1. Introduction
In September 2020, China proposed the concept of “carbon peak and carbon neutrality” (referred to as “dual carbon”) to the world for the first time [
1]. Under this goal, RE generation via wind and photovoltaic power will continue to grow rapidly. In January 2022, the National Development and Reform Commission proposed to accelerate the construction of large-scale wind power and photovoltaic power generation bases in western and northern China, focusing on desert areas [
2]. Therefore, the RE consumption demand of China is continuing to increase during the “14th Five-Year Plan” period.
The proposed “dual carbon” target makes the development of RE installed capacity more urgent. RE generation is characterized by randomness, volatility, and unpredictability. The key studied issue concerns how to reasonably configure the ESS in order to improve the flexibility and rapid response capability of the power grid for the purpose of realizing the effective consumption of new energy resources [
3,
4,
5].
In addition, there are mutual constraints between the RE installed capacity, the RE utilization rate, and the scale of RE power generation [
6,
7]. For example, after increasing the RE installed capacity, the proportion of RE power generation will be increased but the utilization rate will be decreased. The economics of ESS investment is also a key issue [
8]. If investment in ESS is too large, there will be a serious waste of resources. There is an urgent need to select the appropriate ESS configuration capacity to maximize the technical and economic benefits. Through the analysis of the above, the key challenges and difficulties of this study are summarized, which is also a point of innovation compared with other studies.
These include the following considerations:
How to describe the constraints between the RE installed capacity, the RE utilization rate, and the proportion of RE power generation from the mathematical mechanism.
How to visualize the theoretical basis of the way in which RE, generated via the mathematical mechanism, is consumed by ESS.
How to propose a suitable ESS configuration method to realize the balance between the economy of ESS investment, RE utilization rate, and the proportion of RE generation.
At present, there are several main calculation methods for optimizing the configuration of ESS capacity. These include typical scenario methods [
9,
10,
11,
12,
13,
14], production simulation methods [
15,
16,
17,
18,
19,
20,
21,
22], and intelligent algorithm optimization methods [
23,
24,
25].
The typical scenario method uses several typical scenarios of load and RE to calculate the ESS configuration capacity [
9,
10,
11,
12]. In refs. [
9,
10,
11], the ESS is rationally configured to solve the power fluctuation and intermittency problems caused by large-scale renewable energy generation connected to the grid via setting typical scenarios. However, the typical scenario setting is too simple, resulting in inaccurate ESS configuration results. The influence mechanism of ESS and the combined planning model of a source storage network are constructed in [
12,
13]. However, there is a lack of analysis of the relationship between ESS configuration and RE consumption capacity. One study [
14] uses a Philippine offshore island to optimize the capacity configuration of a hybrid energy system. Aiming for the lowest operating cost of an isolated island power grid, the optimal configuration method of ESS is proposed based on selected typical scenarios.
The typical scenario method covers fewer scenarios, meaning that it cannot reflect various extreme cases of energy storage configuration requirements. The typical scenario method can meet the ESS configuration demand in most scenarios throughout the year, but it cannot reflect the optimal configuration of ESS for systems with a high percentage of RE resources in extreme situations. The results are heavily dependent on the data from the selected scenarios. The uncertainty of simulation prediction data can result in excess capacity or a lack of configured capacity. The result may differ greatly from the actual requirement.
The production simulation method can simulate various power supply conditions and power supply balance by time series under the given system operating boundaries. The ESS capacity demand is finally obtained through time series production simulation [
15,
16,
17,
18,
19,
20,
21,
22]. It is also the most frequently used calculation method. Evaluating the energy storage capacity requirements under different time scales, a multi-timescale coordinated optimization strategy considering flexible requirements, is proposed using the time series production simulation in [
15]. Combined with the sequential Monte Carlo simulation method, a wind farm energy storage optimization configuration method considering energy storage life loss, is proposed in [
16]. The operation probability state of photovoltaic power generation and load is obtained using production simulation, and a coordinated planning method of optical storage network based on a probabilistic time series production simulation is proposed in [
17]. An improved stochastic production simulation method is used to study the reliability assessment in [
18] and RE consumption of multi-energy systems in [
19].
However, the production simulation method determines the ESS scale through several tentative simulations, and the complexity and calculation amount increase sharply when the number of traversal scenarios is on the hourly scale. In addition, uncertainty of simulation prediction data can result in the existence of excess capacity or lack of configured capacity, which also occurs in [
20,
21,
22].
In addition, the intelligent optimization algorithm aims to seek the optimal solution to the optimization function of multi-objective ESS configuration [
23,
24,
25]. The INSGA-II algorithm is proposed in [
23] to solve the multi-objective configuration optimization model of ESS, aiming for the minimum comprehensive cost and maximum RE utilization rate. The optimal sizing and configuration method of ESS is established considering its stochastic nature using PSO in the distribution network in [
24]. To maximize the proportion of RE power generation and minimize the annual investment cost as comprehensive optimization objectives, the multi-objective robust optimization allocation for ESS is proposed via the use of a novel confidence gap decision method in [
25].
In the above literature, intelligent algorithms are used to optimize the ESS configuration with the goal of optimizing the performance of certain aspects of the system. This method reflects the ESS demand under specific targets, but it fails to fully utilize the RE generation characteristics. The configuration process lacks the mathematical mechanism of RE consumption. The theoretical basis for ESS absorption RE is not analyzed in the configuration process.
Most of the current ESS capacity configuration methods are carried out based on the typical scenario method or time series production simulation. The typical scenario method is to use typical methods and scenarios to calculate the scale of ESS to reflect the annual demand for ESS configuration. This method can meet the ESS needs of most scenarios throughout the year. However, it cannot reflect the optimal configuration of ESS for a high proportion of RE resources in extreme situations, nor can it reflect the ESS needs when the proportion of RE is very low. This latter method tends to determine the size of the ESS configuration through trialing multiple simulations. Uncertainty of simulation prediction data can result in the existence of excess capacity or lack of configured capacity. In addition, this method reflects the ESS demand under specific targets, but it fails to fully utilize the RE generation characteristics. The configuration process lacks the mathematical mechanism of RE consumption, and the calculation process is too complicated.
The research objective of this paper is to solve the problems of a lack of mathematical basis for ESS absorbing RE, an excess or lack of configured capacity, and a too complicated calculation process. To this end, an ESS configuration method based on “equal area criterion” is provided. The ESS capacity and the RE consumption capacity can be accurately matched by using this provided method to realize the optimal ESS configuration under the established RE consumption target. This method realizes the goal of deep coupling and synergistic planning between ESS and RE consumption for the first time.
Compared with the research in other literature, the contributions of this paper are as follows.
The power balance model of unconstrained grid with RE is established and statistical features are proposed such as “RE consumption characteristic curve” and “interval guarantee hours”. The constraints between the installed capacity of renewable energy, the utilization rate of renewable energy, and the proportion of renewable energy power generation are described mathematically.
The working principle diagram of RE consumption including ESS is constructed to visually reveal the systematic principle of how ESSs absorb RE. The “equal area criterion” is proposed for the ESS optimization configuration. A complete set of parameters such as “ESS peak power, ESS capacity, and RE penetration rate” are obtained for different RE consumption scenarios. The ESS capacity and the RE consumption capacity can be accurately matched to realize the optimal ESS configuration under the established RE consumption target.
The ESS and RE configuration scenarios are obtained based on fitting and interpolation methods in accordance with the known and unknown scenarios of RE installed capacity in the planning year. The configuration scenarios realize the balance between the economics of ESS investment, RE utilization rate, and the proportion of RE generation.
The remainder of this paper is organized as follows. In
Section 2, based on the characteristics of RE sources and power grid, the power balance mechanism is analyzed. On this basis, the consumption characteristic curve is constructed to reveal the consumption mechanism of RE. In
Section 3, the interval power generation statistical characteristics of RE are extracted and the working principle diagram of RE consumption, including ESS, is constructed to visually show the consumption capacity of RE and the working position of ESS. In
Section 4, the “equal area criterion” of ESS optimization configuration is proposed to reveal the systematic principle of ESS absorbing RE. The collaborative configuration process of ESS and RE is proposed in different scenarios. Finally, the power grid of the Q region in China is taken as an example to prove the proposed method reasonable and effective in
Section 5.
4. Optimal Configuration Analysis Method of ESS Based on “Equal Area Criterion”
The ESS configured capacity according to
Figure 8 is the maximum value of Si for the whole year. The ESS only runs at full load on the day to fully play the role of RE consumption, which has rich capacity or is partially idle in other periods. Therefore, it is necessary to find a more reasonable ESS capacity allocation method. In
Section 4.1, the “equal area criterion” of ESS optimization configuration is proposed to reveal the systematic principle of ESS absorbing RE. The optimal configuration process of ESS is proposed under known or unknown RE installed capacity C scenarios in
Section 4.2.
4.1. “Equal Area Criterion” in ESS Optimal Configuration
The number of daily blocked hours of RE
Tdi and the number of interval RE generation hours Δ
Tdi can be calculated from Equations (10) and (11). It is assumed that
Tb represents the number of hours after converting the ESS capacity according to the installed capacity of RE
C. Three kinds of curves, namely,
Tdi, Δ
Tdi, and
Tb, are shown in
Figure 9.
As can be seen from
Figure 9, the intersection point of
Tdi and
Tb is
O+, and the intersection point of Δ
Tdi and
Tb is
O−, respectively. Then, the areas of
S+ and
S− are shown in Equation (18).
The goal of ESS configuration is to absorb all the daily blocked generation that is relatively stable in RE with r% probability throughout the year (that is, the area (S0 + S−) after ΔTdi integration). With O− point as the dividing line, ESS can absorb more blocked generation than is expected on one side and absorb less blocked generation than is expected on the other side. Before O− point, Tb is greater than or equal to ΔTdi; it can absorb an additional area of S+. After O− point, Tb is less than ΔTdi and it can absorb a reduced area of S−. When the amount of absorbed generation by the ESS before and after O− point is equal, the total target of the blocked absorbed generation throughout the year can be guaranteed to remain unchanged. That is called the “equal area criterion”. This method avoids allocating the ESS capacity according to the maximum daily blocked generation of RE (max(Tbr)) and reduces the probability of idle ESS capacity.
The “equal area criterion” is essentially a global optimization method. In addition, the optimal converted hours
Tb of the ESS can be found via a one-dimensional search method. As shown in (19), when Δ
S takes the minimum value, the optimal converted hours
Tbir of the ESS can be found under the consumption capacity
xi and the guaranteed rate
r%.
Pb = [
Pb1,
Pb1, …,
PbN] is the per unit value of the RE theoretical power on the day
τB. The ESS on day
τB needs to absorb all the theoretical power of RE between
xi and max (
Pb) from the working position
xi. At this time, RE generation is no longer blocked. The peak ESS power
Pbir and ESS time
Tbir are shown in Equation (20)
where
Ebir represents ESS capacity. The ESS configuration method described in this paper takes the initial consumption capacity of RE
x1 as the decoupling point. The ESS configuration depends only on the RE characteristics, and the RE consumption capacity depends only on the power system balance and system parameters. According to this,
Tgir,
Pbir, and
Ebir can be obtained under the given consumption capacity
xi and guarantee rate
r%.
In the guaranteed area, the ESS can replace thermal standby power start-up. From (6), the initial consumption capacity
x1 of RE can be calculated. The working position of energy storage can be calculated using Equation (16). The unit value of substituted thermal power generation Δ
x is shown in Equation (21).
The corresponding installed capacity
C of RE can be further obtained from (21), as shown in Equation (22).
At the same time, there will be a probability of 1 − r% throughout the year that the number of interval hours of RE is insufficient; if this occurs, the means of absorbing thermal power is made up. Since the probability r% is generally higher than 85%, the ESS absorbs the RE range with lower prices for a long time, and the thermal generation with relatively high prices is purchased in a short time. Positive economic benefits can still be obtained throughout the year.
In the guaranteed rate failure area, ESS cannot replace thermal power stably. At this time, the working position of ESS is the initial consumption capacity of RE
x1. The installed capacity of RE
C is calculated using Equation (23).
If variable
i is continuously changed between 1 and
m, the lower bound of the corresponding interval
xi varies from
x1 to
xp. For each set of intervals consisting of
x1 and
xi, the result sets of
Tgir,
PHir,
Tbir,
Pbir, and
Ebir are calculated from “equal area criterion”, as shown in Equation (24).
The ESS capacity and the RE consumption capacity can be accurately matched to realize the optimal ESS configuration under the established RE consumption target according to Equation (24). Two typical planning scenarios need to be considered. ESS optimization is carried out when the RE installed capacity is known for the year to be planned. On the contrary, it is necessary to carry out the collaborative optimization of RE and ESS.
4.2. Optimized Configuration Process of ESS Based on “Equal Area Criterion”
When the installed capacity of RE C is known, the optimized configuration process of ESS is shown as follows.
- (a)
The initial consumption capacity of RE x1 is determined from Equation (23) according to the known parameters PLmax, α, β and ε in the planned year.
- (b)
The ESS working position xi is calculated from Equation (21). It is necessary to determine whether the ESS working position is in the guaranteed rate failure area.
- (c)
If the ESS working position is in the guaranteed rate failure area, the working position of ESS will be the initial consumption capacity of RE x1.
- (d)
If the ESS working position is in the guaranteed rate area, taking
xi as the independent variable and
Tgir as the dependent variable, the function
F1 is obtained as shown in (25). The function
F2 fitted from the result set of Equation (24) is shown in Equation (25).
- (e)
The intersection abscissa of the function
F1 and
F2 is defined as
xF, as shown in
Figure 10. The various parameters of ESS (
Tbir,
Pbir, and
Ebir) in the planned year can be obtained by interpolating the results in Equation (24). The specific calculation process is shown in
Figure 11.
When the installed capacity of RE C is unknown, the collaborative configuration process of ESS and RE is shown as follows.
- (a)
The set of initial consumption capacity
x1 of RE can be obtained according to
λ,
β,
Tm and the result sets of Equation (24), as shown in Equation (26).
- (b)
The set of RE installed capacity
C can be determined according to the RE consumption capacity calculation method of Equation (6).
- (c)
The set of RE installed capacity
C is converted into the set of RE penetration rate
θ according to the planned load.
- (d)
Taking the working position of ESS xi as the corresponding point, the relationship between ESS capacity and RE penetration rate is established.
At this time, the obtained installed capacity of ESS and RE is the
m group solution. According to the desired combination, the installed capacity of RE and the corresponding ESS configuration can be selected. The specific calculation process is shown in
Figure 12.