building construction projects. ASCE J. Manag. Eng. 1995, 11, 45–50. [Google Scholar] [CrossRef]
- Al-Momani, A. Construction delay: A quantitative analysis. Int. J. Proj. Manag. 2000, 18, 51–59. [Google Scholar] [CrossRef]
- Sambasivan, M.; Soon, Y.W. Causes and effects of delays in Malaysian construction industry. Int. J. Proj. Manag. 2007, 25, 517–526. [Google Scholar] [CrossRef]
- Aibinu, A.; Odeyinka, A. Construction delays and their causative factors in Nigeria. J. Constr. Eng. Manag. 2006, 132, 667–677. [Google Scholar] [CrossRef]
- Acharya, N.K.; Lee, Y.D.; Im, H.M. Investigating delay factors in construction industry: A Korean perspective. Korean J. Constr. Eng. Manag. 2006, 10, 177–190. [Google Scholar]
- Lee, S.; Peña-Mora, F.; Park, M. Quality and change management model for large-scale concurrent design and construction project. J. Constr. Eng. Manag. 2005, 131, 890–902. [Google Scholar] [CrossRef]
- Zou, P.X.; Zhang, G. Managing Risks in Construction Projects: Life Cycle and Stakeholder Perspectives. Int. J. Constr. Manag. 2009, 9, 61–77. [Google Scholar] [CrossRef]
No. | Category | ID | Design-Phase Related Risks |
---|---|---|---|
Risks from Literature Review | |||
1 | Client | ICD | Interference by the client in the design process |
2 | Client | CIV | Client-initiated modifications/client requests changes in the design |
3 | Client | DRD | Client delays in reviewing and approving design |
4 | Client | UCR | Clients’ unrealistic initial requirements and unreasonably high expectations |
5 | Client | UCD | Unrealistic contract duration imposed by client/pressure to deliver design in an accelerated schedule |
6 | Client | DPP | Delay in progress payments by the client |
7 | Client | FCC | Financial constraints faced by the client |
8 | Client | DPS | Design process suspended by the client |
9 | Consultant | DPD | Delay in preparation of drawings |
10 | Consultant | AMD | Ambiguities/imperfections/mistakes in drawings and specifications |
11 | Consultant | PIQ | Poor implementation of quality control/assurance (QC/QA) |
12 | Consultant | PCC | Poor communication between consultant and other project parties |
13 | Consultant | IDC | Insufficient data collection and survey before the design |
14 | Consultant | MID | Mistakes in the design |
15 | Consultant | SMS | Shortages in the materials specified by the consultant/materials required approval from the concerned authorities |
16 | Approval Authorities | TSA | Time spent in the approval process |
17 | Approval Authorities | CRL | Changes in government regulations and laws |
18 | Other | UGC | Unforeseen ground conditions (such as unexpected geotechnical or groundwater issues, underground utility lines) |
19 | Other | DCE | Deficiencies or inaccuracies in cost estimation |
20 | Other | DPS | Deficiencies in planning and scheduling the project |
21 | Other | IOS | Inappropriate overall organizational structure of companies linked to the project |
22 | Other | MCD | Mistakes and discrepancies in the contract documents |
23 | Other | LDP | Legal disputes between various parties in the project |
Risks from Pilot Study | |||
24 | Client | JOP | Joint ownership of project |
25 | Client | NSE | New stakeholder emerges and requests changes |
26 | Client | CEU | Change in the end users |
27 | Consultant | MCR | Misunderstanding of client requirements |
28 | Consultant | PCD | Poor coordination between design disciplines |
29 | Consultant | IDC | Impractical design/constructability issues not studied during the design phase |
30 | Consultant | DMP | Difficulty in measuring progress during design development |
31 | Consultant | ITR | Insufficient time to review tender documents submitted by contractor |
32 | Consultant | MIB | Mistakes and discrepancies in the itemized bill of quantities (BOQ) prepared by the cost consultant |
33 | Consultant | RCF | Reduction in consultant fees |
34 | Consultant | CSC | Client changes the consultant |
35 | Other | ADU | As-built drawings are not available for the existing structures |
36 | Other | SIF | Slow information flow between project team |
37 | Other | APM | Absence of professional project management |
Emirate | Engineering Consultancies | Project Management Consultancies | Total Number of Companies |
---|---|---|---|
Emirate 1 | 273 | 17 | 290 |
Emirate 2 | 193 | 27 | 220 |
Emirate 3 | 96 | 8 | 104 |
Emirate 4 | 5 | 0 | 5 |
Total | 619 |
Emirate (Strata) | Strata Sample Size | Division of Strata Sample | ||
---|---|---|---|---|
Engineering Consultancies | Project Management Consultancies | Total Number of Companies | ||
Emirate 1 | 14.1 | 13.2 | 0.8 | 14.0 |
Emirate 2 | 10.7 | 9.4 | 1.1 | 10.5 |
Emirate 3 | 5.0 | 4.7 | 0.4 | 5.0 |
Emirate 4 | 0.2 | 0.2 | 0.0 | 0.2 |
Total | 29.7 |
Risk ID | Time Delay | Cost Overrun | Quality | |||
---|---|---|---|---|---|---|
Risk Index | Rank | Risk Index | Rank | Risk Index | Rank | |
ICD | 0.457 | 27 | 0.337 | 28 | 0.162 | 17 |
CIV | 0.447 | 1 | 0.393 | 2 | 0.191 | 15 |
DRD | 0.305 | 2 | 0.169 | 17 | 0.059 | 35 |
UCR | 0.190 | 28 | 0.166 | 1 | 0.129 | 8 |
JOP | 0.295 | 17 | 0.229 | 32 | 0.179 | 34 |
UCD | 0.165 | 9 | 0.203 | 27 | 0.148 | 14 |
DPP | 0.247 | 3 | 0.155 | 14 | 0.070 | 2 |
FCC | 0.224 | 5 | 0.134 | 15 | 0.217 | 32 |
DPS | 0.311 | 15 | 0.230 | 9 | 0.091 | 5 |
NSE | 0.044 | 14 | 0.044 | 5 | 0.023 | 1 |
CEU | 0.124 | 35 | 0.121 | 29 | 0.056 | 6 |
MCR | 0.193 | 33 | 0.176 | 33 | 0.138 | 28 |
DPD | 0.242 | 7 | 0.123 | 35 | 0.047 | 19 |
AMD | 0.272 | 13 | 0.260 | 6 | 0.196 | 12 |
PIQ | 0.273 | 32 | 0.250 | 18 | 0.299 | 16 |
PCC | 0.184 | 29 | 0.108 | 12 | 0.132 | 24 |
PCD | 0.390 | 8 | 0.354 | 19 | 0.329 | 4 |
IDC | 0.214 | 31 | 0.197 | 3 | 0.120 | 18 |
IDC | 0.173 | 18 | 0.175 | 4 | 0.139 | 20 |
MID | 0.152 | 34 | 0.145 | 34 | 0.119 | 22 |
DMP | 0.043 | 12 | 0.035 | 7 | 0.038 | 25 |
ITR | 0.109 | 4 | 0.118 | 20 | 0.118 | 33 |
MIB | 0.041 | 16 | 0.037 | 24 | 0.027 | 31 |
SMS | 0.149 | 19 | 0.140 | 8 | 0.130 | 27 |
RCF | 0.124 | 6 | 0.111 | 13 | 0.116 | 9 |
CSC | 0.097 | 20 | 0.091 | 11 | 0.045 | 7 |
EAP | 0.465 | 24 | 0.265 | 22 | 0.110 | 29 |
CGR | 0.424 | 37 | 0.417 | 37 | 0.148 | 3 |
UGC | 0.228 | 11 | 0.220 | 25 | 0.060 | 11 |
ADU | 0.045 | 25 | 0.041 | 16 | 0.045 | 36 |
SIF | 0.217 | 22 | 0.097 | 31 | 0.113 | 13 |
DCE | 0.237 | 26 | 0.296 | 26 | 0.181 | 30 |
DPS | 0.254 | 36 | 0.204 | 36 | 0.115 | 26 |
IOS | 0.214 | 30 | 0.159 | 10 | 0.215 | 21 |
APM | 0.270 | 10 | 0.203 | 30 | 0.244 | 37 |
MCD | 0.072 | 21 | 0.075 | 23 | 0.054 | 23 |
LDP | 0.125 | 23 | 0.114 | 21 | 0.035 | 10 |
A | ||||||
High-Ranked Design Phase-Related Risks | Project Objective Impacted by Risk | Stakeholder | Identified Root Causes | |||
Time | Cost | Quality | ||||
1 | Time spent in the approval process | ● | ● | Consultant | Poor implementation of quality assurance/quality control (QA/QC) system (poor reviewing system, poor quality of drawings, mistakes in the drawings) | |
Major modifications/comments on the drawings require time from the consultant to rectify the drawings | ||||||
Mistakes in the design | ||||||
Discrepancies in drawings due to the pressure on the consultant to submit the drawings for approval | ||||||
The design was not properly studied by the consultant | ||||||
Major changes in the design require time for the consultant to prepare the drawings for approval and for approval authorities to review the drawings | ||||||
2 | Complying with new regulations and rules | ● | ● | Consultant | Mistakes in implementing the new regulations | |
Adopting international codes in the design which are not compatible with the local regulations | ||||||
3 | Interference by the client in the design process | ● | ● | ● | Client | The client cannot visualize the project/spaces/dimensions/circulation |
The client has different opinions about the design | ||||||
The client does not have a defined requirements/poor scope definition | ||||||
The client cannot understand the AutoCAD drawings | ||||||
4 | Client-initiated variations/client requests changes in the design | ● | ● | ● | Client | Clients are not able to explain their requirements |
Change in real estate market demand | ||||||
Change in the end user requirements | ||||||
5 | Delay in reviewing and approving design by the client | ● | Client | The client cannot understand the 2D drawings | ||
The design did not achieve the client’s expectations | ||||||
The client cannot judge that the design is the optimal design | ||||||
6 | Joint ownership of the project | ● | ● | ● | Client | More than one decision maker for the project |
7 | Design process suspended by the client | ● | ● | Client | Not identified | |
8 | Financial constraints | ● | Client | Not identified | ||
9 | Poor coordination between design disciplines | ● | ● | ● | Consultant | Traditional tools are used in coordination between the design disciplines, such as superimposing drawings in AutoCAD, regular meetings between the design disciplines, and hiring a design coordinator. |
The approval authorities give comments on some drawings which the consultant does not properly coordinate with other drawings. | ||||||
One of the design teams made a change in the design and did not properly coordinate it with other design teams involved in the project. | ||||||
The client requested a change in the design, which is not properly coordinated between the design disciplines. | ||||||
Architectural design is so complicated, and coordination with other design disciplines is difficult using 2D tools. | ||||||
10 | Ambiguities and mistakes in drawings and specifications | ● | ● | ● | Consultant | Poor implementation of the QA/QC system |
Traditional tools are used to review the drawings and specifications | ||||||
The consultant does not have enough resources to provide more details in the drawings | ||||||
The design details are complicated and cannot be presented in 2D. | ||||||
11 | Deficiencies or inaccuracies in cost estimation | ● | ● | Consultant | The quantity take-off is not accurate | |
An approximate method is used in estimating | ||||||
12 | Poor implementation of quality assurance/quality control (QA/QC) system | ● | ● | ● | Consultant | The consultant does not have enough resources to implement a proper QA/Qc system |
13 | Deficiencies in planning and scheduling of the project | ● | Consultant | The consultant does not have a planning department | ||
14 | Absence of professional project management | ● | Consultant | The consultant does not have a project management department | ||
The client does not assign a project management consultancy | ||||||
15 | Inappropriate overall organizational structure | ● | Consultant | Not identified | ||
B | ||||||
High-ranked Design Phase-related Risks | Project Objective Impacted by Risk | Stakeholder | Proposed BIM-based Solution | |||
Time | Cost | Quality | ||||
1 | Time spent in the approval process | ● | ● | Consultant | Predefined templates, families, annotation, etc., within 3D models provide a sufficient method for minimizing errors | |
3D coordination Clash detection reports Digital design review sessions Extracting drawings from a fully coordinated model | ||||||
BIM helps minimize the consequences | ||||||
Incorporating changes and finalizing coordination in 3D models | ||||||
2 | Complying with new regulations and rules | ● | ● | Consultant | BIM helps minimize the consequences | |
BIM helps minimize the consequences | ||||||
3 | Interference by the client in the design process | ● | ● | ● | Client | Using visualization technology augmented reality/virtual reality |
Using 3D models and visualization tools improves project team communication and collaboration | ||||||
4 | Client-initiated variations/client requests changes in the design | ● | ● | ● | Client | Using 3D models and visualization tools improves project team communication and collaboration |
BIM helps minimize the consequences | ||||||
BIM helps minimize the consequences | ||||||
5 | Delay in reviewing and approving design by the client | ● | Client | Using 3D models and visualization tools Using visualization technology augmented reality/virtual reality | ||
6 | Joint ownership of the project | ● | ● | ● | Client | Using 3D models and visualization tools enables the different decision makers reached to a conclusion |
7 | Design process suspended by the client | ● | ● | Client | BIM helps minimize the consequences | |
8 | Financial constraints | ● | Client | BIM helps minimize the consequences | ||
9 | Poor coordination between design disciplines | ● | ● | ● | Consultant | 3D coordination Clash detection reports Digital design review sessions |
Using CDE and centralized model working space, with immediate sync, provides proper workflow without any discoordination or missing data between the project team | ||||||
Utilization of digital tools provides an efficient process to facilitate design, fabrication and installation | ||||||
10 | Ambiguities and mistakes in drawings and specifications | ● | ● | ● | Consultant | Predefined templates, families, annotation, etc., provide sufficient methods for minimizing errors |
Sections and details can be generated from the 3D model | ||||||
Utilization of digital tools provides an efficient process to facilitate design, fabrication and installation | ||||||
11 | Deficiencies or inaccuracies in cost estimation | ● | ● | Consultant | Using accurate MTO extracted from a model | |
12 | Poor implementation of quality assurance/quality control (QA/QC) system | ● | ● | ● | Consultant | Predefined templates, families, annotation, etc., provide sufficient methods for minimizing errors |
13 | Deficiencies in planning and scheduling of the project | ● | Consultant | 4D simulation of time | ||
14 | Absence of professional project management | ● | Consultant | BIM helps minimize the consequences | ||
15 | Inappropriate overall organizational structure | ● | Consultant | BIM helps minimize the consequences |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2023 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Badran, D.; AlZubaidi, R.; Venkatachalam, S. Identification of Key Design Phase-Related Risks in DBB Projects in the UAE—Towards Developing a BIM Solution. Sustainability 2023, 15, 6651. https://doi.org/10.3390/su15086651
Badran D, AlZubaidi R, Venkatachalam S. Identification of Key Design Phase-Related Risks in DBB Projects in the UAE—Towards Developing a BIM Solution. Sustainability. 2023; 15(8):6651. https://doi.org/10.3390/su15086651
Chicago/Turabian StyleBadran, Deena, Radhi AlZubaidi, and Senthilkumar Venkatachalam. 2023. "Identification of Key Design Phase-Related Risks in DBB Projects in the UAE—Towards Developing a BIM Solution" Sustainability 15, no. 8: 6651. https://doi.org/10.3390/su15086651