Next Article in Journal
The Dependence of China’s Monetary Policy Rules on Interest Rate Regimes: Empirical Analysis Based on a Pseudo Output Gap
Next Article in Special Issue
Stochastic Unit Commitment and Optimal Power Trading Incorporating PV Uncertainty
Previous Article in Journal
Optimization and Application of Integrated Land Use and Transportation Model in Small- and Medium-Sized Cities in China
Previous Article in Special Issue
Research on China’s Power Sustainable Transition Under Progressively Levelized Power Generation Cost Based on a Dynamic Integrated Generation–Transmission Planning Model
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Optimum Capacity and Placement of Storage Batteries Considering Photovoltaics

1
Faculty of Engineering, University of the Ryukyus, 1 Senbaru, Nishihara-cho, Nakagami, Okinawa 903-0213, Japan
2
Department of Electrical and Computer Engineering, Power and Renewable Energy Systems (PRES) Lab, University of Texas at El Paso, El Paso, TX 79968, USA
3
Department of Electrical and Electronics Engineering, SASTRA Deemed University, Thanjavur 613401, India
4
Fuji Elctric Co., Ltd., Tokyo 141-0032, Japan
*
Author to whom correspondence should be addressed.
These authors contributed equally to this work.
Sustainability 2019, 11(9), 2556; https://doi.org/10.3390/su11092556
Submission received: 20 March 2019 / Revised: 24 April 2019 / Accepted: 29 April 2019 / Published: 2 May 2019
(This article belongs to the Collection Sustainable Electric Power Systems Research)

Abstract

:
In recent years, due to the enforcement of the Feed-in tariff (FIT) scheme for renewable energy, a large number of photovoltaic (PV) has been introduced, which causes fluctuations in the supply-demand balance of a power system. As measures against this, the introduction of large capacity storage batteries and demand response has been carried out, and the balance between supply and demand has been adjusted. However, since the increase in capacity of the storage battery is expensive, it is necessary to optimize the capacity of the storage battery from an economic point of view. Therefore, in the power system to which a large amount of photovoltaic power generation has been introduced, the optimal capacity and optimal arrangement of storage batteries are examined. In this paper, the determination of storage battery placement and capacity considering one year is performed by three-step simulation based on probability density function. Simulations show the effectiveness of storage batteries by considering the introduction of demand response and comparing with multiple cases.

1. Introduction

Recently, the introduction of renewable energy sources (RES) has been increasing significantly due to the enforcement of Feed-in tariff (FIT) and the environmental impact of human activities. However, the output of these types of power sources is greatly influenced by natural phenomena such as solar radiation and wind speed, making it difficult to predict their power generation. In Japan, RES, especially photovoltaic (PV) power generation, has been introduced on a large scale which further increases the influences due to the large generated power error which causes the fluctuations of system voltage and supply-demand balance.
In recent years, there are many researchers dealing with such renewable energy problems [1,2,3,4,5,6]. Furthermore, conventional day-ahead unit commitment (UC) is insufficient for safe operation of power systems. Therefore, it is necessary to consider the uncertainty of output fluctuation when a large amount of renewable energy electric power system is introduced. Various optimization problems have been solved to cope with uncertainty due to renewable energy [7,8,9,10,11,12]. Moreover, when predicting renewable energy output power on the previous day and making an operation plan, the prediction error will increase with the passage of time. The operation plan made on the previous day is not possible to deal with forecasting error. In this way, with the massive introduction of renewable energy power generation, it becomes difficult to predict power generation of the power grid, therefore the consideration of uncertainty becomes an important issue. Moreover, it is necessary to develop a model to balance demand supply including prediction error. Also, it will be necessary to develop an effective approach to deal with the power generation prediction error of renewable energy generation facilities. Conventionally, the power fluctuations caused by renewable energy generation facilities have been compensated by thermal generators. However, there are restrictions on the adjustable amount (up/down spinning reserves). When power fluctuations exceeding the limit of the adjustable amount flow into the power system, the fluctuations of system frequency and system voltage are caused. As a countermeasure for that, the introduction of large capacity storage batteries and load demand adjustment (demand response) are considered [13,14,15]. It is possible to adjust the disturbance of demand-supply balance due to prediction error of generated power from renewable energy generation facilities by introducing storage batteries and demand response. Furthermore, it is also possible to reduce operating costs by cooperative control of thermal power generator, storage battery and demand response. However, since increasing the storage capacity of the storage battery is expensive, it is necessary to optimize the capacity of the storage battery from the economical point of view. The determination of optimum placement and the optimum capacity of the storage battery have been solved by various methods. Y. Zheng et al. have used a cost-benefit analysis method aimed at maximizing distribution companies (DISCO’s) profit from energy transactions, system planning, and operational cost savings [16]. Mostafa Nick et al. solve the problem of minimizing the storage battery installation-cost by using ADMM (Alternating Direction Method of Multipliers) [17]. C. H. Lo et al. have solved the optimization problem by an algorithm combining multi-path dynamic programming (MPDP) and time-shift technique [18]. S. Kahrobaee et al. proposed a hybrid stochastic method based on Monte Carlo simulation and particle swarm optimization, and decided the optimum size of wind power generation and storage battery [19]. References [20,21] have optimized capacity of storage batteries using bilevel program. References [22,23] introduce various situations, optimum operation of storage batteries in various types of storage batteries, and methods of determining the size of the storage battery. In addition, these papers have sized the storage battery by linear problem [24,25].
In this paper, we solved Mixed-integer linear programming (MILP) problem dealing with DC power flow calculation. Moreover, when determining the demand response and the capacity of the storage battery, it is necessary to consider the adjustable amount in the case where the generated power of the renewable energy generation facility greatly fluctuates. In this paper, the prediction error is quantified using the machine learning model which is the most accurate, and the spinning reserve that can correspond to the forecasting error which is decided on the previous day. Also, in the power grid where solar power generation equipment was massively introduced, we study the optimum capacity and optimum arrangement of grid storage batteries based on the dynamic operation method. This study reports, an economically useful planning method that does not involve rapid and significant operation change of thermal power generations via dynamically planning every 3 h. The effectiveness of the proposed method is verified through one-year simulation of transmission systems using MATLAB software.
In this paper, we propose a new method of determining the optimal arrangement and capacity for storage batteries. By dividing the simulation into three stages, we determined the optimal placement and capacity of the storage battery. This is derived from the idea of the three-stage battery capacity determination method in the literature [26]. The first stage predicts PV output. In the second stage, taking into account the PV prediction error, the optimum capacity and the optimum number of storage batteries are obtained from the standard deviation. In the third stage, a one-year simulation is conducted to confirm the effectiveness of the determined battery placement and capacity. By optimizing storage battery capacity and layout, it is possible to calculate the optimum storage battery capacity for economic improvement and introduce the optimum storage battery capacity, so that even when a large amount of renewable energy equipment is introduced, economic efficiency indicates that operations that do not deteriorate can be performed. Also, we show that proposed method can achieve operation which minimizes fuel cost and startup cost of the generator, and minimizes operation cost.
The paper is organized as follows: Section 2 explains the methodology for determining the optimal placement and optimal capacity of the storage battery proposed in this paper, the objective function for solving the simulation, and the formulation of constraints. Section 3 explains the conditions for simulation to confirm the effectiveness of the optimal placement and capacity of the storage battery determined in Section 2. In Section 4, the simulation results are presented as case studies. Section 5 concludes this paper.

2. Problem Formulations

Figure 1 shows the method for determining the capacity and location of the storage battery [26]. In the first stage, PV output forecasting is performed based on the data of 2015 using feedforward neural network (FFNN) which is machine learning. In the second stage, the UC problem will be solved on a daily basis in the 2016 load demand, using the optimal placement and capacity of storage batteries as variables. In addition, the decision variable S o C b m a x is calculated for one year. It is assumed here that the power demand forecast for 2016 is accurate. In addition, let standard deviation σ b S O C of S o C b m a x for 1 year be the storage battery optimal capacity in the bus b. In the third stage, a one-year simulation is conducted using the load demand of 2017 in order to confirm the effectiveness of the determined placement and capacity of storage batteries. The decision variable S o C b m a x is calculated for one year from the one-day optimization problem with the following objective function and constraints. Let the standard deviation σ b S O C of S o C b m a x for one year be the optimum capacity of the bus b.
σ b S O C = 1 n i = 1 n ( S o C b , i m a x S o C b , i m a x ¯ ) 2
S o C b , i m a x ¯ = i = 1 n S o C b , i m a x n

2.1. Objective Function

The objective function Equation (3) is minimizing total cost (F) which includes fuel cost ( F C ), start-up cost ( S U C ) and penalty cost of energy not served ( E N S × C e n s ).
F = i = 1 N G t = 1 24 b = 1 N B ( F C i t b + S U C i t b ) + t = 1 24 ( E N S t × C e n s ) + b = 1 N B ( S o C b m a x × I C S o C )
I C S o C is the installation cost of storage batteries converted in one day.
I C S o C = C S o C h × 365

2.2. Constraints

  • System power balance
    Equation (5) is a constraint that the sum of the power demand D t b n e t and the amount of electricity generated by the generator P i t b and E N S t become equal.
    i = 1 N G ( P i t b × X i t b ) + E N S t b = D t b n e t t T , b B
  • Generation output limits
    The generation limits of each unit for each period are set as follows [27]
    P i m i n P i t P i m a x
    Constraints Equation (6) bound the generation by the minimum power output and the maximum available power output of unit i in period t.
  • Up/down spinning reserve
    Based on the following constraint formula, even when a forecast error occurs between ± 2 σ P V in the current day operation plan, change of the start/stop state of the generator decided in the next day operation plan will not occur [28].
    D α P V μ P V + 2 σ P V i = 1 N G ( P i m a x × X i )
    D μ P V 2 σ P V i = 1 N G ( P i m i n × X i )
  • Ramp rate
    Ramp rate constraints are constraints that limit the rate of change of generator output.
    | P i t + 1 P i t | Δ P i m a x
  • Transmission constraints
    Transmission line restrictions are restrictions to ensure that the transmission capacity S l t flowing through the transmission capacity limit S l m a x does not exceed.
    S l t S l m a x
  • Minimum up/down time
    Minimum up and down time constraints are first formulated as mixed-integer linear expressions relying on binary variables associated with the startup, shutdown, and on/off states of generating units.
    T i o n X i o n ( t )
    T i o f f X i o f f ( t )
    The explanation of each variable is shown in abbreviation here.
  • Demand response constraints
    t = 1 24 D t b n e t = t = 1 24 ( D t b n e t + D R t b )
    D R t b m a x D R t b D R t b m a x
    where D R t b m a x is the maximum amount of demand response. In this research, D R t b m a x is 5% of the total load demand.
  • Storage battery constraints
    Hereinafter, the storage battery restriction will be described [29]. where ch is the charge energy of the storage battery, and dis is the discharge energy. Each storage battery output at time t must be charge and discharge output within the range of c h m i n ( d i s m i n ) and c h m a x ( d i s m a x ) . Also, charging and discharging cannot be performed beyond the limit of the state of charge (SoC).
    S o C t , b = S o C t 1 , b + c h t b d i s t b t T , b N B
    S o C t b S o C b m a x t T , b N B
    c h t b c h b m a x t T , b N B
    d i s t b c h b m a x t T , b N B
    c h b m a x = S o C b m a x R b N B
    In this section, assume that NaS batteries are used for storage batteries and R = 6 (see Table 2).
Also, the values of constraints in Equations (6), (9), (11) and (12) are described in Table 3. The value of S l m a x in Equation (10) is shown in Table 4.

3. Simulation Conditions

The simulation conditions are shown in Table 1. “w/o ESS” is a case where a storage battery is not placed. Re-predictive re-planning that iteratively solves the optimization problem of the finite interval periodically in all cases (see Figure 2).
The optimization period is 24 h, the sample time is 3 h, and the unit commitment at the time of prediction is updated every 3 h in real time. Table 2 shows the storage battery parameters used in this paper. Table 2 is quoted from the details of the storage battery published by NGK Insulators, Ltd., Nagoya, Japan, a Japanese company [30]. The power system assumed in this paper is shown in Figure 3.
The generator parameters are shown in Table 3. Table 3 uses data published by ”The Okinawa Electric Power”, a Japanese electricity company in Okinawa Prefecture. In Table 3, a, b and c are the fuel cost characteristic constant of each generator. GA ∼ GE in Figure 3 are generator installation bus lines, and the numbers described in parentheses are the numbers of generator G in Table 3. Table 4 shows the transmission capacity assumed by the author. Resistance value R is simply 0 for DC power flow calculation [31]. Table 5 assumes the power demand of each load bus based on the population in Okinawa prefecture of Japan [32]. It is assumed that load demand can be predicted with high accuracy and only PV output is predicted. To verify the effectiveness of the proposed method in this research, we simulate a year from January 2017 to December 2017 (Analysis Stage). To solve this problem, MATLAB mixed integer programming (intlinprog) was used. Figure 4a,b show the actual demand of load demand and PV output ( σ P V = 1) for two years from January 2016 to December 2017, respectively. Figure 4a is the same source as [31]. Figure 4b is calculated using FFNN based on the data of solar radiation in 2015 in Okinawa prefecture in Japan [33].
Annual simulation is not efficient because it takes a lot of time. Therefore, by using clustering, we try to shorten the simulation time. Figure 5 shows the net load demand in 2016 (the demand from which PV output is subtracted from load demand).
The bold lines indicate demand classified into clusters. The number of clusters was set as 30 from the elbow method (Figure 6). The Sum of Squared Errors (SSE) is shown in the following equation.
S S E = i = 1 k { j = 1 A i ( y i y ^ i , j ) ) 2 }
Here, k is the number of clusters, A i is the total number of data classified as cluster i, y i is the cluster i, y ^ i , j In addition, the j th data classified as cluster i.

4. Simulation Results

4.1. Evaluation Stage

Figure 7a–d show the probability density function of the maximum value ( S o C m a x ) of the storage battery capacity in each cases. Figure 8 shows the average and standard deviation SOC of the maximum value ( S o C m a x ) of the storage battery capacity of each bus line according to the annual simulation result. The standard deviation SOC in Figure 8 is taken as the optimum arrangement optimum capacity and is summarized in Table 6. In the case of bus 4 of Case 1 (see Figure 7a), the standard deviation σ 4 S o C of S o C 4 m a x is 64.77 MWh. From Table 2, since it is 4.8 MWh per unit, 64.77/4.8 = 13.4937 = 14 units. From Table 6, it can be read that the storage batteries are not arranged in the bus 1 and many are arranged in the bus 7 and 8. This is because of the load demand of the bus 1 in the power system of Figure 3 is small and there are enough thermal power generators. On the other hand, the load demand is large near the bus 7 and 8, and there are not many generators installed near them. At the peak of load demand, the capacity of the transmission line in the vicinity is congested, and it is necessary to start the low-efficiency generator around it, which increases the operation cost. Therefore, by arranging the storage batteries in the bus 7 and 8 and reducing the size of the load demand by the discharge power of the storage batteries, it is possible to reduce the cost.

4.2. Analysis Stage

Figure 9a shows the daily load rate. Figure 9b,c show the operating costs for each year in each case. Figure 10 shows the total cost in each case. Table 7 shows simulation results of Analysis Stage. From Figure 9a,b, it can be confirmed that the daily load rate is improved and the operation cost can be reduced through one year when the storage battery is arranged (Case 1). From Figure 9c, it can be confirmed that the introduction of PV throughout the year (Case 2, 3) can greatly reduce operating costs. Figure 10 and Table 7, when the storage battery is not considered (Case 0) and the case where the storage battery is arranged (Case 1), the total cost is reduced by 427.51 − 409.96 = 17.55 billion yen I was able to achieve it.
In addition, it can be confirmed that reduction of 413.32 − 409.96 = 3.36 million yen can be achieved even when compared with the case where Day - 212 where penalty cost occurred is excluded. Comparing the case where PV was introduced from σ P V = 1 (Case 1) to σ P V = 2 (Case 2), the storage battery cost increased from 2.05 billion yen to 3.058 million yen, but the total cost increased from 40.996 billion yen It can be confirmed that it can be reduced to 38.769 billion yen. When DR is not taken into account (Case 2) and DR is taken into account (Case 3), by considering DR, the storage battery cost can be reduced and the total cost can be reduced.

5. Conclusions

In this paper, we examined the optimal capacity and optimal placement method for storage battery installation in the power system where a large amount of photo-voltaic (PV) was introduced. Based on the probability density function, we calculated the capacity and location of the storage battery for economic improvement. Even when a large amount of renewable energy power generation equipment was introduced based on the calculated storage battery capacity and the operation plan introducing the placement, the operation was achieved without reducing the economic efficiency. At the same time, operation has been achieved which minimizes generator start-up costs, operating costs and storage battery costs. In addition, the introduction of demand response has also improved the operation cost. As future work, we will carry out system operation to meet various requirements by deciding the optimal capacity and placement of storage batteries considering the multi-objective functions.

Author Contributions

These authors contributed equally to this work.

Conflicts of Interest

The authors declare no conflict of interest.

Abbreviations

The following notations are used in this manuscript:
Objective function and constraints:
bBus number
c h t b Discharged energy of storage battery installed on bus b
c h b m a x Battery rated output of the bus b
d i s t b Discharged energy of storage battery installed on bus b
hExpected life of the storage battery
iThermal power Generator number
nTotal number of days
BTotal number of Bus
C e n s Cost of energy not served
C S o C Battery cost per 1 MWh
DTotal of load demand
D t b n e t Load demand at bus b at time t
D R t b Amount of power transferred by demand response
D R t b m a x Demand response maximum amount
E N S t Energy not served at hour t
F C i t Fuel cost function
I C S O C Storage battery cost per day
N B Number of bus
N G Number of the generators
P i t Output power of ithgenerator at time t
P i m i n Minimum output limit of ith generator
P i m a x Maximum output limit of ith generator
Δ P i m a x Maximum output change rate of generator i
Δ P G i m a x Ramp rate limits of generator i
RRatio of the storage battery capacity to the rated output
S U C i t Start-up cost function.
S o C t b State of charge of storage battery installed on bus b
S o C b , i m a x Maximum value of the storage battery capacity of the bus b in the day i
S l , t Power flow on transmission line l at time t
S l m a x Maximum capacity of line l
TTotal time of day
T i o n Minimum up time of i
T i o f f Minimum down time of i
X i t ith generator status at hour t (1/0 for on/off)
X i o n ( t ) Duration of continuously on of generator i at time t
X i o f f ( t ) Duration of continuously off of generator i at time t
α P V PV installation amount parameter
σ P V Standard deviation of PV output prediction error
σ S O C Standard deviation of foecast error
μ P V Output of PV
Clustering variable:
kNumber of clusters
y i Cluster i
y ^ i j th data classified as cluster i
A i is the total number of data classified as cluster i

References

  1. Korpaas, M.; Holen, A.T.; Hildrum, R. Operation and sizing of energy storage for wind power plants in a market system. Int. J. Electr. Power Energy Syst. 2003, 25, 599–606. [Google Scholar] [CrossRef]
  2. Brekken, T.K.A.; Yokochi, A.; von Jouanne, A.; Yen, Z.Z.; Hapke, H.M.; Halamay, D.A. Optimal Energy Storage Sizing and Control for Wind Power Applications. IEEE Trans. Sustain. Energy. 2011, 2, 69–77. [Google Scholar] [CrossRef]
  3. Atwa, Y.M.; El-Saadany, E.F. Optimal Allocation of ESS in Distribution Systems With a High Penetration of Wind Energy. IEEE Trans. Power Syst. 2010, 25, 1815–1822. [Google Scholar] [CrossRef]
  4. Castronuovo, E.D.; Peças Lopes, J.A. Optimal operation and hydro storage sizing of a wind–hydro power plant. Int. J. Electr. Power Energy Syst. 2004, 26, 771–778. [Google Scholar] [CrossRef]
  5. Alnaser, S.W.; Ochoa, L.F. Optimal Sizing and Control of Energy Storage in Wind Power-Rich Distribution Networks. IEEE Trans. Power Syst. 2016, 31, 2004–2013. [Google Scholar] [CrossRef]
  6. Choi, D.G.; Min, D.; Ryu, J.H. Economic Value Assessment and Optimal Sizing of an Energy Storage System in a Grid-Connected Wind Farm. Energies 2018, 11, 591. [Google Scholar] [CrossRef]
  7. Sedghi, M.; Ahmadian, A.; Golkar, M.A. Optimal Storage Planning in Active Distribution Network Considering Uncertainty of Wind Power Distributed Generation. IEEE Trans. Power Syst. 2016, 31, 304–316. [Google Scholar] [CrossRef]
  8. Bludszuweit, H.; Dominguez-Navarro, J.A. A Probabilistic Method for Energy Storage Sizing Based on Wind Power Forecast Uncertainty. IEEE Trans. Power Syst. 2011, 26, 1651–1658. [Google Scholar] [CrossRef]
  9. Xiong, P.; Singh, C. Optimal Planning of Storage in Power Systems Integrated With Wind Power Generation. IEEE Trans. Sustain. Energy 2016, 7, 232–240. [Google Scholar] [CrossRef]
  10. Zhu, D.; Hug, G. Decomposed Stochastic Model Predictive Control for Optimal Dispatch of Storage and Generation. IEEE Trans. Smart Grid 2014, 5, 2044–2053. [Google Scholar] [CrossRef]
  11. Gast, N.; Tomozei, D.; Le Boudec, J.Y. Optimal Generation and Storage Scheduling in the Presence of Renewable Forecast Uncertainties. IEEE Trans. Smart Grid 2014, 5, 1328–1339. [Google Scholar] [CrossRef] [Green Version]
  12. Haghi, H.V.; Lotfifard, S. Spatiotemporal Modeling of Wind Generation for Optimal Energy Storage Sizing. IEEE Trans. Sustain. Energy 2015, 6, 113–121. [Google Scholar] [CrossRef]
  13. Wogrin, S.; Gayme, D.F. Optimizing Storage Siting, Sizing, and Technology Portfolios in Transmission-Constrained Networks. IEEE Trans. Power Syst. 2015, 30, 3304–3313. [Google Scholar] [CrossRef]
  14. Liu, Y.; Du, W.; Xiao, L.; Wang, H.; Bu, S.; Cao, J. Sizing a Hybrid Energy Storage System for Maintaining Power Balance of an Isolated System With High Penetration of Wind Generation. IEEE Trans. Power Syst. 2016, 31, 3267–3275. [Google Scholar] [CrossRef]
  15. Bucciarelli, M.; Paoletti, S.; Vicino, A. Optimal sizing of energy storage systems under uncertain demand and generation. Appl. Energy 2018, 225, 611–621. [Google Scholar] [CrossRef]
  16. Zheng, Y.; Dong, Z.Y.; Luo, F.J.; Meng, K.; Qiu, J.; Wong, K.P. Optimal Allocation of Energy Storage System for Risk Mitigation of DISCOs With High Renewable Penetrations. IEEE Trans. Power Syst. 2014, 29, 212–220. [Google Scholar] [CrossRef]
  17. Nick, M.; Cherkaoui, R.; Paolone, M. Optimal siting and sizing of distributed energy storage systems via alternating direction method of multipliers. Int. J. Electr. Power Energy Syst. 2015, 72, 33–39. [Google Scholar] [CrossRef] [Green Version]
  18. Lo, C.H.; Anderson, M.D. Economic dispatch and optimal sizing of battery energy storage systems in utility load-leveling operations. IEEE Trans. Energy Convers. 1999, 14, 824–829. [Google Scholar] [CrossRef]
  19. Kahrobaee, S.; Asgarpoor, S.; Qiao, W. Optimum Sizing of Distributed Generation and Storage Capacity in Smart Households. IEEE Trans. Smart Grid 2013, 4, 1791–1801. [Google Scholar] [CrossRef] [Green Version]
  20. Dvorkin, Y.; Fernández-Blanco, R.; Kirschen, D.S.; Pandžić, H.; Watson, J.P.; Silva-Monroy, C.A. Ensuring Profitability of Energy Storage. IEEE Trans. Power Syst. 2017, 32, 611–623. [Google Scholar] [CrossRef]
  21. Hassan, A.; Dvorkin, Y. Energy Storage Siting and Sizing in Coordinated Distribution and Transmission Systems. IEEE Trans. Sustain. Energy 2018, 9, 1692–1701. [Google Scholar] [CrossRef]
  22. Sheibani, M.R.; Yousefi, G.R.; Latify, M.A.; Dolatabadi, S.H. Energy storage system expansion planning in power systems: A review. Renew. Power Gener. 2018, 12, 1203–1221. [Google Scholar] [CrossRef]
  23. Das, C.K.; Bass, O.; Kothapalli, G.; Mahmoud, T.S.; Habibi, D. Overview of energy storage systems in distribution networks: Placement, sizing, operation, and power quality. Renew. Sust. Energy Rev. 2018, 91, 1205–1230. [Google Scholar] [CrossRef]
  24. Fiorini, L.; Pagani, G.A.; Pelacchi, P.; Poli, D.; Aiello, M. Sizing and Siting of Large-Scale Batteries in Transmission Grids to Optimize the Use of Renewables. IEEE J. Emerg. Sel. Top. Circuits 2017, 7, 285–294. [Google Scholar] [CrossRef] [Green Version]
  25. Yacar, D.; Tejada-Arango, D.A.; Wogrin, S. Storage allocation and investment optimisation for transmission-constrained networks considering losses and high renewable penetration. IET Renew. Power Gen. 2018, 12, 1949–1956. [Google Scholar] [CrossRef]
  26. Pandžić, H.; Wang, Y.; Qiu, T.; Dvorkin, Y.; Kirschen, D.S. Near-Optimal Method for Siting and Sizing of Distributed Storage in a Transmission Network. IEEE Trans. Power Syst. 2015, 30, 2288–2300. [Google Scholar] [CrossRef]
  27. Carrion, M.; Arroyo, J.M. A computationally efficient mixed-integer linear formulation for the thermal unit commitment problem. IEEE Trans. Power Syst. 2006, 21, 1371–1378. [Google Scholar] [CrossRef]
  28. Bruninx, K.; Delarue, E. Endogenous probabilistic reserve sizing and allocation in unit commitment models: Cost-effective, reliable, and fast. IEEE Trans. Power Syst. 2017, 32, 2593–2603. [Google Scholar] [CrossRef]
  29. Fernández-Blanco, R.; Dvorkin, Y.; Xu, B.; Wang, Y.; Kirschen, D.S. Optimal Energy Storage Siting and Sizing: A WECC Case Study. IEEE Trans. Sustain. Energy 2017, 8, 733–743. [Google Scholar] [CrossRef]
  30. NGK Insulators, Ltd. Available online: https://www.ngk.co.jp/ (accessed on 11 January 2017).
  31. The Okinawa Electric Power Company, Incorporated (OEPC). Available online: https://www.okiden.co.jp/ (accessed on 11 January 2017).
  32. Okinawa Prefectural Statistical Data Website. Available online: https://www.pref.okinawa.jp/toukeika/index.html (accessed on 11 January 2017).
  33. MathWorks MATLAB Website. Available online: https://jp.mathworks.com/help/deeplearning/ref/feedforwardnet.html (accessed on 11 January 2017).
Figure 1. Optimal placement and optimum capacity.
Figure 1. Optimal placement and optimum capacity.
Sustainability 11 02556 g001
Figure 2. Rolling horizon.
Figure 2. Rolling horizon.
Sustainability 11 02556 g002
Figure 3. Power system model.
Figure 3. Power system model.
Sustainability 11 02556 g003
Figure 4. Load demand curve and PV output. (a) actual demand of load demand and (b) PV output.
Figure 4. Load demand curve and PV output. (a) actual demand of load demand and (b) PV output.
Sustainability 11 02556 g004
Figure 5. Net load demand.
Figure 5. Net load demand.
Sustainability 11 02556 g005
Figure 6. Elbow method.
Figure 6. Elbow method.
Sustainability 11 02556 g006
Figure 7. (a): PDF of Maximum battery capacity for 1 year in Case 1; (b): PDF of maximum battery capacity for 1 year in Case 1 at Bus 4; (c): PDF of Maximum battery capacity for 1 year in Case 2; (d): PDF of Maximum battery capacity for 1 year in Case 3.
Figure 7. (a): PDF of Maximum battery capacity for 1 year in Case 1; (b): PDF of maximum battery capacity for 1 year in Case 1 at Bus 4; (c): PDF of Maximum battery capacity for 1 year in Case 2; (d): PDF of Maximum battery capacity for 1 year in Case 3.
Sustainability 11 02556 g007
Figure 8. Mean and standard deviation of maximum battery capacity in each case (blue: Case 1, green: Case 2, yellow: Case 3).
Figure 8. Mean and standard deviation of maximum battery capacity in each case (blue: Case 1, green: Case 2, yellow: Case 3).
Sustainability 11 02556 g008
Figure 9. Simulation results. (a) Daily load factor; (b) Operation cost for 1 year and (c) Operation cost for 1 year (without Case 0).
Figure 9. Simulation results. (a) Daily load factor; (b) Operation cost for 1 year and (c) Operation cost for 1 year (without Case 0).
Sustainability 11 02556 g009
Figure 10. Total cost.
Figure 10. Total cost.
Sustainability 11 02556 g010
Table 1. Simulation conditions.
Table 1. Simulation conditions.
CaseESS α PV DR
w/o ESS (Case 0)×1×
11×
22×
32
Table 2. NAS battery parameter.
Table 2. NAS battery parameter.
NAS Battery
Output0.8 MW
Capacity4.8 MWh
Cost1.92 Billion yen
Lifespan15 year
Table 3. Generator’s data.
Table 3. Generator’s data.
G1G2G3G4G5G6
Use fuelCoalCoalOilOilCoalCoal
P m a x [MW]220220125103156156
P m i n [MW]848460506060
a [yen]80,00080,000632,000632,00080,00080,000
b [yen/MW]400040009200920040004000
c [yen/MW 2 ]0.40.42.12.10.40.4
Δ P i m a x [MW]444462.551.531.231.2
S U C [yen]1,100,0001,100,000375,000309,000780,000780,000
T o n / o f f [h]886666
G7G8G9G10G11G12
Use fuelLNGLNGLNGOilOilOil
P m a x [MW]2512513512560103
P m i n [MW]12212217603050
a [yen]132,000132,000132,000632,000632,000632,000
b [yen/MW]440044004400920092009200
c [yen/MW 2 ]5.05.05.02.12.12.1
Δ P i m a x [MW]84843562.53051.5
S U C [yen]753,000753,000105,000375,000180,000309,000
T o n / o f f [h]884646
Table 4. Transmission line parameters.
Table 4. Transmission line parameters.
From BusTo BusR [pu]X [pu]Limits [MVA]
120.00.1300
230.00.1480
340.00.1280
360.00.1250
450.00.1480
570.00.1500
670.00.1500
780.00.1700
Table 5. Load demand data.
Table 5. Load demand data.
Load No.L1L2L3L4
Bus No.Bus 1Bus 3Bus 7Bus 8
Ratio9%24%24%43%
Table 6. Optimal placement and optimum capacity.
Table 6. Optimal placement and optimum capacity.
Bus No.12345678Total
Units (Case 1)0701412105958160
Units (Case 2)03619159394575238
Units (Case 3)02222262164447188
Table 7. Simulation result.
Table 7. Simulation result.
CaseBattery Cost [Billion Yen]Operating CostTotal Cost
00427.51427.51
0 (w/o Day-212)0413.32413.32
120.35389.62409.96
230.58357.12387.69
324.15357.83381.99

Share and Cite

MDPI and ACS Style

Aoyagi, H.; Isomura, R.; Mandal, P.; Krishna, N.; Senjyu, T.; Takahashi, H. Optimum Capacity and Placement of Storage Batteries Considering Photovoltaics. Sustainability 2019, 11, 2556. https://doi.org/10.3390/su11092556

AMA Style

Aoyagi H, Isomura R, Mandal P, Krishna N, Senjyu T, Takahashi H. Optimum Capacity and Placement of Storage Batteries Considering Photovoltaics. Sustainability. 2019; 11(9):2556. https://doi.org/10.3390/su11092556

Chicago/Turabian Style

Aoyagi, Hiroki, Ryota Isomura, Paras Mandal, Narayanan Krishna, Tomonobu Senjyu, and Hiroshi Takahashi. 2019. "Optimum Capacity and Placement of Storage Batteries Considering Photovoltaics" Sustainability 11, no. 9: 2556. https://doi.org/10.3390/su11092556

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop