Next Article in Journal
Building and Architectural Details of Tenement Houses Built at the Turn of the 19th and 20th Centuries in Central European Region—Hygrothermal Analysis
Next Article in Special Issue
Automated Semantic Segmentation of Indoor Point Clouds from Close-Range Images with Three-Dimensional Deep Learning
Previous Article in Journal
Investigation into Viscoelastic Properties of Fiber-Reinforced Asphalt Composite Concrete Based on the Burgers Model
Previous Article in Special Issue
Polyethylene (PE) Waste Minimization Study of Cement Mortar with Adding PE Content under Different W/B Ratios
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Real-Time Monitoring for Effects of Vibration and Temperature of Construction Site on Steel Assembly Bracing of Foundation Pit

1
College of Landscape and Architecture, Zhejiang A&F University, Hangzhou 311300, China
2
School of Civil Engineering and Architecture, Zhejiang Sci-Tech University, Hangzhou 310018, China
3
Zhejiang Province Institute of Architectural Design and Research, Hangzhou 310006, China
*
Authors to whom correspondence should be addressed.
Buildings 2023, 13(2), 450; https://doi.org/10.3390/buildings13020450
Submission received: 31 December 2022 / Revised: 31 January 2023 / Accepted: 2 February 2023 / Published: 6 February 2023
(This article belongs to the Special Issue Applications of (Big) Data Analysis in A/E/C)

Abstract

:
In this paper, a real-time monitoring system—including vibration acceleration sensors, temperature sensors, and static and dynamic strain sensors—is used to monitor the safety status of a steel assembly bracing in a practical project. It uses 5G wireless networking technology to transmit monitoring data to a cloud server for early warning of abnormal changes and development trends. Real-time monitoring data obtained in a construction site are used as the inputs of the finite element model and the corresponding results of numerical simulation are compared with the results from the real-time monitoring. It can be concluded that: (1) the stress caused by environmental temperature is very significant which can be higher than the initial prestress of the steel assembly bracing; (2) the stress caused by the vertical vibration mainly from construction vehicles is not remarkable, however, the vertical frequency-weighted acceleration of support vibration is relatively large which can affect the sense of safety of engineering technicians on site; (3) the combination of the environmental temperature and vertical vibration does not affect the safety of the steel assembly bracing.

1. Introduction

Reasonable setting of internal bracing is an important guarantee for the construction safety of deep and large foundation pits. Due to the temporary nature of foundation pit engineering, it is necessary to consider three factors including safety, economy and construction period in the design of a bracing system. A reinforced concrete structure is a traditional and mature support form for a bracing system. However, it has a long construction period of structure-forming and can easily cause excessive environmental noise and produce more construction waste after the bracing system has been removed. In recent years, engineering research companies in Southeast China have developed steel assembly bracing as a new type of bracing system. Compared with traditional bracing technology, its on-site construction period is short, and there are no noise and construction waste problems. Hence, steel assembly bracing is more environmentally friendly and has a wide application market in engineering.
As far as general engineering experience is concerned, even if the reinforced concrete structure is used as the internal support of a foundation pit, the influence of temperature on the internal force of the support must be considered when the length exceeds 40 m. Furthermore, the steel assembly bracing is more sensitive to temperature than the concrete bracing. Affected by higher thermal conductivity and lower specific heat capacity, the temperature of steel coated with dark antirust coating is usually higher than that of concrete in the same environment. The surface temperature of a steel structure bridge which is similar to steel assembly bracing in structural form is 15~20 °C higher than the environmental temperature, and the stress of each component is also different under solar radiation [1,2]. The steel inner brace of a supporting system will produce large additional axial force and axial deformation under the influence of environmental temperature [3,4]. In engineering cases, the method of covering the supporting system with the surface layer is sometimes used for thermal insulation treatment. Other studies related to steel truss structures show that the dynamic characteristics of steel structures will also change under the influence of environmental temperature, and even cause structural damage in severe cases [5,6,7]. Therefore, the effect of temperature on the steel assembly bracing is significant and cannot be ignored.
Steel assembly bracing has been designed as one or multiple supports which consist of H-shaped steel parts [8,9], among which high-strength bolts are usually adopted to connect the steel. The compression bar analysis method of steel structure is used to design the bracing. Steel assembly bracing consisting of steel pipes or section steels has been used to support the vertical retaining wall structure around the foundation pit with a certain prestress applied in the axial direction of members to reduce the inward deformation. The study reported that the steel assembly bracing with appropriate prestress can significantly reduce the horizontal displacement of the retaining structure of the foundation pit [10]. When the environmental temperature changes greatly, sometimes engineers even use steel diagonal assembly bracing for internal support [11]. In fact, the axial force of each horizontal support transfers with the deformation of the retaining wall structure and becomes more complicated if the impact of environmental temperature is also considered [12,13]. With the increase of support length, the influence of temperature will become more and more significant. Sometimes it is even necessary to reinforce the soil near the support to ensure that there is no separation between the soil and the retaining structure when the support shrinks [14].
Calculation of steel bracing of the foundation pit is usually based on the elastic foundation beam model to consider the effect of temperature, or based on the Winkler model to establish the empirical model of the effect of temperature on the bracing system of the foundation pit. Due to its complexity, inappropriate simplified models sometimes underestimate the temperature effect on steel bracing, which eventually leads to bracing failure [15]. For steel assembly bracing, owing to the influence of lateral deformation along the depth direction of the foundation pit, the influence of temperature on the second layer bracing is sometimes greater than the first layer [16]. In the low-temperature area of North China, the reduction of axial force caused by the temperature drop of steel bracing will also cause the additional deformation of the foundation pit retaining to the pit [17]. Meanwhile, earthwork trucks can cause obvious vibration of steel bracing when they pass through concrete trestles near the end of steel bracing in which vehicle load, speed and distance are very important influencing factors [18].
To the authors’ knowledge, at present, the research on steel assembly bracing is not enough and a safety real-time monitoring system has not been reported to be used to study steel assembly bracing. In the practical project studied in the paper, another problem also deserves attention: on-site technicians reflected that the vibration of the steel assembly bracing was sometimes obvious and thus complained about the insecurity. Therefore, the safety of steel assembly bracing under multiple working conditions is studied by the safety real-time monitoring system combined with numerical simulation in the paper.

2. Monitoring and Numerical Method

2.1. Technical Information of Foundation Pit Support

The size of the foundation pit of Huidong No.14 plot in Hangzhou City is 144 m × 215 m × 15 m, which is shown in Figure 1.
Around the foundation pit, the reinforced concrete diaphragm walls and the triaxial cement-soil mixing piles form the lateral enclosure, steel assembly bracing are used in the horizontal direction, and some reinforced concrete purlins are used as trestle bridges on the earthwork transportation path. Figure 1 shows the driving route of earthwork trucks at the foundation pit construction site and the plane layout of the steel assembly bracing. The transportation channel for the earthwork truck is closest to the steel assembly bracing T01. As can be seen from Figure 2, there are upper and lower steel assembly internal bracings along the height direction of the foundation pit, and both ends are supported on the reinforced concrete trestle bridge for earthwork truck transportation. In addition, vertical steel lattice columns are set at a certain distance in the foundation pit to provide vertical support along the length direction of the steel assembly bracing.
In the process of excavating and transporting soil, the steel assembly internal bracing, which is also used as pedestrian passageway, has obvious vibration when earthwork vehicles drive through the pit. This phenomenon makes engineering technicians pay attention to the safety of the foundation pit. Because the project has been under construction, and the site project progress and working conditions are changeable, it is difficult for the traditional once-a-day monitoring technology to obtain axial force, temperature and support vibration data at the same time and realize safety early warning in case of an emergency. In this study, a real-time monitoring network is established by virtue of the wireless sensor monitoring technology in the construction site to support safety monitoring through real-time monitoring data.

2.2. Monitoring Points Locations

Steel tube internal bracing is a common form of the foundation pit, which has been widely used in a narrow and regular foundation pit. In order to monitor the safety of soil, buildings and structures, an underground pipe network and facilities around the foundation pit during excavation and construction of a deep and large foundation pit or special foundation pit, the designers must determine the safety monitoring points and monitoring contents of the steel pipe support in the design documents according to national standards, design documents and engineering experience [19]. In this study, the monitoring experience of reinforced concrete support and steel tube support is used for reference, to set up the monitoring contents and layout of various measuring points for steel assembly bracing.
According to the site investigation, the vertical vibration of T01 reflected by engineers and construction workers can be obviously felt, especially when several earthwork trucks pass through the trestle bridge one after another. In order to master the relationship between the bracing vibration and running vehicle, and study its influence on the safety of the bracing system, the resistive dynamic strain gauges (precision ±0.1 με, range ±3000 με, type XKKJ-DTA100) and vibration acceleration sensors (sensitivity 0.3 V*s/m, range of scale 20 m/s2, range of frequency 0.25~80 Hz, type BY-S07) have been arranged on the first track (initial pre-axial force P01 = 3200 kN, compressive stress 18.22 MPa) and the second track (initial pre-axial force P01 = 8000 kN, compressive stress 22.78 MPa) of T01 which is the closest to the trestle passage and has obvious vibration sense to monitor the dynamic response. Vibrating wire static strain gauges (strain: precision ±7 με, range ±1500 με, type T-900, temperature: precision ±0.2 °C (0~50 °C), range −40~60 °C, type CG-01) have been arranged on the surface of an H-beam because they are widely used in monitoring for foundation pit support and can be utilized to measure the steel surface temperature and surface strain of an H-beam at the same time [20]. In addition, in order to analyze the correlation between vehicle and the response of structural dynamics, video surveillance is used to monitor earthwork truck transportation. A 5G network is used for wireless networking and remotely transmits data to the cloud database. Figure 3 shows the locations and numbers of various types of sensors on the T01 steel assembly internal bracing.
As can be seen in Figure 3, the vibration acceleration sensors are fixed on the beam for the reinforced concrete trestle, while all kinds of measuring points are installed on the upper flange of the H-beam for the steel assembly bracing. Ten dynamic strain measuring points (DSS-01~DSS-10) are arranged on the first steel assembly bracing, and six dynamic strain measuring points (DSS-11~DSS16) are arranged on the second steel assembly bracing. Two static strain measuring points (SSTS-01, SSTS-02) are arranged to master the static strain and steel temperature of steel assembly bracing. At the same time, acceleration sensors, numbered with 3AS-01 and 3AS-02, are arranged on the trestle bridge and steel assembly bracing, respectively. It is noted that the sampling interval of static strain and temperature data is 5 min; the sampling frequency of dynamic strain is 50 Hz; and the sampling frequency of vibration acceleration is 200 Hz.
According to the monitoring and analysis of real-time data for more than one month, the responses of vibration acceleration of the reinforced concrete trestle bridge and the steel assembly bracing are significantly larger when the earthwork truck passes through the trestle bridge, and the amplitude of vertical vibration acceleration on the first steel assembly bracing is larger than that of the concrete trestle bridge. In addition, the steel assembly bracing is obviously affected by environmental temperature. In order to analyze the influence of vehicle vibration and temperature on the safety of steel assembly bracing, the finite element method is adopted to analyze the structural responses under the combined action of vibration and temperature.

2.3. Numerical Method

In this section, a three-dimensional finite element method is adopted to analyze the steel assembly bracing via ABAQUS software. The calculation results can be used as a reference to compare with the results from the real-time monitoring [21]. The finite element analysis involves modal analysis, steady-state thermal analysis and dynamic analysis. The vertical natural frequency and mode of the steel assembly bracing are obtained by modal analysis; the steady-state thermal analysis is used to analyze the temperature effect on the assembly bracing; the dynamic analysis is used to analyze the vibration effect of transport vehicles. Finally, the most unfavorable combination of temperature and vibration is considered to analyze the steel assembly bracing.
It should be emphasized that the highest temperature and the maximum vibration response of the vehicle driving during the monitoring period are simultaneously considered in the numerical simulation which cannot occur at the same time in practice. Therefore, the numerical simulation results in the paper will be conservative.

2.3.1. Numerical Simulation of Soil Layer

In order to consider the influence of the surrounding soil layer on foundation pit structure, the length and width of the soil layer are taken as four times that of the foundation pit size, and the thickness of the soil layer is taken as twice that of the foundation pit depth. The total size of the ABAQUS finite element model is set as 576 m × 860 m × 30 m [22]. An eight-node C3D8R volumetric element is adopted for the soil layer and the number of elements is about 334,000. Considering that there is a concrete trestle bridge, concrete crown beam and diaphragm wall around the steel assembly bracing to be considered, a linear elastic model is adopted to simplify the calculation of soil layer parameters, which are shown in Table 1. In the process of calculation and analysis, the soil layer adopts C3D8R element type with hourglass control. At the same time, in order to improve the calculation accuracy, the soil elements inside and around the foundation pit are encrypted, and the size of the elements far away from the foundation pit is gradually increased to improve the calculation speed. The bottom boundary of soil is constrained by three-dimensional displacement, the side of soil is constrained by normal displacement, and the upper surface is free. Because the mechanical properties of soil are usually little affected by environmental temperature, the temperature of the soil is set at a normal temperature of 25 °C.

2.3.2. Numerical Simulation of Supporting Structure

The supporting structure around the foundation pit is a concrete diaphragm wall with concrete C35 and a thickness of 1000 mm, which extends into the soil layer at the bottom of the foundation pit to twice the depth of the foundation pit by underwater pouring technology. A concrete crown beam is set at the top of the concrete diaphragm wall and a concrete structure is adopted for the purlin of the foundation pit with concrete C30. A steel crown beam and a steel waist beam are arranged along the vertical height of the steel assembly bracing. Both the crown beam and waist beam adopt the section steel with the same specification, i.e., H400 × 400 × 13 × 21 (Q355b), and the upright column also adopts section steel H400 × 400 × 13 × 21 (Q355b).
Based on the above situation, the S4R element, that is, a four-node curved thin shell element with hourglass control, is used for the diaphragm wall and the surrounding concrete purlin plate where the global element size is 1.0 m and the number of the elements is about 28,000. The B31 element, i.e., a two-node spatial linear beam element, is adopted in the model for the steel assembly bracing, steel purlin beam, section steel column and concrete crown beam in which the global element size is 1.0 m and the number of the elements is about 52,000. The thermal expansion coefficient of steel is α = 1.2 × 10−5, the damping coefficient of steel is ζS = 0.02, and that of reinforced concrete is ζC = 0.02. The material parameters of each component of the foundation pit supporting structure are shown in Table 2, and the finite element model is shown in Figure 4. The outer soil and diaphragm wall have face-to-face contact, and the normal contact is set as hard contact which means that the normal pressure can be transmitted between the two contact surfaces only when they are not separated [22,23]. The penalty function is adopted in the tangential direction, and the friction coefficient is taken as 0.2.
With the help of engineering experience, it can be concluded that the stiffness of reinforced concrete diaphragm walls, cement mixing pile and reinforced concrete brace around the wall is much larger than the vertical stiffness of steel assembly bracing, and the low-order natural frequency of the foundation pit support system should occur in the steel assembly bracing, which has been also proved by numerical results. The low-order vertical natural frequencies of the steel assembly bracing system are mainly concentrated in (6.16 Hz~7.02 Hz), and the first four natural frequencies and the corresponding vertical vibration modes are shown in Figure 5, Figure 6, Figure 7 and Figure 8 as follows.
It can be found that the low-order natural frequencies of the steel assembly bracing are mainly concentrated on the T01 steel support shown in Figure 1, and it is easier to cause T01 vibration when the earthwork truck drives over the concrete trestle bridge. The numerical analysis results preliminarily prove the problems reflected by construction workers.

2.3.3. Acting Load

It has been proved that the internal force changes of steel bracing under the action of temperature cannot be ignored. Considering the abnormal vibration of T01 complained of by workers in this project, it is necessary to consider the combined action problem of temperature and vibration of the steel assembly bracing in both field monitoring and calculation analysis. When the site-monitoring system was established, the construction stage was in the binding steel bars and pouring concrete on the right foundation pit bottom plate near T01, while the left side was in the stage of outward soil transportation. Therefore, the working conditions of the construction site were complicated. As far as temperature changes are concerned, from August to November 2022, the 100 consecutive days of monitoring showed that the strain and temperature monitoring data of the steel assembly bracing changed little at night, while the steel surface temperature of the first steel assembly bracing of T01 ranged from 10.9 °C to 51.6 °C during the day, and the compressive strain of the brace decreased or increased with the temperature obviously. During the 100 days of real-time online monitoring, even in October when the temperature drops, for example, the lowest temperature of steel was 26.0 °C at 4 am on October 3, the highest temperature of steel was 51.6 °C at 14 pm, and the temperature difference between high and low was 25.6 °C. On that day, the axial static compressive strain SSTS-01 increased by 156.3 με with the temperature, and the similar high temperature environment frequently occurred within three months. The temperature changes of the steels from 12 August to 22 November is shown in Figure 9.
As for the vertical vibration problem of steel bracing, since the site is in the construction stage, the vibration sources of structure include: (1) the vibration caused by earthwork truck running; (2) the vibration caused by pouring concrete in the foundation pit bottom plate; (3) the vibration caused by tower crane running and hoisting construction materials, and vibration caused by various construction machines and tools. Frankly speaking, it is extremely difficult to accurately analyze the steel assembly bracing under the action of each vibration source. The multi-day vibration monitoring data show that the vertical vibration of the reinforced concrete trestle bridge and steel assembly bracing increases obviously when the earthwork truck passes through the trestle bridge, which further shows that the earthwork truck passing through the trestle bridge is the main reason for the significant vibration of T01. Video monitoring of the speed of earthwork trucks on the trestle is about 10 km/h. The truck is fully loaded and the roof soil layer is neatly covered, and the average total mass weighed is 20,000 kg. In order to obtain the moving load of the truck running on the trestle, a vertical vibration sensor is installed on one of the trucks to collect the vertical vibration monitoring data of the vehicle. The vibration action during the driving process of the vehicle is shown in Figure 10 and Figure 11 below. The vertical vibration responses of trestle ground vibration acceleration monitoring point 3AS-01 and steel support vibration acceleration monitoring point 3AS-02 at the same time are shown in Figure 12 and Figure 13. It can be seen from the vibration time history and frequency spectrum curves in Figure 10 and Figure 12 that the first-order frequency (Figure 10) of the vehicle action when the truck passes through the concrete trestle is basically consistent with the first-order dominant frequency of the vertical trestle response. The trestle vibration contains forced vibration components, and the frequency components are complex. The first frequency of the vibration response in Figure 13 is 6.661 Hz, which is close to the vertical natural frequency of the bracing in Figure 7 of numerical analysis. The vertical vibration of the bracing is mainly caused by resonance.
During numerical analysis, the vibration effect of earthwork truck as the unique vibration source is considered and the static and dynamic strain of steel assembly bracing at the highest temperature difference are only considered. With regard to the vibration calculation input, the amplitude modulation input model of Figure 10 is calculated based on the maximum value Atbt.max of the vibration response of the concrete trestle bridge (purlin) in Figure 14, such that Atbt.max of Figure 12 is equal to Atbt.max of Figure 14. The time history curve of vehicle vibration acceleration after amplitude modulation in Figure 10 was taken as the calculation input.
In order to simulate the influence of the vertical vibration of vehicles, eight concentrated forces are set in this model to represent the mass distribution of vehicles on the trestle bridge. The numerical values are calculated according to the vehicle weight and the vehicle mass distribution percentage. The first half of the earthwork vehicle accounts for 36% of the total mass of the vehicle, and the second half accounts for 64% of the total mass of the vehicle, and then the mass is evenly distributed to the concentrated force in the area located. During numerical analysis, the total mass of the vehicle is taken as 20,000 kg, and the front and rear wheels of the vehicle are distributed in proportion, in which the concentrated forces exerted by the front wheels RP-1 to RP-4 are all 1800 kg, and the concentrated forces exerted by the rear wheels RP-5 to RP-8 are all 3200 kg, as shown in Figure 15. The time history curve of vehicle vibration acceleration after amplitude modulation is assigned as the amplitude curve which is multiplied by the above mass of the vehicle to obtain the dynamic load-time history curve. Finally, the dynamic load action can be analyzed. It is assumed that the most unfavorable working condition is considered, that is a linear combination of the maximum temperature difference of steel assembly bracing and the maximum vibration response amplitude of the trestle which occur at the same time.

3. Results and Discussion

3.1. Strain of the Steel Assembly Bracing

According to the change of steel assembly bracing with temperature for more than 100 days in Figure 9, the surface temperature changes of section steel collected in typical weather environments of low temperature, medium temperature and high temperature are selected and input into the finite element model, and the temperature influence analysis of static strain at the SSTS-01 measuring point of T01 steel assembly bracing is carried out. SSTS-01 steel surface temperature, monitoring strain, and model in-situ calculated strain are shown in Figure 16, and monitoring strain and calculated strain information are listed in Table 3.
According to the data listed in Figure 16 and Table 3, it can be concluded that the calculated strain is larger than the actual monitored strain, and such a difference at high temperature is larger. In addition, the temperature of steel in the steel assembly bracing is affected by environmental temperature and sunlight radiation, and the surface temperature of each member varies with the degree of sunlight exposure. The temperature of steel used in calculation and simulation comes from SSTS-01, which is located on the upper surface of the first support of the steel assembly bracing. During the monitoring period, it receives more sunlight radiation, which belongs to the support area most affected by temperature and is the most unfavorable position affected by temperature. When the input steel temperature measuring point is located in the position that can accept the full radiation of the sun, the calculation and analysis results of temperature action according to the high temperature environment are too large, but it is beneficial to the structural safety from the engineering point of view.
Then, the finite element dynamic analysis is carried out under the vibration action of the earthwork truck after amplitude modulation. The total time of model calculation is 6 s, the step size is 0.005 s, and the sampling frequency of the field vibration sensor is 200 Hz. It is assumed that the temperature of steel is approximately in a stable state of 50.6 °C during the period when the earthwork truck passes through the trestle bridge. As shown in Figure 17, Figure 18, Figure 19 and Figure 20 below, the monitoring data of the dynamic strain of typical position number DSS-06 (the same position as static strain SSTS-01), DSS-10, DSS12 and DSS-14 of T01 are compared with the calculation results at the same point of the model (the monitoring data of dynamic strain of other positions are in Supplementary Materials).
The following conclusions can be drawn from the data analysis of Figure 17, Figure 18, Figure 19 and Figure 20: (1) Dynamic strain responses monitored, except for DSS-10, are less than the calculated results, including the dynamic strains of other measuring points not listed in this paper; (2) The maximum monitoring value of DSS-10 is 0.76 με, which is slightly larger than the calculated result of 0.46 με. Considering the influence of a tower crane near the measured support point, the larger monitoring value may be acceptable; (3) The maximum dynamic strain of measuring points is 1.4 με, which accounts for about 1% of the static strain of 146.44 με of steel assembly bracing under a high temperature of 50.6 °C. The sum of the stress caused by temperature rise and the maximum stress caused by vibration is 30.46 MPa, which is larger than that of the first (initial pre-axial force P01 = 3200 kN, compressive stress 18.22 MPa) and the second (initial pre-axial force P01 = 8000 kN, compressive stress 22.78 MPa) bracing initial prestress of T01 and less than the yield strength of steel.

3.2. Acceleration of the Steel Assembly Bracing

Figure 21 shows the vertical calculated acceleration response and monitored acceleration response of measuring point 3AS-02 on steel assembly bracing. The acceleration response is less than the calculated results. It should be noted that the vertical vibration of T01 steel assembly bracing causes complaints from on-site construction technicians, which can be clearly felt during the construction. In order to understand the influence of the vibration of steel assembly bracing on the walking comfort of technicians, according to ISO 2631-1:1997, the vertical frequency-weighted vibration acceleration is calculated as aw = 79.30 dB for Figure 21. Obviously, the vertical frequency weighted acceleration aw is really large and it is reasonable for technicians to complain about the insecurity of bracing vibration [24].

4. Conclusions

As a new type of bracing system for the construction of deep, large foundation pits, steel assembly bracing has been gradually applied in the civil engineering field. In this paper, the effects of vibration and temperature of the construction site on steel assembly bracing of the foundation pit is studied by virtue of the safety real-time monitoring system and FEM technology based on an engineering case. The following conclusions can be drawn:
(1) The influence of environmental temperature on steel assembly bracing is significant and cannot be ignored. The axial compressive stress of bracing caused by environmental temperature even exceeds the prestress. Under the most unfavorable conditions, the stress caused is less than the yield strength of material Q355b, and hence the steel assembly bracing is in a safe state.
(2) The steel assembly bracing is made up of hundreds of H-beams of different specifications connected by high-strength bolts, and the bolt joints are easy to loosen due to construction vibration. Therefore, the working state of key joints of the steel assembly bracing should be checked regularly during construction. Meanwhile, the steel assembly bracing is under axial compression, and the out-of-plane vertical deformation has great influence on its stability. Accordingly, it is necessary to regularly monitor the out-of-plane deformation of brace.
(3) The vertical frequency-weighted vibration acceleration aw is an important indicator to reflect the comfort related with vibration. In this engineering case, this value of the steel assembly bracing aw = 79.30 dB, which is large. The reality is that on-site technicians complained about the insecurity of bracing vibration which is consistent with our theoretical analysis.
(4) The safety real-time monitoring system can be used as an effective way to analyze the steel assembly bracing under complex working conditions. The results of the paper can provide guidance for the systematic design and further application of steel assembly bracing in engineering.

Supplementary Materials

The following supporting information can be downloaded at: https://www.mdpi.com/article/10.3390/buildings13020450/s1, Figures S1–S11 about Dynamic strain comparison between simulation and monitoring of DSS-01 to DSS-16.

Author Contributions

Conceptualization, Y.Y., B.Y. and Y.L.; methodology, Y.Y. and Y.L.; software, B.Y., H.Z. and X.L.; validation, Y.L.; formal analysis, Y.Y. and H.Z.; investigation, Y.Y. and H.Z.; resources, Y.L.; data curation, Y.Y. and H.Z.; writing—original draft preparation, Y.Y. and H.Z.; writing—review and editing, B.Y. and X.L.; visualization, X.L. and B.Y.; supervision, X.L. and B.Y.; project administration, Y.Y., B.Y. and Y.L.; funding acquisition, Y.Y. and Y.L. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the Natural Science Foundation of Zhejiang Province, grant number LGG20E080002.

Data Availability Statement

Not applicable.

Conflicts of Interest

The funders had no role in the design of the study; in the collection, analyses, or interpretation of data; in the writing of the manuscript; or in the decision to publish the results.

References

  1. Cai, W.; Lin, Y.; Wen, F. Analysis of Temperature Difference Effect of Long-Span Plate-Truss Composite Girder. Bridge Constr. 2019, 49, 41–46. [Google Scholar]
  2. Zhu, Q.; Wang, H.; Mao, J.; Wan, H.; Zheng, W.; Zhang, Y. Investigation of Temperature Effects on Steel-Truss Bridge Based on Long-Term Monitoring Data: Case Study. J. Bridge Eng. 2020, 25, 05020007. [Google Scholar] [CrossRef]
  3. Batten, M.; Powrie, W.; Boorman, R.; Yu, H.; Leiper, Q. Use of vibrating wire strain gauges to measure loads in tubular steel props supporting deep retaining walls. Proc. Inst. Civil Eng.-Geotech. Eng. 1999, 137, 3–13. [Google Scholar] [CrossRef]
  4. Han, L.; Sun, M.; Huang, P.; Chen, H.; Wang, Q. Design analysis and engineering application research of new H-section steel support system. Build. Struct. 2021, 51, 95–102. [Google Scholar]
  5. Venglar, M.; Lamperova, K. Effect of the temperature on the modal properties of a steel railroad bridge. Slovak. J. Civ. Eng. 2021, 29, 1–8. [Google Scholar] [CrossRef]
  6. Luo, J.; Huang, M.; Lei, Y. Temperature Effect on Vibration Properties and Vibration-Based Damage Identification of Bridge Structures: A Literature Review. Buildings 2022, 12, 1209. [Google Scholar] [CrossRef]
  7. de Battista, N.; Brownjohn, J.M.W.; Tan, H.P.; Koo, K.Y. Measuring and modelling the thermal performance of the Tamar Suspension Bridge using a wireless sensor network. Struct. Infrastruct. Eng. 2015, 11, 176–193. [Google Scholar] [CrossRef]
  8. Li, Y.; Chen, D.; Liu, X.; Zhu, H.; Tang, D. Application of prestressed assemble steel support system in retaining structures for foundation pits in soft soils. Chin. J. Geotech. Eng. 2014, 36, 51–55. [Google Scholar]
  9. Liu, X.; Tong, G.; Li, Y.; Hu, H.; Chen, D. Stability Analysis of Assembly Steel Struts in Deep Excavation. Eng. Mech. 2020, 35, 200–207. [Google Scholar]
  10. Li, H.; Tang, Y.; Liao, S.; Shen, M. Structural Response and Preservation of Historic Buildings Adjacent to Oversized Deep Excavation. J. Perform. Constr. Facil. 2021, 35, 04021095. [Google Scholar] [CrossRef]
  11. Cui, X.; Ye, M.; Zhuang, Y. Performance of a foundation pit supported by bored piles and steel struts: A case study. Soils Found. 2018, 58, 1016–1027. [Google Scholar] [CrossRef]
  12. He, J.; Liao, S.; Sun, J.; Tang, J. Study on axial force interference of soft soil deep excavation under multi-point synchronous loading. China Civil. Eng. J. 2020, 53, 99–107. [Google Scholar]
  13. Boone, S.J.; Crawford, A.M. Braced Excavations Temperature, Elastic Modulus, and Strut Loads. J. Geotech. Geoenviron. Eng. 2000, 126, 870–881. [Google Scholar] [CrossRef]
  14. Hu, Q.; Zhang, K.; Song, J.; Fang, H.; Xie, J.; He, P.; Ran, L. Numerical Simulation and Analysis of Thermal Stress on Restressed Assembly Steel Struts System in Foundation Excavation. IOP Conf. Ser. Earth Environ. Sci. 2019, 300, 022162. [Google Scholar] [CrossRef]
  15. Wu, M.; Du, C.; Yang, K.; Geng, X.; Liu, X.; Xia, T. A new empirical approach to estimate temperature effects on strut loads in braced excavation. Tunn. Undergr. Space Technol. 2019, 94, 103115. [Google Scholar] [CrossRef]
  16. Wang, F.; Shi, G.; Zhai, W.; Li, B.; Zhang, C.; Fang, H. Internal Force on and Deformation of Steel Assembled Supporting Structure of Foundation Pit under Thermal Stress. Appl. Sci. 2021, 11, 2225. [Google Scholar] [CrossRef]
  17. Li, B.; Qu, J.; Ge, S. Effect of Temperature on Supporting Structure of Metro Deep Foundation Pit. J. Shenyang Jianzhu Univ (Nat. Sci.) 2021, 37, 69–76. [Google Scholar]
  18. Zhang, X.; Chen, J.; Wan, L.; Luo, W.; Xu, C. Field test and analysis of vehicle load and its influence on the retaining structure of adjacent foundation pits. China Earthq. Eng. J. 2020, 42, 490–497. [Google Scholar]
  19. Wang, Z.; Guo, X.; Wang, C. Field Monitoring Analysis of Construction Process of Deep Foundation Pit at Subway Station. Geotech. Geol. Eng. 2019, 37, 549–559. [Google Scholar] [CrossRef]
  20. Yang, Y.; Lu, J.; Huang, X.; Tu, X. Sensor monitoring of a newly designed foundation pit supporting structure. J. Cent. South Univ. 2013, 20, 1064–1070. [Google Scholar] [CrossRef]
  21. Zhuang, S.; Zhang, J.; Zhang, C.; Li, S. On stiffness of prefabricated prestressed fish-belly steel support system. China Civil. Eng. J. 2021, 54, 18–25. [Google Scholar]
  22. Tong, L.; Li, H.; Ha, S.; Liu, S. Lateral bearing performance and mechanism of piles in the transition zone due to pit-in-pit excavation. Acta Geotech. 2022, 17, 1935–1948. [Google Scholar] [CrossRef]
  23. Shi, X.; Rong, C.; Cheng, H.; Cui, L.; Wang, B.; Sun, S. Analysis on deformation and stress characteristics of a multibraced pit-in-pit excavation in a subway transfer station. Adv. Civ. Eng. 2020, 2020, 8844461. [Google Scholar] [CrossRef]
  24. ISO 2631-1; Mechanical Vibration and Shock Evaluation of Human Exposure to Whole-Body Vibration Part 1: General Requirements. International Organization Standardization: Geneva, Switzerland, 1997; p. 12.
Figure 1. Steel assembly bracing of foundation pit and truck driving route.
Figure 1. Steel assembly bracing of foundation pit and truck driving route.
Buildings 13 00450 g001
Figure 2. Side view of steel assembly bracing of foundation pit.
Figure 2. Side view of steel assembly bracing of foundation pit.
Buildings 13 00450 g002
Figure 3. Layout of monitoring points in steel assembly bracing.
Figure 3. Layout of monitoring points in steel assembly bracing.
Buildings 13 00450 g003
Figure 4. Numerical model of foundation pit braced by section steel assembly.
Figure 4. Numerical model of foundation pit braced by section steel assembly.
Buildings 13 00450 g004
Figure 5. Vertical first-order vibration mode (6.16 Hz).
Figure 5. Vertical first-order vibration mode (6.16 Hz).
Buildings 13 00450 g005
Figure 6. Vertical second-order vibration mode (6.31 Hz).
Figure 6. Vertical second-order vibration mode (6.31 Hz).
Buildings 13 00450 g006
Figure 7. Vertical third-order vibration mode (6.59 Hz).
Figure 7. Vertical third-order vibration mode (6.59 Hz).
Buildings 13 00450 g007
Figure 8. Vertical fourth-order vibration mode (7.02 Hz).
Figure 8. Vertical fourth-order vibration mode (7.02 Hz).
Buildings 13 00450 g008
Figure 9. Temperature–strain diagram of steel assembly bracing during monitoring period (12 August to 22 November 2022).
Figure 9. Temperature–strain diagram of steel assembly bracing during monitoring period (12 August to 22 November 2022).
Buildings 13 00450 g009
Figure 10. Vibration action of earthwork truck.
Figure 10. Vibration action of earthwork truck.
Buildings 13 00450 g010
Figure 11. Test system of vehicle vibration.
Figure 11. Test system of vehicle vibration.
Buildings 13 00450 g011
Figure 12. Vibration response of concrete trestle bridge.
Figure 12. Vibration response of concrete trestle bridge.
Buildings 13 00450 g012
Figure 13. Vibration response of steel assembly bracing.
Figure 13. Vibration response of steel assembly bracing.
Buildings 13 00450 g013
Figure 14. Maximum vibration response of trestle bridge during monitoring period.
Figure 14. Maximum vibration response of trestle bridge during monitoring period.
Buildings 13 00450 g014
Figure 15. Mass distribution of front and rear wheels of earthwork trucks.
Figure 15. Mass distribution of front and rear wheels of earthwork trucks.
Buildings 13 00450 g015
Figure 16. Influence of typical ambient temperature change on steel brace strain.
Figure 16. Influence of typical ambient temperature change on steel brace strain.
Buildings 13 00450 g016
Figure 17. Comparison of dynamic strain between measurement and simulation results of DSS-06.
Figure 17. Comparison of dynamic strain between measurement and simulation results of DSS-06.
Buildings 13 00450 g017
Figure 18. Comparison of dynamic strain between measurement and simulation results of DSS-10.
Figure 18. Comparison of dynamic strain between measurement and simulation results of DSS-10.
Buildings 13 00450 g018
Figure 19. Comparison of dynamic strain between measurement and simulation results of DSS-12.
Figure 19. Comparison of dynamic strain between measurement and simulation results of DSS-12.
Buildings 13 00450 g019
Figure 20. Comparison of dynamic strain between measurement and simulation results of DSS-14.
Figure 20. Comparison of dynamic strain between measurement and simulation results of DSS-14.
Buildings 13 00450 g020
Figure 21. Comparison of vertical acceleration between measurement and simulation results of 3AS-02.
Figure 21. Comparison of vertical acceleration between measurement and simulation results of 3AS-02.
Buildings 13 00450 g021
Table 1. Physical and mechanical parameters of soil layer.
Table 1. Physical and mechanical parameters of soil layer.
Name of Soil LayerThickness of Soil Layer h (m)Unit Weight γ (N/m3)Elastic Modulus E (MPa)Poisson’s Ratio υ
Miscellaneous fill6.0185007.40.40
Sandy silt10.6194009.90.35
Silt with sand3.51970011.30.34
Sandy silt2.4194009.90.35
Muddy clay5.0192003.60.41
Silty clay2.5198007.70.35
Table 2. Physical and mechanical parameters of steel assembly bracing.
Table 2. Physical and mechanical parameters of steel assembly bracing.
Material of Supporting StructureElastic Modulus E (MPa)Poisson’s Ratio μDensity ρ (kg/m3)
Diaphragm wall31,0000.22400
Surrounding purlin31,0000.22400
Steel assembly bracing210,0000.37850
Section steel column210,0000.37850
Table 3. Strain of steel brace at different ambient temperatures.
Table 3. Strain of steel brace at different ambient temperatures.
Temperature ConditionSteel Temperature (°C)Temperature Difference (°C)Calculated Strain (με)Measured Strain (με)Calculated Strain –Measured Strain (με)
Low temperature environment10~18.98.987.4053.5533.85
Moderate temperature environment11.7~32.721.0187.94131.6956.25
High temperature environment26.5~50.624.1258.44146.44115.88
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Yang, Y.; Zeng, H.; Liu, X.; Yang, B.; Li, Y. Real-Time Monitoring for Effects of Vibration and Temperature of Construction Site on Steel Assembly Bracing of Foundation Pit. Buildings 2023, 13, 450. https://doi.org/10.3390/buildings13020450

AMA Style

Yang Y, Zeng H, Liu X, Yang B, Li Y. Real-Time Monitoring for Effects of Vibration and Temperature of Construction Site on Steel Assembly Bracing of Foundation Pit. Buildings. 2023; 13(2):450. https://doi.org/10.3390/buildings13020450

Chicago/Turabian Style

Yang, Yingwu, Hangbin Zeng, Xingxi Liu, Bo Yang, and Ying Li. 2023. "Real-Time Monitoring for Effects of Vibration and Temperature of Construction Site on Steel Assembly Bracing of Foundation Pit" Buildings 13, no. 2: 450. https://doi.org/10.3390/buildings13020450

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop