Next Article in Journal
The Ethically Conscious Flower Consumer: Understanding Fair Trade Cut Flower Purchase Behavior in Germany
Previous Article in Journal
Towards More Resilient Conservation Practices: Bridging the Past and Present of Human–Wildlife Interactions
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Productivity Metrics and Its Implementations in Construction Projects: A Case Study of Singapore

1
School of Civil Engineering, Central South University, Changsha 410004, China
2
Department of Building, National University of Singapore, 4 Architecture Drive, Singapore 117566, Singapore
*
Author to whom correspondence should be addressed.
Sustainability 2021, 13(21), 12132; https://doi.org/10.3390/su132112132
Submission received: 30 August 2021 / Revised: 28 October 2021 / Accepted: 31 October 2021 / Published: 3 November 2021

Abstract

:
Although some studies have used or developed different types of metrics to assess construction productivity in the existing literature, few of them investigated those metrics systematically and the differences between assessment results. This study examined the various types of metrics used in the assessment of the productivity of construction projects. First, a literature review was conducted first to identify prevailing productivity metrics at four levels, namely trade, project, company, and industry. Then, the questionnaire was developed and disseminated to 53 Singapore-based construction companies for data collection. Subsequently, non-parametric statistical tests were conducted to analyze the data collected by the questionnaire. Results showed that the top five metrics in terms of usage frequency and relative importance were “constructability score”, “buildable design score”, “square meter of built-up floor area per man-day”, “square meter per dollar”, and “output per worker.” In addition, results showed that differences existed in the assessment results when productivity metrics at different levels were used to conduct the same measurement. This is the first study to explore the most widely used metrics in productivity assessments of construction projects and investigate possible differences in assessment results. This study could help the authorities to review, evaluate, and modify the productivity metrics used in practice. Thus, this study is beneficial to the practice as well.

1. Introduction

The construction industry is widely reported to have a relatively low productivity level, especially when comparing with other industrial sectors such as mining, manufacturing, and oil and gas [1]. This is mainly because the construction industry is labor-intensive and is deeply affected by various internal and external factors including social culture, environmental and legal constraints, inappropriate management actions, extreme weather, excessive overtime, and transportation conditions [2,3,4,5].
Productivity must be assessed before it can be improved. The assessment of productivity cannot be carried out without appropriate metrics. In the current literature, several researchers have used different metrics to assess productivity. For example, Shehata and El-Gohary [6] used capital productivity, output per worker, and output per work hour as indicators to assess construction labor productivity. Vogl and Abdel-Wahab [7] suggested using total factor productivity, output per worker, and output per work hour to measure the construction productivity performance at the industry level. Ayele and Fayek [8] developed a framework to measure the total productivity of construction projects, which consists of metrics at three levels: activity, project, and industry, and proposed a metric for measuring the total productivity of construction projects, which considers all resources used, including labor, material, capital, energy, construction project indirect cost, and owner cost. Huang et al. [9] stated that productivity can be measured at three levels: task, project, and industry, according to the nature of the construction process. Although different metrics have been proposed to measure construction productivity, there are few systematic studies investigating how those productivity metrics are used in practice. Furthermore, a report of Singapore indicated that the framework for measuring productivity is patchy [10]. As a result, this study is determined to bridge the knowledge gap by answering the following questions.
  • What metrics are used to measure construction productivity in Singapore?
  • Are those metrics frequently used in practice?
  • Will there be any significant differences in productivity measurement results when different metrics are used to measure the same project?
The research efforts described in the paper were carried out in the context of Singapore. Singapore is an island country featured in tiny size but developed economy. The population of the country is limited making the country has no choice but to seek for a higher productivity. To improve construction productivity in Singapore, the governmental department Building Construction Authority (BCA) has announced several initiatives in recent years. For example, BCA launched the 2nd Construction Productivity Roadmap in 2015 which encourages using advanced technologies such as Building Information Modelling (BIM), Prefabricated Prefinished Volumetric Construction (PPVC), and 3D printing to improve construction productivity [11,12]. In addition to the efforts made by the government, the academia has also carried out a series of research attempting to improve the construction productivity in Singapore. Ofori [13] investigated the barriers to achieving high construction productivity in Singapore. Ofori [14] examined the initiatives that would enable contractors in Singapore to improve the level of construction productivity. Lin et al. [15] proposed a framework for developing a productivity and safety monitoring system using Building Information Modelling. Hwang et al. [16] identified the critical factors affecting the productivity of green building construction projects in Singapore. Hwang et al. [17] identified and prioritized the critical management strategies that can help improve productivity in the construction industry of Singapore. Although great efforts are made both by the practice and academia, the productivity of Singapore’s construction industry is still low [18,19]. Hence, it is imperative to review and evaluate the practices conducted for improving construction productivity in Singapore. Moreover, according to the World Population Review [20]. Singapore is the second most productive country in Asia, which merely ranks behind Japan. A lot of countries, particularly for the emerging economies in Asia, are following the practice of Singapore for seeking productivity enhancement. For example, China chosen Singapore as its model and privileged partner [21]. Vietnam is learning from Singapore’s experiences in preparing for a productive workforce targeting the Industrial Revolution 4.0 [22]. India is investigating the model of Singapore trying to secure its tremendous growth and economic success [23]. Thus, research findings generated in Singapore would be useful, informative, and generalizable to the emerging economies worldwide. Therefore, Singapore is a good context to carry out the piece of the research.
Although some studies in the existing literature have used or developed different types of metrics to assess construction productivity, few of them investigated the implementation of these metrics. This study revealed the implementation of different productivity metrics in Singapore by checking the usage frequency, relative importance, and possible differences in the assessment results of various productivity metrics. Thus, this study can contribute to the current body of knowledge on productivity. Meanwhile, this study can help achieve further productivity growth in the industry by enhancing the government and the construction companies’ understandings of productivity metrics and updating the corresponding rules and policies. Therefore, this study is also beneficial for the industry. Moreover, this study can be replicated in other countries, which will allow government and construction industry managers to understand how local productivity metrics are implemented in real projects. Therefore, it is believed that this study can make contribution to the global construction community.

2. Background

2.1. Productivity

Generally, there are two types of productivity, namely single factor productivity, and multi-factor or total-factor productivity. Single factor productivity, which includes labor productivity and capital productivity, relates to just one input factor, while multi-factor or total-factor productivity takes into account all the inputs [7]. Labor productivity is a single-factor productivity often expressed as output per worker or output per hour worked [6,7,10]. The Construction Industry Institute (CII) [24] attempted to propose definitions of productivity for consistency, where productivity refers to “work-hours performed per units of work completed”, and “the ratio of planned productivity to actual productivity” refers to productivity index. Another single-factor productivity is capital productivity. Capital productivity can be defined as a percentage return on capital invested [25]. Li and Liu [26] stated that it can provide an overall capital utilization level of the construction industry. Multi-factor productivity considers the contribution of both labor and capital as inputs [10]. Total factor productivity (TFP) takes into account a combination of inputs with adjustments for technological progress [27]. Carson and Abbott [28] also stated that Data Envelopment Analysis (DEA) is a linear programming technique that computes the ratio of total inputs employed to total output produced for each unit to estimate organizational efficiency.

2.2. Construction Productivity in Singapore

Construction is a mainstay of Singapore’s economy. It accounts for 3–6% of Singapore’s gross domestic product (GDP) and takes up an estimated 12% of the total workforce in the country. According to Bowen [29], the vitality of one country’s economy is best indicated by its productivity performance. Therefore, improving the productivity level of the construction industry is important, critical, and imperative to the national development of Singapore. BCA has launched a series of initiatives in the past years to improve the construction productivity of Singapore. For example, in 2013 BCA initiated the Balcony Bonus Gross Floor Area Scheme which rewards developers who work closely with architects, engineers, and contractors towards higher construction productivity [30]. In addition, BCA operates a Certified Construction Productivity Professional Scheme which grants registered contractors additional bonus points for project bidding [31]. However, in the current construction industry of Singapore, there is a lack of systematic research on productivity metrics, making the industry companies unable to interpret their productivity level accurately, thereby leading to poor management and hindering the further improvement of the industry productivity.

2.3. Metrics Used to Measure Productivity in Construction Projects

The research team carried out a comprehensive literature review to identify the metrics that are used for construction productivity assessment. The identification of productivity metrics refers to the “PRISMA” guidelines [32]. Ten journal articles and two official reports that particularly addressed construction productivity metrics were identified. After examining the results of the literature review, the research team found that the prevailing productivity metrics can be grouped at four levels, namely, trade level, project level, company level, and industry level. Table 1 summarized the specific metrics used at four different levels.
At the trade level, productivity metrics involving measuring the output units for activities carried out at construction sites. Shehata and El-Gohary [6] mentioned that activity-oriented models are commonly adopted by contractors to measure productivity at construction sites. CII [24] suggested using work hours expended over quantity installed to measure activities’ productivity on site. BCA [36] published a guidebook that sets out the best practices to measure productivity for 12 key trades which are commonly found in most construction projects. The 12 key trades include formwork installation, concrete placement, reinforcement placing and fixing, drywall installation, timber door installation, painting, wall tiling, air-con ducting installation, suspended ceiling installation, floor tiling, electrical conduit installation, and water pipe installation. A study by Singapore Contractors Association Ltd. (SCAL) also stated that construction firms used trade-level labor productivity that can be expressed as either unit of output per dollar, per work-hour, or per man-day to monitor site activity [10]. Therefore, when measuring productivity at construction sites, it can be measured by the work hours expended over quantity installed.
At the project level, metrics such as square meters of built-up floor area per man-day or square meters per dollar are used as a composite measure of labor productivity [10]. In addition, “output per person-hour on key trades”, “total revenue per month”, “square meters per man-day”, “value-added per work” and “constructability scores”, are also metrics that can be used to assess project productivity [10]. Shehata and El-Gohary [6] also used square feet per dollar as a form to assess project productivity. However, due to the unique nature of the construction projects, measuring productivity at the project level poses limitations for benchmarking of data as construction items are non-identical [10]. Therefore, when measuring productivity at the project level, it is important not only to consider quantitative metrics but also to adapt qualitative metrics in the light of the actual situation of the project to obtain appropriate results.
At the company level, metrics such as “gross output per worker” and “square meters per man-day” are used to assess productivity [10]. In addition, value-added productivity is also used in some instances in the context of Singapore. For example, value-added per worker or value-added per hour worked are used and are estimated from progress payments or renovation bank loans and data from Housing Development Board and Urban Redevelopment Authority or production volume [10]. Subsequently, using price indices to deflate nominal value to get the real value-added. However, the challenges facing by the metric involves the difficulties in understanding the concept of value-added and in obtaining accurate figure due to project complexity [10]. Therefore, if productivity is to be measured within a certain period, metrics of company level can be used, but it will lack accuracy when considering long-term productivity.
At the industry level, productivity metrics include labor productivity, multifactor productivity, total factor productivity as well as estimations using cost or production function such as the growth accounting approach or data envelopment analysis. Issues with metrics at the industry level are the measurement to use for output or value-added, and what measurements should be used use for labor input. Additionally, problems in finding appropriate deflators for data adjustments happen due to affected output and inputs data by business cycles [10]. Despite productivity metrics at the industry level have many advantages in theory compared with other levels, the value of inputs and outputs cannot be measured only by quantitative metrics in practice. Therefore, errors due to uncertainties should also be considered.

3. Methods

This study adopted data collection methods, including literature review, pilot interviews, and questionnaire. The data analysis includes frequency and importance analysis, alignment analysis, and difference analysis.

3.1. Data Collection

3.1.1. Literature Review

Literature review is an effective way for researchers to learn some specific areas [37]. To identify the productivity metrics used by the current construction industry, this study conducted a literature review. The search scope of the literature expands vastly, covering the relevant books, journal articles, government reports, authoritative documents, and information on websites.

3.1.2. Pilot Interview

Pilot interview with experienced industry expert is widely used in the construction engineering and management research to verify whether the information retrieved from the literature review is reasonable [38,39]. Therefore, this study carried out pilot interviews with three experts from the construction industry of Singapore, to verify the productivity metrics identified in the literature review, checking their applicability to the context of the country. The list of productivity metrics retrieved from the literature review was then used in a focus group meeting with three experts to check the applicability of the metrics to the Singapore industry. All three experts have at least 14 years of experience in the construction industry and at least 8 years of experience in assessing construction productivity. These experts are experienced enough to provide views and opinions that are correct and reliable. The experts did not add any new metrics but modified the descriptions of some metrics and provided suggestions in the discussion section. Table 2 presents the profiles of the post-interviewees.

3.1.3. Development of Questionnaire

Questionnaire is a widely used method for obtaining the opinions of industry professionals in construction engineering and management research [40]. This study used questionnaires to gather industry professionals’ perceptions of productivity metrics. The questionnaire was developed based on the results of literature review and was composed of three sections. The first section recorded the respondent’s profile including the designation, years of experience in construction industry, and years of experience in assessing construction productivity. The second section asked the respondents to assess the identified metrics in terms of their usage in frequency and relative importance, using two different five-point rating scales, namely, 1 = never, 2 = rarely, 3 = sometimes, 4 = often, 5 = always, and 1 = not important at all, 2 = low important, 3 = moderate, 4 = important, 5 = extremely important. The third section of the questionnaire requested the respondents to assess the productivity of one project they have participated in, based on the identified metrics. During the assessment, another five-point rating scale, namely, 1 = very poor, 2 = poor, 3 = moderate, 4 = good, and 5 = very good, were used. A sample of the questionnaire has been attached as Appendix A.
The sampling frame of the questionnaire covered 4168 contractors and licensed builders registered under the BCA Directory [41]. Referring to a frequently used sample rate of 10% [42], 416 contractors were randomly selected from the BCA Directory as potential respondents of the questionnaire, which was distributed via email, phone calls, and in person. A total of 53 responses were received, yielding a low response rate of 12.7%, but for the survey research of Singapore’s construction industry, this response rate is acceptable [43,44]. Such a low response rate is understandable, because construction industry is always full of stress and challenges, and that construction professionals within a pressured and dynamic work environment are unlikely to respond in the same way as members of the public receiving questionnaires in their own homes or others who may work in more stable work environments (e.g., office workers in large organizations) [45]. The data set was checked for outliers, and the result showed that the data of the 53 responses were all valid. The respondents had different types of designations, such as contractors, consultants, owners, and government agency personnel. Among the respondents, approximately 90% had at least five years of working experience in the construction industry and approximately 50% had at least five years of experience in assessing construction productivity. These proportions indicated that the questionnaire respondents were experienced in the field and that data collected were reliable. Table 3 presents the profiles of the survey respondents.

3.2. Data Analysis Methods

Statistical tests were conducted to analyze the data collected by the questionnaire. Although the sample size of this study (i.e., 53) was not large, statistical analysis could still be performed because the central limit theorem holds true as long as the sample size is no less than 30 [46,47]. Two types of tests are widely used for statistical analysis, parametric statistical tests and non-parametric statistical tests [48]. For parametric statistical tests, they have a specific requirement which is data to be analyzed must fall in normal distribution, while non-parametric statistical tests have no such constraint [49]. Based on the experience of general questionnaire survey research in the construction industry, this study uses non-parametric statistical tests to analyze the data. All tests were conducted with the aid of SPSS Statistics 26.0.

3.2.1. Identification of the Most Frequently Used and Most Important Metrics

One sample Wilcoxon signed-rank test was used for the identification of the metrics that are most frequently used and most important. One sample Wilcoxon signed-rank test is a non-parametric statistical method, which checks whether the median of the sample data is different from a test value [50,51]. According to [52], the null hypothesis of the test is that the median of the sample data is statistically same as the test value. If the p-value generated by the test is greater than 0.05, the null hypothesis is supported. By contrast, a p-value less than 0.05 indicates the median of the sample data is statistically different from the test value. For this study, “4” was selected as the test value, which means the metric is frequently used and important according to the five-point Likert scale. Thus, by conducting the One sample Wilcoxon signed-rank test using the test value of 4, the metrics that are most frequently used and most important could be revealed. One sample Wilcoxon signed-rank test used the data from the second part of the questionnaire to analyze the frequency and importance. In addition, the mean generated for each productivity metric is evaluated as well, with top five productivity metrics for both level of frequency and importance identified for discussions.

3.2.2. Investigation of Stakeholders’ Alignment on the Various Metrics

As the respondents of the questionnaire are from different institutions such as contractors, consultants, owners, and government agencies, it is necessary to carry out an inter-group comparison checking whether the respondents opine differently in sense of their institutions. Kruskal–Wallis test is a rank-based non-parametric statistical test method checking the potential differences among two or more different groups [53,54,55]. This study used the Kruskal–Wallis test rather than the one-way ANOVA test because the studied groups in Table 3 were of non-equal sample size and almost all metrics have their Levene’s values ranging from 0.013 to 4.967 for frequency, from 0.057 to 6.074 for importance, and from 0.019 to 3.524 for performance (significant at p < 0.05) [56,57]. The null hypothesis is that there are no differences in the median between groups. A significance level (α) of 0.05 is used to assess the hypothesis. A p-value lesser than 0.05 rejects the null hypothesis and concludes that there is a difference in the median between the groups. On the other hand, if the p-value is more than 0.05, the null hypothesis is accepted indicating a consensus in the median between the groups. Kruskal–Wallis test used the data from the second part and third part of the questionnaire to analyze the scoring of frequency, importance of metrics and productivity performance by respondents from different groups.
To further evaluate the results of differences between two groups (e.g., between contractors and consultants, contractors and owners), Mann–Whitney U test was conducted, it is also a non-parametric test [58]. The Kruskal–Wallis test conducted in the previous step only identified a difference between subgroups for the productivity metrics and does not tell which specific groups are significantly different. Hence, a more extensive analysis to understand which specific groups were statistically significant different from each other. Use the Mann–Whitney U test for post hoc analysis, Bonferroni adjustment should be considered to adjust the significance level to control for Type 1 errors [59]. The null hypothesis is that there are no differences between two groups. A p-value lesser than adjusted significance level rejects the null hypothesis and concludes that there is a difference between two groups. Mann–Whitney U test used the same data as Kruskal–Wallis test for analysis.

3.2.3. Investigation of Differences on Assessments at Different Levels

To check whether there are significant differences in results when different metrics are used to assess the same project, the Friedman test was conducted. The Friedman test is suitable for two-way rank analysis of variance in the randomized block design [60]. It is similar to the Kruskal–Wallis test, but takes into account the influence of different groups [61]. In this step, according to the results of the Kruskal–Wallis test, the data set was divided into different blocks to minimize the difference between the groups. This step aims to reduce the error caused by the influence of the blocks to effectively distinguish whether there is a significant difference in results when different metrics are used to assess the same project. The null hypothesis is that there is no difference between the four levels of metrics when assessing the same project. A p-value lesser than 0.05 rejects the null hypothesis and concludes that there is a significant difference between the four levels of metrics. The Friedman test uses the data in the third part of the questionnaire. The test item is the rank of productivity performance. To determine which level has the highest and lowest productivity performance, the average performance score of each level (i.e., industry, company, project, and trade) was calculated for every group of respondents (i.e., designation or years of experience in industry or years of experience in assessing productivity), and the ranking of the scores of the four levels for different groups were presented, then SPSS was used for significant difference analysis.

4. Results and Discussion

4.1. Statistical Test Results of Productivity Metrics

This study mainly uses four non-parametric statistical test methods to analyze the data, one sample Wilcoxon signed-rank test was adopted to check whether the identified productivity metrics are frequently used in practice, as well as whether they are of importance to the practice; Kruskal–Wallis test was used to carry out inter-group comparison; Mann–Whitney U test was used for post hoc analysis between two groups; and Friedman test was suitable for checking the significant difference in results achieved by different metrics upon one project. Table 4 presents respondents’ assessments of productivity metrics (usage in frequency and relative importance) as well as the relevant results of statistical analyses.

4.1.1. The Most Frequently Used and Most Important Metrics

According to the one sample Wilcoxon-signed rank test results in Table 4, assessments of most productivity metrics were statistically lower than the test value 4, except for P10, P15, P16, P19, and P20. Such results indicate that, although many metrics are proposed by the authorities to assess productivity, only several of them are frequently used and considered important by the practice.

4.1.2. Stakeholders’ Alignment on the Various Metrics

As for inter-group comparison based on the second part of the questionnaire, the Kruskal–Wallis test results show that all respondents shared unanimous opinions on frequency and importance regardless of their years of experience in the construction industry and in assessing construction productivity, but there are differences between designation groups. To determine which two designation groups have a statistically significant difference, the Mann–Whitney U test was conducted for metrics P7, P19, and P20 in the frequency section, and P7, P10, P19, and P20 in the importance section. According to Bonferroni adjustment, adjusted significance level α′ = α/m = 0.05/6 = 0.00833 [62]. Results indicated that there is a difference between the designations with government agencies, as presented in Table 5. The values in bold show a statistically significant difference.
As for inter-group comparison based on the third part of the questionnaire, Table 6 lists the differences in productivity performance among different groups of respondents. The Kruskal–Wallis test results show that although respondents of different designations and years of experience in the construction industry shared unanimous opinions on productivity performance, according to the different years of experience in assessing construction productivity, the respondents’ perspective on metrics are inconsistent, especially the trade level (P21–P33). To determine which two specific groups are statistically different, the Mann–Whitney U test was conducted as the results presented in Table 7. Adjusted significance level α′ = α/m = 0.05/3 = 0.0167. Results observed a difference in the group of more than 10 years of experience in assessing construction productivity. Respondents in subgroup “>10 years” indicated a perception of trade level productivity metrics having a better productivity performance compared to the two other groups.

4.1.3. Differences on Assessments at Different Levels

The results were affected by the subjective judgments of the respondents, thus it may fail to accurately reflect the actual situation. It is suitable to use the Friedman test method for comparison. Table 8 shows the average scores and corresponding ranks of productivity metrics performance, based on different levels as well as the different designations of respondents. The result of Friedman test reported p = 0.017, which was less than 0.05. The null hypothesis was rejected and concludes that there are significant differences when using different levels of productivity metrics to assess the same projects.

4.2. Discussion

Recalling the three research questions raised in the introduction section, first, 33 prevailing metrics for construction productivity measurement in Singapore were obtained through literature review and pilot interview. Then based on the second part of the questionnaire and statistical analysis, explored the usage in frequency and relative importance of different productivity metrics, and determined the top five productivity metrics in usage frequency and importance. Stakeholders’ alignment on the various metrics reflects the main reasons for the differences. Finally, based on the third part of the questionnaire and statistical analysis, reported that there are significant differences when using different levels of productivity metrics to assess the same projects.

4.2.1. Top Five Productivity Metrics in Usage Frequency and Importance

In terms of usage frequency, the one sample Wilcoxon signed-rank test in Table 4 showed that the p-values of P10, P15, P16, P19, and P20 are greater than 0.05, suggesting respondents’ assessments of these metrics are statistically same as the test value of 4. In addition, as presented in Table 4, none of the identified metrics received a mean value greater than 4; according to the rating scale adopted by the questionnaire, it means that P10, P15, P16, P19, and P20 are the only productivity metrics that are frequently used in productivity assessment. In terms of relative importance, as shown in Table 4, the p-values of P15, P16, P19, and P20 generated by one sample Wilcoxon signed-rank test are greater than 0.05, indicating respondents’ assessments of these four metrics are statistically equal to the test value of 4. Furthermore, none of the identified metrics received a mean value higher than 4 except P19 and P 20; according to the rating scale adopted by the questionnaire, it means that P15, P16, P19, and P20 are the only productivity metrics that are considered important by the practice. Due to the word limit, only P10, P15, P16, P19, and P20 are discussed in this paper.
As shown in Table 4, P19 “Constructability Score” and P20 “Buildable Design Score” received the top two highest assessments both in usage frequency and relative importance. As the results of the Kruskal–Wallis test and the Mann–Whitney U test, the government pays more attention to the Constructability Score and the Buildable Design Scores. The Constructability Score in Singapore is an index that measures contractors regarding their adoption level of labor-efficient construction methods and construction processes, such as system formwork and climbable scaffolding [63]. The score can reflect the productivity levels of contractors and it has become a mandatory requirement of BCA in tender evaluation to improve construction productivity. The Buildable Design Score is an index measuring the potential impact of a building design on labor usage. It facilitates the adoption of less labor-intensive construction methods and promotes greater use of prefabricated, modular, and standardized building components to improve site productivity [63]. It has been required by the government that any projects with a gross floor area of 2000 m2 and above must comply with a minimum Buildable Design Score [63]. Additionally, the expert opined that these two scores are important to benchmark contractors’ involvement on values for the project, as well as the client’s involvement and consultant’s value-added performance. Therefore, ignoring the productivity increase brought about by new construction technologies may lead to an underestimation of actual productivity, at the same time, appropriate productivity metrics should be identified according to the state of the art of construction in a region.
P16 “square meter of built-up floor area per man-day” ranked third both in usage frequency and relative importance. This metric reflects how productive the work conducted by one worker is. This metric is important because it is crucial to know how much work is completed on site so as to decide manpower requirements or if any adjustments are required to be made. A study conducted by SCAL [10] also revealed that square meter per man-day is one of the leading methods of assessing productivity by construction companies in Singapore. The survey respondents are also of the perception that “square meter of built-up floor area per man-day” is frequently adopted in the local construction industry. The metric provides an easy yardstick for the measurement of physical site productivity.
P15 “square meter per dollar” received the fourth highest assessment both in usage frequency and relative importance. The metric checks how much work is done on account of the amount of money spent. It investigates profitability which is governed by how productive per area of works. The expert commented that this metric can be used as a benchmark on the cost-effectiveness of a project, and it has been widely used by the construction industry of Singapore. The importance of financial consideration is underline in productivity assessment in the study by SCAL [10], the cost implications in this metric measurement are imperative to the productivity assessment. Especially in international projects, “square meter per dollar” is used as an important metric to measure project cost and productivity assessment [64].
P10 “output per worker” at a company level (P10) ranked fifth in usage frequency and relative importance. The metric was identified as a common measure of productivity by numerous studies, associating labor productivity as outputs to labor inputs [7,25]. It aids in measuring the competency of workers, which is a good yardstick to measure the productivity of the workers. Additionally, the metric allows review of workers’ involvement and cost-effectiveness of workers’ output so that changes can be made for future implementations. On the other hand, workers are directly engaged by contractors, which is good for contractors to keep track of productivity data, as opined by experts. Thereby “output per worker” will be more realistic for implementation as it is based on practicability, especially for projects that require many workers.

4.2.2. Differences on Assessments at Different Levels

As shown in Table 8, there are differences in productivity measurement results when different metrics are used to measure the same project. Therefore, it cannot consider only one certain level when assessing productivity. According to the results of the Kruskal–Wallis test and the Mann–Whitney U test, the respondents with more than 10 years of experience in assessing construction productivity indicated a perception of trade level having a higher productivity performance. The reason may be that metrics of trade level are the basis for productivity measurement, they are relatively easy and straightforward for use [10]. Then, the Singapore government concluded almost all trade level productivity metrics in the builders’ guide of BCA a long time ago, thus, when the project is planned or implemented, metrics may have been incorporated into the schedule to respond to the need for high productivity. Finally, trade level productivity metrics are related to the individual performance of each trade, and workers will meet higher index requirements to obtain more rewards. Therefore, the trade level is not only easy to measure, but more importantly, rules based on metrics are also easy to implement. So, it is suitable for measuring the productivity of on site, and it also facilitates the government and managers to develop effective incentive policies.
Although the productivity performance evaluated by trade level productivity metrics is higher, stakeholders prefer to consider project level and company level productivity metrics in terms of frequency and importance. By contrast, productivity metrics at the project, company, and industry levels involves are more complex as they involve all the trades and require more details to be taken into consideration. Industry level productivity metrics are persuasive in theory but have initial investment and derived values that are difficult to measure in practice. It is also further supported by experts that trade level is the base of the productivity measurement, as project level is built upon the multiple trades, and company level is built upon projects and the industry level is up to the results of different companies. Consequently, it is important to measure productivity from a holistic view and select appropriate metrics or develop new metrics to measure productivity according to the actual situation of project, such as the character of project, site conditions, human resources, and local regime.

4.3. The Implications of Study

This study has practical implications because it revealed the implementation status of the different productivity metrics in the real world, provides evidence for finding effective management strategies which could help the authorities and the industry update their rules and policies accordingly. The research results also suggest that the authorities and industry practitioners adjust the productivity assessment system in the light of the actual situation, instead of selecting the only commonly used productivity metrics. A holistic assessment of productivity covering different aspects needs to be carried out if they want to gain objective and reliable information regarding the status quo of the productivity in their construction industry.
Apart from being beneficial to the practice, this study contributes to the current body of knowledge of productivity research. Although various types of metrics are used to assess productivity currently, limited research was carried out to investigate their usage in practice. This is the first study that presents a methodological approach to investigates the various productivity metrics used in the construction industry, by checking its usage frequency, relative importance, and possible differences in assessment results. The results indicate that the benchmarking of the productivity metrics system needs to be improved and exploring productivity metrics more friendly for assessment will be a research direction that can be considered for future research. Although this research is based on Singapore, other countries, particularly those emerging economies in Asia could use the methodological approach presented in this study to examine the productivity metrics used in their industry and carry out modification if needed.

5. Conclusions and Recommendations

This study investigated the different metrics that were used to measure productivity in the construction industry of Singapore. It first conducted the literature review of the productivity metrics and categorized the metrics at four different levels, namely trade, project, company, and industry. Subsequently, the frequency and importance levels of various productivity metrics were assessed. Results showed that the top five productivity metrics used in the construction of Singapore were “constructability score”, “buildable design score”, “square meter of built-up floor area per man-day”, “square meter per dollar”, and “output per worker.” Results also showed that differences existed when metrics at different levels were used to conduct the same measurement, and that results generated by the metrics at the trade level are relatively higher than those from the project, company, and industry levels. The findings from this study can help government authorities review, evaluate, and modify the productivity metrics used by the practice, which would further help achieve the sustainable development of the industry.
Although the objectives of the study were achieved, there are limitations. First, this study collected perception-based data from experts in the industry, which may cause the issue of subjectivity. Second, the sample size of the questionnaire is relatively small and thus, caution should be warranted when the results are interpreted. Lastly, this study was conducted in the context of Singapore and the results may have applicability issue when applying to other countries.
Future studies could develop productivity assessment benchmarking systems and integrates the overview of project to implement productivity measurements. In addition, how to measure productivity accurately and efficiently in an era of information technology development will be an important task for industry research and policy development.

Author Contributions

Conceptualization, M.S. and B.-G.H.; methodology, M.S., J.-E.C. and Y.-S.L.; validation, M.S. and Y.-S.L.; formal analysis, Y.-S.L.; investigation, J.-E.C.; resources, B.-G.H.; data curation, J.-E.C.; writing—original draft preparation, Y.-S.L. and J.-E.C.; writing—review and editing, M.S. and B.-G.H.; visualization, Y.-S.L.; supervision, M.S. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Some or all of the data that support the findings of this study are available from the corresponding author on reasonable request. Additional data that support the findings of this study, including the survey template and raw survey results, are available from the corresponding author on reasonable request.

Acknowledgments

Sincere thanks go to the industry experts who have participated into the survey carried out in this study.

Conflicts of Interest

The authors declare no conflict of interest.

Appendix A. Main Survey Questionnaires

Appendix A.1. Respondents’ Profile

Please indicate your designation by ticking ✓ below.
[ ] Consultant [ ] Contractor [ ] Owner [ ] Government Agencies [ ] Others (please specify):
Please indicate your years of experience in the construction industry:
Please indicate your years of experience in assessing productivity in your organization:
Please indicate the years of experience of your company/organization in the construction industry:
Please indicate the years of experience in assessing productivity in your organization:

Appendix A.2. Frequency and Importance of Construction Productivity Metrics

This section assesses the productivity metrics identified from literature reviews. Please tick ✓ the productivity metrics that your company/organization have adopted to measure productivity (You may tick more than one).
Following which, the general perception of the frequency and importance is assessed. Please rate the frequency and importance of ALL metrics with a scale of 1 to 5: (Kindly mark an X in the boxes below.)
Frequency: 1- Never, 2- Rarely, 3- Sometimes, 4- Often, 5- Always
Importance: 1- Not important at all, 2- Low important, 3- Moderate, 4- Important, 5- Extremely important
For your information:
The following metrics are extracted from literature reviews:
Single factor productivity includes output per one input, or in some instances value-added form.
Multi-factor productivity is defined as output per the contributions of both labor and capital as inputs.
Total-factor productivity takes into account combination of inputs (capital, labor and materials) with adjustment for technological progress (shift factor).
Growth Accounting Approach is estimations of cost functions, by estimating productivity over time by estimating production function.
Data Envelopment Analysis is a nonparametric method to determine efficiency of decision making unit (DMU) by the projection of input and output variables in geometric figures.
Table A1. Frequency and Importance of Construction Productivity Metrics.
Table A1. Frequency and Importance of Construction Productivity Metrics.
LevelsMetricsPlease Tick ✓ if the Metric Is UsedFrequency (Answer for ALL Metrics)Importance (Answer for ALL Metrics)
1- Never2- Rarely3- Sometimes4- Often5- Always1- Not Important at All2- Low Important3- Moderate4- Important5- Extremely Important
IndustryTotal Factor Productivity
Multi-Factor Productivity
Output per worker
Output per work hour
Value-added per worker
Value-added per hour worked
Square metre per man day
Growth Accounting Approach
Data Envelopment Analysis
CompanyOutput per worker
Output per work hour
Value-added per worker
Value-added per hour worked
Capital Productivity
ProjectSquare metre per dollar
Square metre of built-up floor area per man-day
Value-added per worker
Output per person-hour on key trades
Constructability Score
Buildable Design Score
TradeWork-Hours expended/Quantity Installed
Formwork Area per manhour
Amount of rebar/prefab mesh per manhour
Volume of concrete per manhour
Area of Drywall per manhour
Painted Area per manhour
Number of doors installed per manhour
Wall tiled area per manhour
Floor tiled area per manhour
Suspended ceiling per manhour
Length of ducting per manhour
Length of electrical conduit per manhour
Length of water pipe per manhour

Appendix A.3. Productivity Performance of Projects by Metrics

This section assesses the productivity performance of projects by metrics. You may encounter different outcomes when using different productivity metrics to measure the same project. Based on your experience in the past three to five years projects, please indicate your perception of the productivity performance under different productivity metrics by marking an X in the boxes below, using a scale of 1 to 5 for ALL the metrics (if the measured productivity outcome is good or poor):
Performance: 1- Very Poor, 2- Poor, 3- Moderate, 4- Good, 5- Very Good
Table A2. Productivity Performance of Projects by Metrics.
Table A2. Productivity Performance of Projects by Metrics.
LevelsMetricsPerformance by Metrics
1-
Very Poor
2-
Poor
3-
Moderate
4-
Good
5-
Very Good
IndustryTotal Factor Productivity
Multi-Factor Productivity
Output per worker
Output per work hour
Value-added per worker
Value-added per hour worked
Square metre per man day
Growth Accounting Approach
Data Envelopment Analysis
CompanyOutput per worker
Output per work hour
Value-added per worker
Value-added per hour worked
Capital Productivity
ProjectSquare metre per dollar
Square metre of built-up floor area per man-day
Value-added per worker
Output per person-hour on key trades
Constructability Score
Buildable Design Score
TradeWork-Hours expended/Quantity Installed
Formwork Area per manhour
Amount of rebar/prefab mesh per manhour
Volume of concrete per manhour
Area of Drywall per manhour
Painted Area per manhour
Number of doors installed per manhour
Wall tiled area per manhour
Floor tiled area per manhour
Suspended ceiling per manhour
Length of ducting per manhour
Length of electrical conduit per manhour
Length of water pipe per manhour

References

  1. Hasan, A.; Baroudi, B.; Elmualim, A.; Rameezdeen, R. Factors affecting construction productivity: A 30 year systematic review. Eng. Constr. Archit. Manag. 2018, 25, 916–937. [Google Scholar] [CrossRef]
  2. Caldas, C.H.; Kim, J.Y.; Haas, C.T.; Goodrum, P.M.; Zhang, D. Method to Assess the Level of Implementation of Productivity Practices on Industrial Projects. J. Constr. Eng. Manag. 2015, 141, 9. [Google Scholar] [CrossRef]
  3. Durdyev, S.; Ismail, S.; Kandymov, N. Structural Equation Model of the Factors Affecting Construction Labor Productivity. J. Constr. Eng. Manag. 2018, 144, 11. [Google Scholar] [CrossRef]
  4. Ghodrati, N.; Wing Yiu, T.; Wilkinson, S.; Shahbazpour, M. Role of Management Strategies in Improving Labor Productivity in General Construction Projects in New Zealand: Managerial Perspective. J. Manag. Eng. 2018, 34. [Google Scholar] [CrossRef]
  5. Tan, Y.T.; Shuai, C.Y.; Shen, L.Y.; Hou, L.; Zhang, G.M. A study of sustainable practices in the sustainability leadership of international contractors. Sustain. Dev. 2020, 28, 697–710. [Google Scholar] [CrossRef]
  6. Shehata, M.E.; El-Gohary, K.M. Towards improving construction labor productivity and projects’ performance. Alex. Eng. J. 2011, 50, 321–330. [Google Scholar] [CrossRef] [Green Version]
  7. Vogl, B.; Abdel-Wahab, M. Measuring the construction industry’s productivity performance: Critique of international productivity comparisons at industry level. J. Constr. Eng. Manag. 2015, 141. [Google Scholar] [CrossRef]
  8. Ayele, S.; Fayek, A.R. A framework for total productivity measurement of industrial construction projects. Can. J. Civ. Eng. 2019, 46, 195–206. [Google Scholar] [CrossRef]
  9. Huang, A.L.; Chapman, R.E.; Butry, D.T. Metrics and Tools for Measuring Construction Productivity: Technical and Empirical Considerations, Special Publication 1101; U.S. Department of Commerce National Institute of Standards and Technology: Washington, DC, USA, 2009. Available online: https://nvlpubs.nist.gov/nistpubs/Legacy/SP/nistspecialpublication1101.pdf (accessed on 7 July 2021).
  10. SCAL. Construction Productivity in Singapore: Effective Measurement to Facilitate Improvement; The Singapore Contractors Association Ltd.: Singapore, 2017. [Google Scholar]
  11. Building Construction Authority (BCA). The Second Construction Productivity Roadmap 14. 2015. Available online: https://www.bca.gov.sg/emailsender/BuildSmart-062015/microsite/others/bca-newsletter.pdf. (accessed on 17 May 2021).
  12. Liu, S.Y.; Qian, S.Z. Towards sustainability-oriented decision making: Model development and its validation via a comparative case study on building construction methods. Sustain. Dev. 2019, 27, 860–872. [Google Scholar] [CrossRef]
  13. Ofori, G.; Zhang, Z.; Ling, F.Y.Y. Key barriers to increase construction productivity: The Singapore case. Int. J. Constr. Manag. 2020, 1–12. [Google Scholar] [CrossRef]
  14. Ofori, G.; Zhang, Z.; Ling, F.Y.Y. Initiatives that enable Singapore contractors to improve construction productivity. Built Environ. Proj. Asset Manag. 2021. [Google Scholar] [CrossRef]
  15. Teo Ai Lin, E.; Ofori, G.; Tjandra, I.; Kim, H. Framework for productivity and safety enhancement system using BIM in Singapore. Eng. Constr. Archit. Manag. 2017, 24, 1350–1371. [Google Scholar] [CrossRef]
  16. Hwang, B.-G.; Zhu, L.; Ming, J.T.T. Factors Affecting Productivity in Green Building Construction Projects: The Case of Singapore. J. Manag. Eng. 2017, 33. [Google Scholar] [CrossRef]
  17. Hwang, B.-G.; Li, Y.-S.; Shan, M.; Chua, J.-E. Prioritizing Critical Management Strategies to Improving Construction Productivity: Empirical Research in Singapore. Sustainability 2020, 12, 9349. [Google Scholar] [CrossRef]
  18. Krishnankutty, P.; Hwang, B.G.; Caldas, C.H.; Muralidharan, S.; De Oliveira, D.P. Assessing the Implementation of Best Productivity Practices in Maintenance Activities, Shutdowns, and Turnarounds of Petrochemical Plants. Sustainability 2019, 11, 1239. [Google Scholar] [CrossRef] [Green Version]
  19. Shang, G.; Pheng, L.S.; Hui, W.J. Drivers and barriers for multiskilling workers in the Singapore construction industry. Int. J. Constr. Manag. 2020, 20, 289–304. [Google Scholar] [CrossRef]
  20. World Population Review. Most Productive Countries 2021. 2021. Available online: https://worldpopulationreview.com/country-rankings/most-productive-countries. (accessed on 26 October 2021).
  21. Curien, R. Singapore, a model for (sustainable?) urban development in China. An overview of 20 years of Sino-Singaporean cooperation. China Perspect. 2017, 2017, 25–35. [Google Scholar] [CrossRef] [Green Version]
  22. Quyen, N.T.H. An analysis of the Singaporean preparation for the future workforce and recommendations for Vietnam. VNU J. Foreign Stud. 2019, 35. [Google Scholar] [CrossRef]
  23. Management, Enterprise and Benchmarking in the 21st Century. Small Economy but Big Lessons: What India and Hungary Can Learn from Outward Looking Model of Singapore? Available online: http://kgk.uni-obuda.hu/sites/default/files/18_Kumari_Bharti.pdf (accessed on 12 May 2021).
  24. Construction Industry Institute (CII). Craft Productivity Program Phase I. In Research Summary 252-1; The University of Texas at Austin: Austin, TX, USA, 2009. [Google Scholar]
  25. Lowe, J.G. The measurement of productivity in the construction industry. Constr. Manag. Econ. 1987, 5, 101–113. [Google Scholar] [CrossRef]
  26. Li, Y.; Liu, C. Construction capital productivity measurement using a data envelopment analysis. Int. J. Constr. Manag. 2011, 11, 49–61. [Google Scholar] [CrossRef]
  27. Crawford, P.; Vogl, B. Measuring productivity in the construction industry. Build. Res. Informat. 2006, 34, 208–219. [Google Scholar] [CrossRef]
  28. Carson, C.; Abbott, M. A review of productivity analysis of the New Zealand construction industry. Australas. J. Constr. Econ. Build. 2012, 12, 1–15. [Google Scholar] [CrossRef] [Green Version]
  29. Bowen, W. The prospects for productivity in Rukeyser. In Working Smarter, 2nd ed.; Ruckeyser, W.S., Fortune Magazine Editors, Eds.; Penguin: New York, NY, USA, 1984; pp. 1–18. [Google Scholar]
  30. Building Construction Authority (BCA). Balcony Bonus GFA Scheme. 2020. Available online: https://www1.bca.gov.sg/buildsg/productivity/other-incentives-scheme/balcony-bonus-gfa-scheme. (accessed on 17 May 2021).
  31. Building Construction Authority (BCA). Qualification for CCPP. 2019. Available online: https://www1.bca.gov.sg/buildsg/productivity/bca-certified-construction-productivity-professional-scheme/qualification-for-ccpp. (accessed on 9 June 2021).
  32. Page, M.J.; Mckenzie, J.E.; Bossuyt, P.M.; Boutron, I.; Hoffmann, T.C.; Mulrow, C.D.; Shamseer, L.; Tetzlaff, J.M.; Akl, E.A.; Brennan, S.E.; et al. The PRISMA 2020 statement: An updated guideline for reporting systematic reviews. BMJ 2021, 372, n71. [Google Scholar] [CrossRef] [PubMed]
  33. OECD. Measuring Productivity. Organisation for Economic Co-Operation and Development; OECD: Paris, France, 2001; Available online: http://www.oecd.org/sdd/productivity-stats/2352458.pdf. (accessed on 12 May 2021).
  34. Dozzi, S.P.; Abourizk, S.M. Productivity in Construction; Institute for Research in Construction, National Research Council: Ottawa, ON, Canada, 1993. [Google Scholar]
  35. De Valence, G.; Abbott, M. A review of the theory and measurement techniques of productivity in the construction industry. In Measuring Construction: Prices, Output and Productivity; Routledge: London, UK, 2015; pp. 205–221. [Google Scholar]
  36. Building Construction Authority (BCA). Builders’ Guide on Measuring Productivity—A Guide to Help Builders Measure Productivity of Various Trades. 2012. Available online: https://www.bca.gov.sg/Productivity/others/builders_guide_productivity.pdf (accessed on 6 June 2021).
  37. Zhao, X.B. A scientometric review of global BIM research: Analysis and visualization. Autom. Constr. 2017, 80, 37–47. [Google Scholar] [CrossRef]
  38. Hwang, B.-G.; Shan, M.; Phua, H.; Chi, S. An Exploratory Analysis of Risks in Green Residential Building Construction Projects: The Case of Singapore. Sustainability 2017, 9, 1116. [Google Scholar] [CrossRef] [Green Version]
  39. Li, A.S.; Ling, F.Y.Y.; Low, S.P.; Ofori, G. Strategies for Foreign Construction-Related Consultancy Firms to Improve Performance in China. J. Manag. Eng. 2016, 32, 6. [Google Scholar] [CrossRef]
  40. Hwang, B.-G.; Zhao, X.; Yang, K.W. Effect of BIM on Rework in Construction Projects in Singapore: Status Quo, Magnitude, Impact, and Strategies. J. Constr. Eng. Manag. 2019, 145. [Google Scholar] [CrossRef]
  41. Building Construction Authority (BCA). BCA Directory of Registered Contractors & Licensed Builders. 2020. Available online: https://www.bca.gov.sg/BCADirectory/ (accessed on 14 April 2020).
  42. Sommer, A.; Steland, A. Multistage acceptance sampling under nonparametric dependent sampling designs. J. Stat. Plan Inference 2019, 199, 89–113. [Google Scholar] [CrossRef]
  43. Hartono, B.; Sulistyo, S.R.; Chai, K.H.; Indarti, N. Knowledge Management Maturity and Performance in a Project Environment: Moderating Roles of Firm Size and Project Complexity. J. Manag. Eng. 2019, 35. [Google Scholar] [CrossRef]
  44. Liao, L.; Teo, E.a.L. Managing critical drivers for building information modelling implementation in the Singapore construction industry: An organizational change perspective. Int. J. Constr. Manag. 2019, 19, 240–256. [Google Scholar] [CrossRef]
  45. Root, D.; Blismas, N.G. Increasing questionnaire responses from industry: Practices surrounding the use of postal questionnaires. In Proceedings of the 19th Annual ARCOM Conference, Brighton, UK, 3–5 September 2003; Greenwood, D.J., Ed.; Association of Researchers in Construction Management: Reading, UK, 2003; Volume 2, pp. 623–631. [Google Scholar]
  46. Ott, R.L.; Longnecker, M.T. An Introduction to Statistical Methods and Data Analysis, 7th ed.; Cengage Learning: Boston, MA, USA, 2015. [Google Scholar]
  47. Zhao, X.; Singhaputtangkul, N. Effects of firm characteristics on enterprise risk management: Case study of Chinese construction firms operating in Singapore. J. Manag. Eng. 2016, 32. [Google Scholar] [CrossRef]
  48. Kim, T.K. T test as a parametric statistic. Korean J. Anesthesiol. 2015, 68, 540–546. [Google Scholar] [CrossRef] [Green Version]
  49. Minchin Jr, R.E.; Corona, F.; Lucas, E.D.; Zhang, Y.; Pan, J.; Walters, R.C. Chinese Organizations’ Actions, Attitudes, and Motivations When Faced with Counterfeit Items in Their Construction Supply Chains. J. Leg. Aff. Disput. Resolut. Eng. Constr. 2017, 9. [Google Scholar] [CrossRef]
  50. Conover, W.J. Practical Nonparametric Statistics, 3rd ed.; John Wiley & Sons, Inc.: Hoboken, NJ, USA, 1999; pp. 350–357. [Google Scholar]
  51. Thas, O.; Rayner, J.; Best, D. Tests for symmetry based on the one-sample Wilcoxon signed rank statistic. Commun. Stat. Simul. Comput. 2005, 34, 957–973. [Google Scholar] [CrossRef]
  52. Taheri, S.; Hesamian, G. A generalization of the Wilcoxon signed-rank test and its applications. Stat. Pap. 2013, 54, 457–470. [Google Scholar] [CrossRef]
  53. Kruskal, W.H.; Wallis, W.A. Use of Ranks in One-Criterion Variance Analysis. J. Am. Stat. Assoc. 1952, 47, 583–621. [Google Scholar] [CrossRef]
  54. Rajendran, S.; Gambatese, J.A.; Behm, M.G. Impact of green building design and construction on worker safety and health. J. Constr. Eng. Manag. 2009, 135, 1058–1066. [Google Scholar] [CrossRef]
  55. Tixier, A.J.-P.; Hallowell, M.R.; Albert, A.; Van Boven, L.; Kleiner, B.M. Psychological antecedents of risk-taking behavior in construction. J. Constr. Eng. Manag. 2014, 140. [Google Scholar] [CrossRef] [Green Version]
  56. Howell, D.C. Statistical Methods for Psychology; Cengage Learning: Boston, MA, USA, 2012; pp. 324–325. [Google Scholar]
  57. Levene, H. Robust tests for equality of variances. Contrib. Probab. Statistics. Essays Honor. Harold Hotell. 1960, 2, 278–292. [Google Scholar]
  58. Mann, H.B.; Whitney, D.R. On a Test of Whether one of Two Random Variables is Stochastically Larger than the Other. Ann Stat. 1947, 18, 50–60. [Google Scholar] [CrossRef]
  59. Cohen, J. Statistical Power Analysis for the Behavioral Sciences; Routledge Academic: New York, NY, USA, 1988. [Google Scholar]
  60. Friedman, M. The Use of Ranks to Avoid the Assumption of Normality Implicit in the Analysis of Variance. J. Am. Stat. Assoc. 1937, 32, 675–701. [Google Scholar] [CrossRef]
  61. Sheldon, M.R.; Fillyaw, M.J.; Thompson, W.D. The use and interpretation of the Friedman test in the analysis of ordinal-scale data in repeated measures designs. Physiother. Res. Int. 1996, 1, 221–228. [Google Scholar] [CrossRef] [PubMed]
  62. Chen, S.-Y.; Feng, Z.; Yi, X. A general introduction to adjustment for multiple comparisons. J. Thorac. Dis. 2017, 9, 1725–1729. [Google Scholar] [CrossRef] [PubMed] [Green Version]
  63. Building Construction Authority (BCA). Building Control (Buildability and Productivity) Regulations. 2020. Available online: https://www1.bca.gov.sg/buildsg/productivity/buildability-buildable-design-and-constructability/building-control-regulations (accessed on 2 August 2021).
  64. Townsend, T. International Construction Market Survey 2019. 2019. Available online: https://www.turnerandtownsend.com/en/perspectives/international-construction-market-survey-2019/ (accessed on 29 March 2021).
Table 1. Productivity metrics used in the construction sector of Singapore at different levels.
Table 1. Productivity metrics used in the construction sector of Singapore at different levels.
LevelsMetricsCodeReferences
IndustryTotal factor productivityP1 [7] [27]
Multi-factor productivityP2 [10] [33]
Output per workerP3[6][7] [25] [27] [33][34][35]
Output per work hourP4[6][7] [25] [33][34]
Value-added per workerP5 [10] [33]
Value-added per hour workedP6 [10]
Square meter per man dayP7 [10]
Growth Accounting ApproachP8 [28]
Data envelopment analysisP9 [26] [28]
CompanyOutput per workerP10[6][7] [25] [27] [33][34][35]
Output per work hourP11[6][7] [25] [33][34]
Value-added per workerP12 [10] [33]
Value-added per hour workedP13 [10] [33]
Capital productivityP14 [25][26]
ProjectSquare meter per dollarP15[6] [10]
Square meter of built-up floor area per man-dayP16 [10]
Value-added per workerP17 [10]
Output per person-hour on key tradesP18 [10]
Constructability ScoreP19 [10]
Buildable Design ScoreP20 [10]
TradeWorkhours expended/quantity installedP21 [24]
Formwork area per manhourP22 [34] [36]
Amount of rebar/prefab mesh per manhourP23 [36]
Volume of concrete per manhourP24 [36]
Area of drywall per manhourP25 [36]
Painted area per manhourP26 [36]
Number of doors installed per manhourP27 [36]
Wall tiled area per manhourP28 [36]
Floor tiled area per manhourP29 [36]
Suspended ceiling per manhourP30 [36]
Length of ducting per manhourP31 [36]
Length of electrical conduit per manhourP32 [34] [36]
Length of water pipe per manhourP33 [36]
Table 2. Profiles of post-interviewees.
Table 2. Profiles of post-interviewees.
IntervieweeDesignationOccupationYears of Experience in Construction IndustryYears of Experience in Assessing Construction Productivity
AContractorProject Manager2715
BConsultantSenior Consultant4118
CContractorSenior Site Manager148
Table 3. Profiles of survey respondents.
Table 3. Profiles of survey respondents.
Respondent ProfilesCategorizationNumber of RespondentsPercentage
Type of designationContractor2241.51%
Consultant1426.42%
Owner
Government Agencies
815.09%
916.98%
Years of Experience in Construction Industry1–200.00%
2–311.89%
3–423.77%
4–547.55%
5–101630.19%
>103056.60%
Years of Experience in Assessing Construction Productivity1–235.66%
2–3611.32%
3–4815.09%
4–51324.53%
5–101324.53%
>101018.87%
Table 4. Assessments of productivity metrics in sense of usage in frequency and relative importance.
Table 4. Assessments of productivity metrics in sense of usage in frequency and relative importance.
CodeMeanp-Value of Wilcoxon Signed-Rank Testp-Values of Kruskal–Wallis Test
DesignationsYears of Experience in Construction IndustryYears of Experience in Assessing Construction Productivity
FrequencyImportanceFrequencyImportanceFrequencyImportanceFrequencyImportanceFrequencyImportance
P13.403.720.000 10.005 10.4100.1060.5440.1770.5780.611
P23.513.720.002 10.004 10.1900.0840.3580.6360.1490.229
P33.603.580.011 10.002 10.1580.1360.7560.3800.6360.878
P43.383.320.000 10.000 10.3720.1340.2710.1250.4560.887
P53.323.430.000 10.000 10.6710.0850.8900.3260.3430.707
P62.963.190.000 10.000 10.2730.0520.5570.1270.5730.938
P73.453.680.004 10.015 10.01020.02120.0730.1510.7170.404
P82.743.170.000 10.000 10.4340.6070.3400.1040.7760.369
P92.753.090.000 10.000 10.7370.2770.2300.1160.4960.150
P103.743.740.0550.048 10.1520.00320.7000.3750.3050.169
P113.263.380.000 10.000 10.3900.0840.6840.0850.3440.565
P123.363.530.000 10.001 10.6260.1210.2710.0980.4640.817
P133.003.230.000 10.000 10.3170.5940.5570.0580.3180.714
P143.473.620.001 10.006 10.6950.5760.8390.2170.7890.633
P153.773.870.2260.2470.0980.0680.9870.6020.2080.385
P163.793.910.2390.4040.2400.1070.5460.9060.3530.144
P173.263.51 0.000 10.2150.7730.5760.1500.1400.998
P183.423.490.000 10.000 10.6830.0760.7600.0900.8870.453
P193.964.110.9550.3250.00720.03020.1790.0660.8650.479
P203.924.090.5850.4070.01920.01620.1120.1180.9160.552
P213.493.530.003 10.001 10.1440.0820.9490.4130.2440.189
P223.383.470.001 10.000 10.3910.2870.5410.4620.2400.141
P233.423.490.002 10.000 10.1200.3140.5030.3640.2350.142
P243.423.450.001 10.000 10.1700.2080.8630.6220.2810.102
P253.303.430.000 10.000 10.0670.1830.3000.4770.4400.381
P263.403.510.001 10.000 10.3390.1580.6890.5700.2040.155
P273.343.500.000 10.000 10.3000.3740.5420.6750.1100.110
P283.363.470.000 10.000 10.2900.3170.7720.5760.1010.096
P293.323.490.000 10.000 10.5700.2290.5790.5240.0570.121
P303.343.490.000 10.000 10.2060.2290.6460.5240.0790.121
P313.253.420.000 10.000 10.1170.1660.6740.5770.0560.063
P323.253.430.000 10.000 10.1170.1790.6740.6280.0560.064
P333.253.430.000 10.000 10.1170.1790.6740.6280.0560.064
1 The one sample Wilcoxon signed-rank test was significant at the level of 0.05, suggesting the respondents’ assessment was statistically different from the test value of 4. 2 The Kruskal–Wallis test was significant at the level of 0.05, suggesting the respondents’ assessment was statistically different due to different backgrounds of the respondents.
Table 5. Mann–Whitney U test between designations—frequency and importance.
Table 5. Mann–Whitney U test between designations—frequency and importance.
CodeContractor–ConsultantContractor–
Owner
Contractor
–Government
Consultant–
Owner
Consultant
–Government
Owner–
Government
Frequency
P70.7520.6650.00730.8030.00330.0013
P190.4050.4010.00130.9410.00630.009
P200.3510.3520.00330.9410.0190.025
Importance
P70.2730.8430.00830.3620.0300.0063
P100.0260.0270.0890.00430.0140.526
P190.0540.5840.0100.2600.2380.057
P200.0310.4820.00630.2600.2380.057
3 The Mann–Whitney U test was significant at the level of 0.00833, suggesting the respondents’ assessment was statistically different due to different designations of the respondents.
Table 6. Inter-group comparison of productivity performance.
Table 6. Inter-group comparison of productivity performance.
Codep-Values of Kruskal–Wallis Test
DesignationsYears of Experience in Construction IndustryYears of Experience in Assessing Construction Productivity
P10.6480.2620.969
P20.8560.1390.647
P30.5400.5220.895
P40.1900.2760.290
P50.4610.9410.112
P60.1900.1040.717
P70.2270.8680.369
P80.4320.5500.920
P90.7090.3110.741
P100.3140.5100.101
P110.1150.9930.177
P120.4440.5450.259
P130.9770.9500.917
P140.7990.6830.189
P150.0530.2400.0282
P160.7610.6690.107
P170.1300.9080.284
P180.1160.6740.233
P190.0930.6550.264
P200.0610.5240.185
P210.4770.8670.0092
P220.6850.7190.0042
P230.7310.7620.0042
P240.5850.7670.0032
P250.7570.7560.0022
P260.7570.7560.0022
P270.5680.8720.0022
P280.7570.7560.0022
P290.7570.7560.0022
P300.7570.7560.0022
P310.7570.7560.0022
P320.7570.7560.0022
P330.7570.7560.0022
2 The Kruskal–Wallis test was significant at the level of 0.05, suggesting the respondents’ assessment was statistically different due to different backgrounds of the respondents.
Table 7. Mann–Whitney U test between years of experience in assessing construction productivity performance.
Table 7. Mann–Whitney U test between years of experience in assessing construction productivity performance.
Code<5 Years–5–10 Years<5 Years–>10 Years5–10 Years–>10 Years
P150.0690.01630.696
P210.2440.00830.0073
P220.2190.00530.0033
P230.1510.00530.0033
P240.2390.00330.0033
P250.3880.00130.0033
P260.3880.00130.0033
P270.3070.00230.0033
P280.3880.00130.0033
P290.3880.00130.0033
P300.3880.00130.0033
P310.3880.00130.0033
P320.3880.00130.0033
P330.3880.00130.0033
3 The Mann–Whitney U test was significant at the level of 0.0167, suggesting the respondents’ assessment was statistically different due to different designations of the respondents.
Table 8. Average scores and ranks of productivity performance.
Table 8. Average scores and ranks of productivity performance.
RespondentIndustryCompanyProjectTrade
MeanRankMeanRankMeanRankMeanRank
Contractor3.2513.2623.4233.574
Consultant3.1313.4723.6033.734
Owner3.1923.0014.043.383
Government Agencies2.9813.2423.533.564
Σ Rank 5 7 13 15
Significant p = 0.017
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Shan, M.; Li, Y.-S.; Hwang, B.-G.; Chua, J.-E. Productivity Metrics and Its Implementations in Construction Projects: A Case Study of Singapore. Sustainability 2021, 13, 12132. https://doi.org/10.3390/su132112132

AMA Style

Shan M, Li Y-S, Hwang B-G, Chua J-E. Productivity Metrics and Its Implementations in Construction Projects: A Case Study of Singapore. Sustainability. 2021; 13(21):12132. https://doi.org/10.3390/su132112132

Chicago/Turabian Style

Shan, Ming, Yu-Shan Li, Bon-Gang Hwang, and Jia-En Chua. 2021. "Productivity Metrics and Its Implementations in Construction Projects: A Case Study of Singapore" Sustainability 13, no. 21: 12132. https://doi.org/10.3390/su132112132

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop