Next Article in Journal
Feeling Good in the Place We Live: The Moderating Role of the Perception of Environmental Resources in the Relationship between Values and Personal and Family Well-Being
Previous Article in Journal
Visualizing Sustainable Supply Chain Management: A Systematic Scientometric Review
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Stability Control of Deep Coal Roadway under the Pressure Relief Effect of Adjacent Roadway with Large Deformation: A Case Study

1
Key Laboratory of Deep Coal Resource Mining, Ministry of Education of China, School of Mines, University of Mining and Technology, Xuzhou 221116, China
2
Open Laboratory for Large-Scale Scientific Instruments, Jiangsu Normal University, Xuzhou 221116, China
3
Zhongtian Hechuang Energy Co. Ltd., Ordos 017020, China
*
Authors to whom correspondence should be addressed.
Sustainability 2021, 13(8), 4412; https://doi.org/10.3390/su13084412
Submission received: 3 March 2021 / Revised: 12 April 2021 / Accepted: 14 April 2021 / Published: 15 April 2021

Abstract

:
High-efficiency maintenance and control of the deep coal roadway surrounding rock stability is a reliable guarantee for sustainable development of a coal mine. However, it is difficult to control the stability of a roadway that locates near a roadway with large deformation. With return air roadway 21201 (RAR 21201) in Hulusu coal mine as the research background, in situ investigation, theoretical analysis, numerical simulation, and engineering practice were carried out to study pressure relief effect on the surrounding rock after the severe deformation of the roadway. Besides, the feasibility of excavating a new roadway near this damaged one by means of pressure relief effect is also discussed. Results showed that after the strong mining roadway suffered huge loose deformation, the space inside shrank so violently that surrounding rock released high stress to a large extent, which formed certain pressure relief effect on the rock. Through excavating a new roadway near this deformed one, the new roadway could obtain a relative low stress environment with the help of the pressure relief effect, which is beneficial for maintenance and control of itself. Equal row spacing double-bearing ring support technology is proposed and carried out. Engineering practice indicates that the new excavated roadway escaped from possible separation fracture in the roof anchoring range, and the surrounding rock deformation of the new roadway is well controlled, which verifies the pressure relief effect mentioned. This paper provides a reference for scientific mining under the condition of deep buried and high stress mining in western China.

1. Introduction

With China’s main coal mining center moving westward [1,2,3], the average mining depth of the western mining area continues to extend at the rate of 10–25 m per year [4,5], which is about to reach the absolute deep coal mining of 700–1000 m [6]. Due to the fact that the layout of double roadways can alleviate the imbalance of mining ratio and realize the rapid recovery of coal resources, some western mining areas still adopt double roadways after entering deep mining. They draw lessons from the layout of double roadway with large coal pillar used in shallow mining area, namely “one working face with three roadways” layout (the layout of double roadways) [7,8,9], in which the auxiliary transportation roadway is reserved as the return air roadway of the next working face with a 20–40 m coal pillar [10]. However, obvious defects are shown in the layout of double roadways. During the service period, the auxiliary roadways have experienced many times of mining disturbance, which is prone to severe contraction of roadway section, deformation, fracture, and instability, and even cannot continue to serve for the working face in the next section. At this time, it is the only choice to re-excavate the return air roadway of the next working face, and the selection of roadway excavation position becomes very important. As for the high gas mine that contains a connecting roadway, it is the only choice to look for the pressure relief area formed by roadway excavation and re-excavating the roadway along the residual roadway, in order to prevent the gas and other harmful gas from overflowing during driving.
For excavating roadway in pressure relief area, most of the existing researches focus on gob-side roadway excavating, using “voussoir beam theory” to analyze the pressure relief mechanism and the selection of reasonable position (coal pillar width). Zheng [11] developed a mechanical model of gob-side roadway overburdens to analyze the large deformation and stress field distribution. In order to mitigate the problem of the coal pillar extrusion and serious deformation that will occur in the gob-side roadway, Tai [12] developed the roof-cutting technology with a chainsaw arm and its equipment. Zhang [13] investigated the effects of dynamic loading to gob-side entries and optimized the support parameters; the field test results showed that the potential for loosening, deformation, and failure of the surrounding rock were effectively controlled. Wu [14] studied the initiation, propagation, and failure of cracks within this gob-side coal pillar during its formation by using the methods of field tests and numerical modeling. Zhang [15] had studied how to set narrow coal pillar along the edge of upper goaf in large coal pillar to excavate the roadway in this section. The stability and failure mechanism of coal pillar have also been widely studied [16,17]. The existing research results focus on the stability of narrow coal pillar and the reasonable width of section coal pillar. However, research on the problem of width choice in the coal pillar is not adequate. With the help of the pressure relief effect of the surrounding rock caused by the severe deformation of the residual auxiliary transportation roadway in the upper sectional working face, it is worth researching how to determine the width of the coal pillar in the return air roadway of the working face in this section by setting a narrow coal pillar along the broken roadway.
In view of the problems above, this paper takes the RAR 21201 of Hulusu coal mine as the engineering background, analyzes the pressure relief effect on the surrounding rock after the violent deformation of roadway, and probes into the feasibility of excavating new RAR 21201 near this deformed roadway 21102 (AHR 21102) after setting a narrow coal pillar. Equal row-spacing double-bearing ring support technology is proposed, and engineering practice has verified the pressure relief effect on the new roadway, which improves the controlling effect of surrounding rock.

2. Project Overview

2.1. Roadway Location and Mining Relationship

Hulusu coal mine is located in Ordos City, Inner Mongolia Province, China, with a depth of 650–900 m. It is a typical kind of Western deep buried mine. In the early stage of the mine, the “the layout of double roadways” method was adopted (Figure 1), in which the AHR 21102 served for the working face 21102. After the mining of the working face 21102, the AHR 21102 was reserved as the return air roadway of the working face 21201 in the second panel area, and a 30-m coal pillar was reserved between the working face 21102 and the working face 21102. As the result of severe deformation, most of the roadway sections have no value of roadway repairing, so it is considered to set up a new coal pillar along the west side of AHR 21102 and excavate RAR 21201 to serve working face 21201. According to the in-situ stress measurement data provided by the mine, the maximum horizontal stress is 24.74 MPa, the maximum vertical stress is 16.31 MPa, and the maximum minimum horizontal principal stress is 13.36 MPa. The angle of maximum horizontal principal stress is between N20.4° and 38.5° W, and the direction of roadway axis is north-south direction, that is, the angle between maximum horizontal principal stress and roadway axis is between N20.4° and 38.5° W.

2.2. Lithology of Coal Seam, Roof and Floor

The average thickness of main mining 2–1 coal seam is 2.79 m, and the average buried depth is 626.65 m. The immediate roof is sandy mudstone with an average thickness of 4 m, and the floor is mainly sandy mudstone and fine-grained sandstone. The concrete occurrence and the mechanical parameters of the roof and floor strata are shown in Table 1.

2.3. Support Scheme of Auxiliary Haulage Roadway 21102

As shown in Figure 2, the roof of AHR 21102 is supported by “blot + cable” at stage of excavating. The roof is supported by five Φ 20 × 2200-mm left-hand threaded steel bolts. Moreover, the bolts in the left wing and right wing had an indentation of 15° and the rest were installed vertically. Each bolt is anchored by one MSCK 2370 mm resin coil and the pretension of bolt is 60 kN. In addition, two Φ 17.8 × 6200 mm cables are arranged for two rows of anchor bolts in each interval as the reinforcement support. All the cables were installed vertically on the roof of the roadway. Each cable was anchored with two MSCK 2370 mm resin coils, with pretension of 130 kN. Furthermore, the inter-row spacing of the bolts and anchor cables is 1100 × 1000 mm and 2200 × 2000 mm, respectively. Each row of non-mining side of roadway is supported by three Φ 20 × 2200 mm left-hand threaded steel bolts and the row spacing between bolts is 1000 × 1000 mm. Besides, the top angle and bottom angle of coal side are installed with 15° inclination and the rest bolts are installed vertically to the rock surface. Each bolt is anchored by one MSCK 2370 mm resin coil and the pretension of bolt is 30 kN, and each row of mining side is installed with three Φ 27 × 2000 mm glass fiber-reinforced plastics bolts. Finally, the inter-row spacing of the bolts is 1000 × 1000 mm, and the pretension of the bolt is 12 kN.

2.4. Maintenance Status of AHR 21102

Affected by the mining stress of the working face 21102, the AHR 21102 has a large deformation, and different roadway sections show different degrees of section contraction. The full section of roadway lane 2 and lane 4 (Figure 1) is pressed and shrinks violently, and the roof and floor of some sections are almost closed, relying on the wooden crib support (Figure 3), so it cannot be used as the return air roadway of the working face 21201. Although the surrounding rock of lane 1, lane 3, and lane 5 roadway section has large deformation, the stability structure of surrounding rock still exists.

3. Pressure Relief Mechanism of Roadway with Large Deformation

3.1. Principle of Pressure Relief of Roadway with Large Deformation

Given that there is a 30-m wide coal pillar between AHR 21102 and working face 21102, the high concentrated stress caused by working face 21102 mining mainly acts on the 30-m-wide coal pillar during the mining period of working face 21102. The wide coal pillar produces a large amount of deformation under the action of high stress, resulting in the whole cross section of the RAR 21201 being under great pressure and having great deformation and failure full section weighting and severe contraction. As a result, a certain range of pressure relief area is formed near the working face 21201. If the pressure relief effect of the surrounding rock caused by the violent deformation of AHR 21102 is used, the reasonable width narrow coal pillar is reserved at the working face 21201 side of AHR 21102 to excavate RAR 21201, so that the narrow coal pillar bears less stress, and the RAR 21201 is in the pressure relief zone, which is not only conducive to the maintenance of the roadway, but also improves the recovery rate of coal resources. Two coal pillars are formed on both sides of AHR 21102. One side is the residual 30 m wide coal pillar, which is called pressure-bearing pillar (Figure 4), and the other side is the protective coal pillar of 21201 return air roadway (hereinafter referred to as protective coal pillar). Because the protective coal pillar bears less stress, it is called a pressure-yielding pillar. The width of the pressure-yielding pillar is the key to determine whether the RAR 21201 can be in the effective pressure relief area.

3.2. Simulation Analysis of Pressure Relief Effect

3.2.1. Setting up the Numerical Model

The finite difference FLAC3D numerical model is established based on the working face 21102, AHR 21102 and RAR 21201 with a coal pillar along the 21102 auxiliary haulage roadway. The model length × width × height = 270 m × 120 m × 78 m (Figure 5). The width of 21102 working face is 165 m (half, actual width is 330 m), and the dimensions of 21102 auxiliary haulage roadway and 21201 return air roadway are width × height = 5 m × 2.8 m (according to the actual cross-section size of roadway). In order to ensure the calculation accuracy, the grid of roadway and coal pillar area is designed to be densified. The upper end of the model is a free surface with a vertical load of 15 MPa (calculated according to the actual buried depth of 626 m). Besides, the displacement boundary conditions are applied both around and at the bottom of the model. The bottom boundary of the model is fixed in the vertical direction, while the left and right boundaries fixed in the horizontal direction to eliminate the displacement. Besides, the model adopts the Mohr-Coulomb yield criterion, and the physical parameters of rock stratum are shown in Table 1; the text related to Table 1 and the caption should clearly state the parameters were taken from [18,19,20] and that they represent rock mass properties while considering the effect of cleat networks in the coal seam.
The numerical calculation process is as follows: original rock stress calculation → excavation of AHR 21102 → mining of working face 21102 → excavation of RAR 21201 by setting different width (2 m, 4 m, 6 m, 8 m, 10 m, 12 m, 14 m, 16 m, 18 m, 20 m) protective coal pillars.

3.2.2. Calculation Results

It can be concluded from Figure 6 that: (1) the 30 m residual coal pillar work is in cooperation and linkage with the protective coal pillar of the RAR 21201. When the width of the protective coal pillar is small (e.g., 2 m, 4 m, 6 m), the vertical stress above the 30 m residual coal pillar is higher than that when the RAR 21201 is not excavated, and the vertical stress above the corresponding protective coal pillar is lower than that when the RAR 21201 is not excavated; (2) with the increase of coal pillar width (2 m~10 m), the width of elastic core area in the coal pillar increases and begins to undertake higher concentrated stress, which makes the concentrated stress above the 30 m residual coal pillar decrease; (3) when the width of the coal pillar increases to a certain range (10 m~20 m), the RAR 21201 enters into the original rock stress area by avoiding the stress rising area, which is formed in the lateral solid coal after mining in the 21102 working face of the upper section. Therefore, the vertical stress above the coal pillar has a decreasing trend, at this time, the vertical stress above the 30 m residual coal pillar also gradually returns to the state when the RAR 21201 is not excavated; (4) the width of coal pillar should be less than 8~10 m when considering the pressure relief effect of surrounding rock caused by severe deformation of AHR 21102.

4. Engineering Practice and Mining Pressure Monitoring

4.1. Determination of Coal Pillar Width of RAR 21201

According to the calculation method of yield coal pillar width in [21], the width calculation method of pressure-yielding pillar is as follows:
P = L p γ H
where Lp is the width of the roof loading zone of the yielding coal pillar. It can be concluded from Figure 4 that:
L p = ( 0.5 b + L n + d ) / 2
where b, d is the width of RAR 21201 and AHR 21102 respectively, which is 2.8 m according to the actual width of the two roadways; H is the buried depth of roadway, which is 620 m; and γ is the volume weight of overlying strata, which is 25 kN/m3.
The ultimate bearing load of the protective coal pillar of return air roadway is as follows:
Q = L n R ( L n / M ) 2 / 3
where: R is the ultimate compressive strength of pressure-yielding pillar, which is 15 MPa. The concentration factor of abutment pressure in advance of working face is k = 3. Making kP = Q, we can get the limit coal pillar (pressure-yielding pillar) Ln = 10.9 m. Combined with the results of numerical simulation and engineering practice, the coal pillar width of RAR 21201 is determined to be 10.75 m.

4.2. Support Scheme Design

4.2.1. Roof Supporting

In the previous support scheme, the length of bolt and cable is quite different, and the outer layer of bolt anchoring zone is borne by cable, but the density of the cable is low. When the cable is too close to the bolt, the anchoring stress interferes with each other, resulting in poor group supporting effect. Due to the different mechanical properties of bolt and cable, it is difficult to carry the load cooperatively. The early load is mainly concentrated on the cable with higher pretension and stronger sensitivity. In case of strong dynamic pressure, the cable is often broken first and then the bolt is broken again, and the support system is broken by each one. In order to promote the bolt and cable cooperative bearing support, the previous support scheme should be optimized, and the optimized support scheme is as follows:
The roof adopts the “bolt + cable” equal row spacing double-bearing ring support technology [22,23].
(1) Bolt support: The roof is supported by six Φ 20 × 2200 mm left-hand threaded steel bolts (Figure 7). The bolts in the left wing and right wing have an indentation of 15° and the rest are installed vertically. Each bolt is anchored by one MSCK 2370 mm resin coil and the pretension of bolt is 60 kN, and the inter-row spacing of the bolts is 1100 × 2000 mm.
(2) Cable support: Each row of the roof is supported by four Φ 21.8 × 4300 mm cables, all of which are vertical to the roof of roadway. Each cable is anchored by two MSCK 2370 mm resin coils, and the pretension is 200 kN.

4.2.2. Coal Rib of Roadway Supporting

The “bolt + cable” combined support is adopted for the coal rib, that is, the high-strength screw steel bolt is used as the foundation support for both ribs, and the cable is used as the reinforcement support for the side of the coal pillar.
(1) Foundation support: Each row of the coal rib is supported by three left-hand threaded steel bolts with diameter of 22 × 2800 mm and diamond-shaped metal mesh; the inter-row spacing of the bolts is 1000 × 1000 mm; the top angle and bottom angle of coal side are installed with 15° inclination; and the rest bolts are installed vertically to the rock surface. Each bolt was anchored by one MSCK 2370 mm resin coil and the pretension of bolt is 60 kN.
(2) Reinforced support at the side of coal pillar: Every two rows of bolts are reinforced by two Φ 21.8 × 4300 mm cables; the inter-row spacing of the bolts is 1800 × 1000 mm. The upper and lower anchor cables are installed at an external angle of 20°, and each cable is anchored with two MSCK 2370 mm resin coils with a pretension of 200 kN.

4.3. Mine Pressure Monitoring

4.3.1. Monitoring of Roadway Surface Displacement

During roadway excavation, four roadway surface displacement measuring stations are arranged: numbered WY1, WY2, WY3, and WY4 in turn. Among them, WY1 and WY2 measuring stations are arranged in the 21201 roadway corresponding to roadway lane 1 (Figure 1); WY3 and WY4 measuring stations are arranged in the 21201 roadway corresponding to roadway lane 2. The cross section method is adopted for monitoring. The displacement curves of the four measuring stations are shown in Figure 8.
(1) Within the range of 30~50 m away from the excavating face, the monitoring results of the four stations show that the deformation of two ribs and roof subsidence increase rapidly, showing a linear growth trend. When the distance between the station and the excavating face exceeds 50 m, with the weakening of the dynamic pressure disturbance, the deformation decreases significantly, then tends to be stable, and finally enters the rheological period. After stability, the maximum deformation of the middle point of the roof is 35~70 mm, and the maximum displacement of two ribs is 161~244 mm. In addition to the station of WH1, the deformation of coal pillar side is slightly larger than that of solid coal side.
(2) The deformation of the floor varies from the four stations among which the floor deformation of WY1 and WY2 station is more severe. With the increasing distance between station and excavating face, the amount and rate of deformation have no obvious trend of stabilization. During the monitoring period, the maximum floor deformations of WY1 and WY2 station are 391 mm and 331 mm respectively. On the contrary, the corresponding floor deformations of WY3 and WY4 station is relatively mild, and the floor deformation tends to be stable with the weakening of driving dynamic pressure disturbance. The maximum floor deformations of WY3 and WY4 station are 111 mm and 83 mm respectively. Compared with WY1 and WY2 station, the floor deformations of the WY3 and WY4 are obviously improved.

4.3.2. Roof Separation Crack Monitoring

There are two boreholes in the roof separation cracks of roadway, numbered ZK1 and ZK2 in turn, which are respectively located in the 21201 roadway corresponding to roadway Section 1 and roadway Section 2. The integrity of roof strata reflected by drilling is shown in Figure 9. Results of two boreholes show that there are no obvious separation cracks inside and outside the anchorage zone of roof bolt and anchor cable, and the roof integrity is good.
The results indicate that the “bolt + cable” equal row-spacing double-bearing ring support technology can effectively control the development of internal and external separation cracks in the roof anchorage zone, and finally guarantee the integrity and stability of the roof deep surrounding rock.

5. Roadway Maintenance Effect and Discussion

5.1. Roadway Surrounding Rock Control Effect

RAR 21201 has been excavated for nearly 700 m, whose excavating face is located in the corresponding roadway section of roadway lane 2. According to the control effect of roadway surrounding rock, the roof rock layers of the two roadway lanes are relatively complete, showing no obvious separation cracks both inside and outside the anchorage zone. Besides, there are significant differences in the construction conditions, which are shown as follows: When the roadway is excavating into the corresponding roadway lane 1: (1) Floor heave appears generally in the roadway, whose amount is 300~400 mm, and the floor heave time generally begins to appear after 2 days of roadway excavation; (2) the mine pressure behavior of two ribs vary obviously, meanwhile, the coal pillar side shows the phenomenon of vertical outward coal block collapse. Besides, the sound of coal gun is frequent, and the solid coal side is relatively gentle. (3) Hole collapse and top drilling easily occurs when building cables on the coal pillar side, which leads to the longest construction time of single bolt up to 45 min (repeated hole collapse). On the contrary, when the roadway is excavated into the corresponding roadway lane 2: (1) The floor heave phenomenon is obviously improved, with floor heave of 80~120 mm; (2) Coal block collapse and coal gun sound still occur from time to time, with decreased frequency; (3) The problems of hole collapse and top drilling are greatly alleviated during the construction of a cable on the coal pillar side.

5.2. Discussion

(1) At present, RAR 21201 has been excavated for nearly 700 m. Due to the different deformation degrees of roadway lane 1 and lane 2, the two roadway sections of RAR 21201 have shown obvious differences in construction. In the roadway section corresponding to lane 1, the surrounding rock structure of AHR 21102 has not been completely destroyed, and the roof stress has not been fully released. Meanwhile, the protective coal pillar of RAR 21201 still bears large stress, resulting in the strong mining pressure behaviors such as severe floor heave, frequent coal gun sound, hole collapse, and top drilling in the construction of coal pillar side. After entering the roadway lane 2, the severe deformation of the residual roadway effectively releases high concentrated stress of the roof, which informs a pressure relief effect on the surrounding rock. When excavating the RAR 21201, the floor heave, the frequent sound of coal guns, the hole collapse and top drilling in the construction of coal pillar side, and other strong mine pressure phenomena are obviously improved, which means the surrounding rock control effect is good (Figure 10).
(2) According to the field construction situation and surrounding rock control effect of two roadway lanes, when the coal pillar of 21201 return air roadway is 10.75 m, it bears large vertical stress, which is reflected in severe floor heave, coal gun sound, hole collapse, and top drilling of coal pillar side construction (when excavating to the section of lane 1). Even so, the severe deformation section of AHR 21102 still has a pressure relief effect on RAR 21201, which is reflected in the improved equal strength mine pressure phenomenon when excavating to the section of lane 2. In order to achieve high efficiency and safety of later excavation to the mild deformation section, it is necessary to further detect the width of the broken area and the elastic core width of the protective coal pillar. In addition, it is necessary to try to further narrow the width of the roadway pillar, as well as make full use of the pressure relief effect of the severe deformation of AHR 21102 on the surrounding rock, and finally create a good stress environment for the maintenance of a new excavated roadway.

6. Conclusions

(1) Severe deformation of deep roadway can exert a pressure relief effect on surrounding rock mass. The results of numerical simulation show that the pressure relief effect declines with the increase of the width of the coal pillar of RAR 21201. When the width of the coal pillar increases to a certain range, the pressure relief effect basically disappears.
(2) The mine pressure monitoring results of RAR 21201 show that the pressure relief effect of RAR 21201 is not obvious when the deformation of AHR 21102 is relatively mild. During the construction of the roadway, the strong mine pressure phenomenon is obvious including severe floor heave, frequent coal gun soundm and repeated hole collapse during the construction of cable on the coal pillar side. In the section of AHR 21102 with severe deformation, the above-mentioned strong mine pressure problems are significantly improved during the construction of RAR 21201, showing an optimistic pressure relief effect. It proves that the severe deformation of AHR 21102 has pressure relief effect on RAR 21201.
(3) Equal row-spacing double-bearing ring support technology can effectively control the surrounding rock deformation of RAR 21201. As soon as entering the pressure relief area, there is no obvious separation crack development in the roof, and the surrounding rock deformation is well controlled. After stability, the maximum deformation of the midpoint of the roof is 35~70 mm, and the control effect is good.
(4) In the follow-up study, it is worth further studying the deformation degree of different sections in AHR 21102. When excavating to the mild deformation section of auxiliary haulage roadway 21102, the width of broken zone and elastic core of roadway pillar of RAR 21201 should be further detected so to ensure efficient and safe construction. Besides, through a narrower width of coal pillar and application of pressure relief effect on surrounding rock, a better stress environment can be created to maintain RAR 21201.

Author Contributions

Data curation—H.Y.; Formal analysis—H.Y., N.Z. and C.H.; Funding acquisition—H.Y.; Investigation—H.Y. and C.S.; Project administration—N.Z. and C.H.; Writing—original draft—H.Y.; Writing—review & editing—H.Y., N.Z., C.H., G.S., Y.S., K.S. All authors have read and agreed to the published version of the manuscript.

Funding

This work was supported by the Postgraduate Research & Practice Innovation Program of Jiangsu Province (KYCX20_2016), Future Scientists Program of China University of Mining and Technology (2020WLKXJ010).

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Data is contained within the article.

Acknowledgments

The authors are very grateful to the reviewers for carefully reading the manuscript and providing valuable suggestions. Houqiang Yang wants to particularly thank his teachers and girlfriend Suwan Yu for their support.

Conflicts of Interest

The authors declare no conflict of interest.

Abbreviations

AHR 21102auxiliary haulage roadway 21102
RAR 21201return air roadway 21201
WH1The first monitoring station of roadway surface displacement
WH2The second monitoring station of roadway surface displacement
WH3The third monitoring station of roadway surface displacement
WH4The forth monitoring station of roadway surface displacement
ZK1The first monitoring station of roadway roof fracture
ZK2The second monitoring station of roadway roof fracture

References

  1. Wang, J.H.; Kang, H.P.; Liu, J.Z.; Chen, P.P.; Fan, Z.Z.; Yuan, W.M.; Liu, Y.P. Layout strategic research of green coal resource development in China. J. China Univ. Min. Technol. 2018, 47, 15–20. [Google Scholar]
  2. Yao, Q.L.; Tang, C.J.; Liu, Z.C. Discussion on coal and water co-mining in ecologically fragile mining areas in western China. Coal Sci. Technol. 2020, 1–7. Available online: http://kns.cnki.net/kcms/detail/11.2402.TD.20200215.2005.008.html (accessed on 17 February 2020).
  3. Yuan, L.; Zhang, T.; Zhao, Y.X.; Ren, B.; Hao, X.J.; Xu, C. Precise coordinated mining of coal and associated resources: A case of enviromental coordinated mining of coal and associated rare metal in Ordos basin. J. China Univ. Min. Technol. 2017, 46, 449–459. [Google Scholar]
  4. Sun, Y.T.; Li, G.C.; Zhang, J.F. Investigation on jet grouting support strategy for controlling time-dependent deformation in the roadway. Energy Sci Eng. 2020, 8, 2151–2158. [Google Scholar] [CrossRef] [Green Version]
  5. Yuan, L. Strategic thinking of simultaneous exploitation of coal and gas in deep mining. J. China Coal Soc. 2016, 41, 1–6. [Google Scholar]
  6. Xie, H.P.; Zhou, H.W.; Xue, D.J.; Wang, H.W.; Zhang, R.; Gao, F. Research and consideration on deep coal mining and critical mining depth. J. China Coal Soc. 2012, 37, 535–542. [Google Scholar]
  7. Wang, Z.Q.; Su, Y.; Song, Z.Y.; Shi, L.; Sun, Z.W. Technology and application effect analysis of gob-side entry driving for super-long two-entry longwall panel. Chin. J. Rock Mech. Eng. 2018, 37, 4170–4176. [Google Scholar]
  8. Wang, Z.Q.; Wang, H.H.; Shi, L.; Su, Y. Sequential extraction technology for high-intensity super-long two-entry longwall panels. J. China Coal Soc. 2017, 42, 302–310. [Google Scholar]
  9. Dong, Y.D.; Yao, W.; Liu, Y.H. Strong mining pressure treatment in double lane layout working face with large mining depth and high ground stress. Coal Sci. Technol. 2018, 46, 103–107. [Google Scholar]
  10. Wang, B.; Jiang, F.X.; Zhu, S.T.; Qu, X.C.; Zhang, X.F.; Wei, Q.D.; Wu, Z.; Xie, H.D. Mechanism and prevention of rock burst induced by segment pillars in the deep mining areas of Shaanxi-Inner Mongolia adjacent regions. J. Min. Saf. Eng. 2020, 37, 505–513. [Google Scholar]
  11. Zheng, J.; Ju, W.; Sun, X.; Li, Z.; Wang, S.; Liu, B. Large Deformation Mechanics of Gob-Side Roadway and Its Controlling Methods in Deep Coal Mining: A Case Study. Adv. Civ. Eng. 2020, 2020, 1–13. [Google Scholar] [CrossRef]
  12. Tai, Y.; Yu, B.; Xia, B.; Li, Z.; Xia, H. Research on stress release for the gob-side roadway using the roof-cutting technology with a chainsaw arm. R. Soc. Open Sci. 2020, 7, 191663. [Google Scholar] [CrossRef] [PubMed] [Green Version]
  13. Zhang, Y.; Yang, Y.; Zhuge, C. Deformation Caused by Dynamic Load and Support Requirements in a Deep Gob-Side Entry Rock Mass. Adv. Mater. Sci. Eng. 2019, 2019, 1–16. [Google Scholar] [CrossRef] [Green Version]
  14. Wu, W.-D.; Bai, J.-B.; Wang, X.-Y.; Yan, S.; Wu, S.-X. Numerical Study of Failure Mechanisms and Control Techniques for a Gob-Side Yield Pillar in the Sijiazhuang Coal Mine, China. Rock Mech. Rock Eng. 2019, 52, 1231–1245. [Google Scholar] [CrossRef]
  15. Zhang, K.X.; Jiang, Y.D.; Zhang, Z.B.; Zhang, Y.P.; Pang, X.F.; Zeng, X.T. Determining the reasonable width of narrow pillar of roadway in gob entry driving in the large pillar. J. Min. Saf. Eng. 2014, 31, 255–262. [Google Scholar]
  16. Mohan, G.M.; Sheorey, P.; Kushwaha, A. Numerical estimation of pillar strength in coal mines. Int. J. Rock Mech. Min. Sci. 2001, 38, 1185–1192. [Google Scholar] [CrossRef]
  17. Wattimena, R.; Kramadibrata, S.; Sidi, I.; Azizi, M. Developing coal pillar stability chart using logistic regression. Int. J. Rock Mech. Min. Sci. 2013, 58, 55–60. [Google Scholar] [CrossRef]
  18. Xie, Z.; Zhang, N.; Feng, X.; Liang, D.; Wei, Q.; Weng, M. Investigation on the evolution and control of surrounding rock fracture under different supporting conditions in deep roadway during excavation period. Int. J. Rock Mech. Min. Sci. 2019, 123, 104122. [Google Scholar] [CrossRef]
  19. Xie, Z.; Zhang, N.; Meng, F.; Han, C.; An, Y.; Zhu, R. Deformation Field Evolution and Failure Mechanisms of Coal–Rock Combination Based on the Digital Speckle Correlation Method. Energies 2019, 12, 2511. [Google Scholar] [CrossRef] [Green Version]
  20. Yang, H.; Han, C.; Zhang, N.; Pan, D.; Xie, Z. Research and Application of Low Density Roof Support Technology of Rapid Excavation for Coal Roadway. Geotech. Geol. Eng. 2019, 38, 389–401. [Google Scholar] [CrossRef]
  21. Lu, Y.; Zou, X.Z.; Liu, C.Y.; Xing, S.J. Technology of Digging Stress-Relax Entryby the Roadside and Its Application. J. Min. Saf. Eng. 2006, 3, 329–332. [Google Scholar]
  22. Han, C.L.; Zhang, N.; Kan, J.G.; Ran, Z. Mechanism and application of double active control with pressure-relieving and anchoring for gob-side entry retaining. J. China Coal Soc. 2017, 42, 323–330. [Google Scholar]
  23. Yang, H.; Han, C.; Zhang, N.; Sun, C.; Pan, D.; Dong, M. Stability Control of a Goaf-Side Roadway under the Mining Disturbance of an Adjacent Coal Working Face in an Underground Mine. Sustainability 2019, 11, 6398. [Google Scholar] [CrossRef] [Green Version]
Figure 1. Roadway location and mining relationship. (a) General mining layout of Hulusu coal mine (reproduced from literature [18]); (b) geological conditions and layout of the test areas.
Figure 1. Roadway location and mining relationship. (a) General mining layout of Hulusu coal mine (reproduced from literature [18]); (b) geological conditions and layout of the test areas.
Sustainability 13 04412 g001
Figure 2. Support scheme of AHR 21102.
Figure 2. Support scheme of AHR 21102.
Sustainability 13 04412 g002
Figure 3. Maintenance effect of auxiliary haulage roadway 21102.
Figure 3. Maintenance effect of auxiliary haulage roadway 21102.
Sustainability 13 04412 g003
Figure 4. Stress distribution of AHR 21102.
Figure 4. Stress distribution of AHR 21102.
Sustainability 13 04412 g004
Figure 5. Numerical calculation model.
Figure 5. Numerical calculation model.
Sustainability 13 04412 g005
Figure 6. Stress analysis of roadway and coal pillar roof with different width coal pillars.
Figure 6. Stress analysis of roadway and coal pillar roof with different width coal pillars.
Sustainability 13 04412 g006
Figure 7. Support scheme of RAR 21201.
Figure 7. Support scheme of RAR 21201.
Sustainability 13 04412 g007
Figure 8. Surface displacement of the RAR 21201 versus distance to excavation face. (a) The monitoring results of WH1 station; (b) the monitoring results of WH2 station; (c) the monitoring results of WH3 station; and (d) the monitoring results of WH4 station.
Figure 8. Surface displacement of the RAR 21201 versus distance to excavation face. (a) The monitoring results of WH1 station; (b) the monitoring results of WH2 station; (c) the monitoring results of WH3 station; and (d) the monitoring results of WH4 station.
Sustainability 13 04412 g008aSustainability 13 04412 g008b
Figure 9. Monitoring results of roadway roof fracture. (a) The monitoring results of ZK1 station; (b) the monitoring results of ZK2 station.
Figure 9. Monitoring results of roadway roof fracture. (a) The monitoring results of ZK1 station; (b) the monitoring results of ZK2 station.
Sustainability 13 04412 g009
Figure 10. Overall maintenance of roadway. (a) Overall section maintenance of roadway; (b) maintenance effect of coal pillar side.
Figure 10. Overall maintenance of roadway. (a) Overall section maintenance of roadway; (b) maintenance effect of coal pillar side.
Sustainability 13 04412 g010
Table 1. Distribution and mechanical parameters of strata.
Table 1. Distribution and mechanical parameters of strata.
NumberLithologyThickness (m)Density (kg·m−3)Bulk Modulus (GPa)Shear Modulus/(GPa)Internal Friction Angle (°)Cohesion (MPa)
3Sandy mudstone2625302.562.36362.16
2Fine grained sandstone13287321.0113.52423.2
1Sandy mudstone425302.562.36362.16
02–1 Coal318201.921.6224.21.89
−1Sandy mudstone3025302.562.36362.16
−22–2 Coal218201.921.6224.21.89
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Yang, H.; Zhang, N.; Han, C.; Sun, C.; Song, G.; Sun, Y.; Sun, K. Stability Control of Deep Coal Roadway under the Pressure Relief Effect of Adjacent Roadway with Large Deformation: A Case Study. Sustainability 2021, 13, 4412. https://doi.org/10.3390/su13084412

AMA Style

Yang H, Zhang N, Han C, Sun C, Song G, Sun Y, Sun K. Stability Control of Deep Coal Roadway under the Pressure Relief Effect of Adjacent Roadway with Large Deformation: A Case Study. Sustainability. 2021; 13(8):4412. https://doi.org/10.3390/su13084412

Chicago/Turabian Style

Yang, Houqiang, Nong Zhang, Changliang Han, Changlun Sun, Guanghui Song, Yuantian Sun, and Kai Sun. 2021. "Stability Control of Deep Coal Roadway under the Pressure Relief Effect of Adjacent Roadway with Large Deformation: A Case Study" Sustainability 13, no. 8: 4412. https://doi.org/10.3390/su13084412

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop