1. Introduction
A microgrid (MG) can be defined as a group of distributed generators (DGs), storage devices and loads, which are connected to a main grid through a controllable switchgear, providing reliable and safe electrical power to a local community [
1]. MGs allow for the massive incorporation of renewable DGs, representing a new and powerful alternative to meet the needs of a growing energy demand. In general terms, they have a positive impact on the integration of renewable energy sources and can be used to improve the overall performance of electricity grids. Nonetheless, there are several challenges associated with the incorporation of MGs in modern electrical systems. These include reliability issues [
2], protection coordination [
3,
4] and optimal sizing [
5,
6]. This paper deals with the last issue, providing a sizing assessment of islanded MGs that considers investment costs and tax benefits.
Islanded MGs are one of the most promissory proposals for supplying electricity in off-grid areas when the cost of energy production is high or when power-supply problems occur [
7]. Usually, off-grid areas use diesel generators for electricity supply; however, the use of diesel generators has negative environmental impacts, while their supply and maintenance are costly [
8]. To overcome the dependence on this technology, hybrid systems that involve distributed energy resources (DERs) such as battery energy storage systems (BESS) and photovoltaic (PV) and wind generators have become a convenient option. Nonetheless, DERs working alone can not continuously supply power to the loads; in consequence, diesel generators and BESS must meet the load demands when DERs present intermittence.
Several researchers have reported the use of hybrid systems in islanded MGs. In [
5,
6,
9], the authors propose configurations of PV generators, wind turbines, fuel cells and backup battery systems. In [
10,
11,
12,
13,
14,
15], only a wind turbine and a battery-backed PV generator were considered, while in [
16,
17,
18,
19,
20,
21,
22,
23,
24,
25,
26] a diesel generator was added as backup. Other generation sources, such as biomass, thermal systems, flywheel and the utility grid, are considered in [
27,
28,
29,
30,
31,
32]. However, the optimal sizing of generators in islanded MGs is still being researched.
MGs planning must guarantee the reliability of the system at a minimum cost, satisfying the needs of users. MGs planning is usually divided into sizing and operation. This is because of the multi-level nature of the problem. Additionally, optimization problems regarding MG planning are often non-convex and NP-hard [
25]. Single- and multi-objective optimization methodologies have been proposed in the technical literature for successful MG planning.
Researchers have used different optimization techniques to size MGs. These techniques can be classified into exact and approximate methods. For example, in [
24], an iterative method and dynamic programming (DP) approach are used to size BEES, considering the energy management system of an MG. In [
26], the authors propose an optimal scheduling approach for a hybrid MG using dynamic programming, which considers BESS, conventional generation (e.g., diesel generator), and PV solar generators. The main objective is to ensure the maximum utilization of the renewable energy resources and minimum operational cost of the conventional resources. In [
29], a methodology based on PV power forecasting and the evolution of load curve is proposed for the optimization of an isolated MG. The proposed method aims to determine the size of PV panels and batteries at minimal cost, maintaining the system’s reliability. In [
16], the authors present a multi-objective optimization method to jointly optimize the planning and operation of a grid-tied MG with various DG sources, such as wind turbine and PV arrays with the assistance of demand-side management. To solve the multi-objective optimization problem, a fuzzy method is adopted to convert the original problem into a single objective optimization problem and a mixed-integer linear programming algorithm is then used to solve this. In [
33], the authors propose a mixed-integer linear programming (MILP) problem that allows for the optimal DER size in a DC MG to be determined. In [
28], an MILP algorithm is used for the optimal sizing of a grid-connected MG, minimizing the total cost. In [
30], dynamic programming and an MILP algorithm was implemented for sizing a small MG with storage. In [
15,
19,
34], the authors use the HOMER tool, which is a widely used software for sizing MGs.
Several metaheuristic techniques were implemented for MG planning in recent years. In [
9], a multi-objective particle swarm optimization (MOPSO) algorithm was carried out to minimize the loss of load expected (LOLE) and loss of energy expected (LOEE) costs of hybrid wind–solar-generating MG systems. In [
6], a gray wolf optimization (GWO) algorithm was used for the optimal sizing of BESS to minimize the operation cost of MGs. In [
10], an improved fruit fly optimization algorithm (IFOA) was used to size islanded MGs with real data collected from Dongao Island. In [
11], an ant colony optimization (ACO) approach was employed to minimize the total capital cost and total maintenance cost in a hybrid PV–wind energy system. In [
35], an artificial bee colony (ABC) algorithm was implemented to size a grid-connected MG with solar PV plants, wind turbines and energy storage systems. The goal is the maximization of energy-saving benefits for the community being served. In [
12], a genetic algorithm (GA) is used for the multi-objective design of hybrid energy systems. The authors aim to minimize the life-cycle cost and greenhouse gas emissions, and dump energy in remote residential buildings. In [
13], the authors tested four different algorithms, namely, ABC, PSO, GA and the gravitational search algorithm (GSA), to solve the optimal sizing of grid-connected MG components. In [
14], a PSO algorithm is developed to determine the optimal configuration of an MG with minimal costs, satisfying the desired loss of power supply probability. In [
18], the whale optimization algorithm (WOA), water cycle algorithm (WCA), moth–flame optimizer (MFO), and hybrid particle swarm-gravitational search algorithm (PSOGSA) were applied for the optimal sizing of PV/wind/diesel hybrid MG systems with BESS, while minimizing the cost of energy (COE) supplied by the system and increasing the reliability and efficiency of the system. In [
20], the ABC optimization algorithm was used the for sizing and performance analysis of a standalone hybrid energy system. In [
22], the authors compare the performance of PSO and invasive weed optimization (IWO) algorithms for the optimal sizing of hybrid microgrids based on PV, wind, diesel and BESS. In this case, the BESS is considered in summer and winter to determine daily storage. In [
21], a GA approach minimizes the total annual cost of the number of solar panels and micro-turbines, battery capacity, and diesel generator size, with a constraint on renewable energy penetration. In [
23], a double-layer optimization strategy is implemented to determine the optimal BESS size, considering the energy management system of an MG. The authors in [
25] propose a bi-level optimization model to solve the problem of planning and operating MG projects, inspired by the system of systems (SoS) concept. In [
27], an optimization technique based on a multi-objective genetic algorithm (MOGA), which uses a high temporal resolution, is implemented to size an MG. The proposed MOGA employs a techno-economic approach to determine the microgrid system design, optimized by considering multiple criteria, including size, cost, and availability. In [
31], the optimal sizing of a standalone PV/wind/biomass hybrid energy system is carried out using GA and PSO optimization techniques.
In the technical literature, some researchers have also analyzed fiscal incentives for implementing MGs. In [
36], the authors conducted a feasibility analysis of solar generation in local communities in Libya. The study was carried out using the Net Present Value (NPV) and payback time indicators to determine the impacts of feed-in tariff (FiT) rates, financial incentives, electricity tariff, and the inflation rate on the economic viability of the PV grid system. In [
37], the authors provide a comprehensive evaluation of the technical and financial feasibility of a campus MG based on a techno-economic analysis. This analysis captures all the benefits of financial incentives for MG projects in California, U.S. The authors in [
38] investigate the effect and cost-efficiency of different renewable energy incentives and the potential for hydrogen energy storage, as well as the perceived viability of an MG project, from the perspective of different stakeholders, i.e., government, energy hub operators and consumers, in Ontario province, Canada. The aforementioned research papers focuses on an analysis of the financial incentives that each government provides to projects that include renewable energy sources; however, the research does not provide a sizing methodology for the MG. Additionally, the analysis is always focused on each studied area and the tax benefits vary with respect to the respective country. The main contribution of this paper is to provide a methodology for the sizing assessment of islanded MGs that minimizes the total cost of supplying the load through a combination of several power sources. Furthermore, tax benefits are included to facilitate the task of decision-makers. Although tax incentives were specifically applied in Colombia, this methodology can be used in other markets adopting different tax benefit rules.
The Colombian government aims to promote the development and implementation of non-conventional energy sources (NCES), primarily those of a renewable nature. These energy sources are meant to be integrated into the electricity market, allowing for the reduction in greenhouse gas emissions and providing a more varied energy basket. Projects that implement NCES could save 50% of the total investment made from their annual income tax over a period no longer than 15 years. They also may apply an accelerated depreciation of up to 20%, an exclusion of value-added tax (VAT) goods and services, and an exemption from customs duties. The 50% income deduction tax and the accelerated depreciation were included in the methodology.
This paper is organized as follows:
Section 2 presents the proposed methodology, which includes the mathematical representation of different elements of the MG. This section also describes the economic and reliability indicators implemented in the proposed methodology.
Section 3 details the proposed optimization model.
Section 4 corresponds to tests and results considering real data.
Section 5 presents a discussion of the results of the paper. Finally,
Section 6 presents the conclusions and future work.
5. Discussion
This section shows the results of 159 tests that were carried out on the case study with a personal computer equipped with an Intel Core i7-8550U 1.8 GHz processor with 8 CPUs and 8 GB of RAM memory. The proposed optimization model was implemented in the Pyomo Python-based open-source package. The solver used in Pyomo was a Gurobi Optimizer version 9.0.3 with an academic license.
Since the formulated model is linear, it is possible to use an open-source solver. However, due to the size of the problem, this is not recommended, because the performance is lower than a solver such as GUROBI, as can be seen in
Figure 8. Note that GUROBI achieves a solution between 0 and 5% of GAP, around 20 min, while CBC achieves the same solution in about 70 min with a higher GAP.
A matrix that correlates the energy supplied with the load and the ASC and LCOE indicators is shown in
Figure 9. Note that diesel energy and ASC have a negative and strong correlation. This means that if the diesel energy increases, the ASC decreases. This behavior is due to the load profile; if the model uses more PV modules and batteries to satisfy the load, then the capital, replacement, operation, and maintenance cost increase. On the other hand, the LCOE has a negative and medium correlation with the PV energy and BESS. This is because of the energy that is supplied to the load; in other words, if the PV modules and BESS increase, the load can be fully covered. In this case, the energy supplied by the diesel generator is not decisive in the LCOE due to operational constraints; if the load is lower than the minimum capacity that is able to dispatch the diesel generator, the load cannot be met.
Figure 10a,b show the relationship between the energy delivered to the load by the MG and the
and
indicators, respectively. The size of the circles indicates the amount of energy delivered to the load by the technoology over a year. The bigger the circle, the more energy is delivered by the corresponding resource.
Figure 10a shows that when ASC is greater than 15k, the energy delivered by the PV array is higher. This indicates that the increase in the installed capacity of the PV array also increases the
costs. Additionally, in
Figure 10b, it is shown that the LCOE is lower in cases where the energy delivered by the PV array is higher with respect to the other resources. Therefore, the simulations that obtained an LCOE of below 0.3 were the ones with the highest installed capacity of the PV array and BESS.
The diesel generator is not decisive in the LCOE because it is a backup resource. In addition, it has technical restrictions regarding the minimum dispatch of its capacity. In other words, in the simulations, the constraint is that the diesel generator is only dispatched if the energy to be covered is at least 90% of its capacity.
Figure 11 shows the fulfillment of the allowed
, which was considered as the objective. It is observed that the resulting
is always lower than the maximum value and varies according to the input parameters. In general terms, if more power generation is available, the resulting
is lower.
Table 5 presents the results of the planning problem for two MG configurations. The first case considers PV panels, BESS, and a diesel generator, while the second case only considers PV panels and BESS.
According to the Institute for Planning and Promotion of Energy Solutions for Non-Interconnected Zones (IPSE), there are 106,566 users in-off grid areas in Colombia, which typically have between 5 and 10 hours of daily electrical service [
45]. If this type of MG were installed in a non-interconnected area with similar characteristics, the two solutions found in this paper would improve electricity supply in these off grid areas, with 19 and 21 h, respectively. In these hours, the load was fully supplied (
). This may vary according to the
selected at the beginning of the projects and the user criteria when selecting the sizing methodology. Furthermore, the results show that the best cost is obtained in the first option, with an
of 0.51
$/kWh, which is 0.27
$/kWh lower than the second option, with 0.78
$/kWh. This result is due to the load profile, in which, during the hours of lower solar radiation, there is a high energy demand; therefore, for the second option, more PV and BESS units are required to satisfy the energy demand.
Figure 12 corresponds to the energy supplied to the load in a year.
Figure 12a,b shows that, for the first and second cases, the energy provided from renewable resources is prioritized over the energy provided by the diesel generator, in accordance with the proposed optimization model. Then, in the PV-BESS-DG solution, the energy delivered by the PV array to the load corresponds to
, the energy delivered by the BESS to the load corresponds to
, and the energy delivered by the diesel generator to the load was
. Finally, the non-served energy was
. For the PV-BAT solution, the energy delivered by the PV array to the load corresponds to
, while the energy delivered by the BESS was
. Finally, the non-served energy was
.
Figure 13 corresponds to the energy supplied to the load in a day from PV-BESS-DG and PV-BESS. Samples were randomly taken from one day that illustrates the hourly load curve. These figures show that the diesel generator and BESS are only used when the PV energy is not available or is insufficient, with the diesel generator providing the last option to supply the load and charge the BESS.
Figure 13a shows that energy is not supplied for some hours. This is because the
of the BESS is below the allowable limits or, due to technical restrictions, the diesel generator is at its minimum operative power. For the PV-BESS-DG solution in the early morning hours of 0, 2, 3, 4 and 5, the use of BESS was required. Nonetheless, at hours 0, 4 and 5, there was PENS. At hour 1, all the energy was supplied by diesel energy. In hours 6, 7, 8, 9, PENS was present even though PV energy was available. This is due to the fact that the irradiance in those hours is low and does not cover the demand. Likewise, the BESS did not have stored energy and the diesel generator could not be dispatched due to technical restrictions. In hours 10, 11, 12, 13 and 14, the demand was supplied only by PV energy due to the high availability of the solar resource. Hours 15 and 16 were supplied by the BESS and PV energy. Hours 17 and 18 were supplied solely by the diesel generator. This is due to the fact that the minimum capacity restrictions for the diesel generator were met while there is no solar resource or sufficient energy in the BESS. Finally, in hours 19, 20, 21, 22 and 23, the demand was supplied by the BESS. For the PV-BAT-DG solution, it is shown that, in hours 17 and 18, the diesel generator was used as a backup due to the shortage of energy from the PV array and BESS. In hours 5, 6, 7, 8, and 9, there was no power supplied for the day under analysis. In the evening hours, power was mainly supplied from the BESS. In the PV-BAT solution, between 6 and 17 hours, energy was mainly used from the PV array, while in the evening hours, the BESS was used to supply the energy.
Figure 14 shows the hourly average for the whole year of the energy used to charge the BESS. The blue line is the energy used to charge the BESS, while the orange and green lines indicate the energy used from PV and diesel to charge the BESS, respectively.
Figure 14 illustrates that the optimization model proposed prioritizes PV energy when charging the BESS and only uses the energy from the diesel generator when PV energy is not available. The model prioritizes the BESS load according to the cheapest resource: in this case, PV energy. Then, between 6 a.m. and 5 p.m., the BESS is charged with the energy left over from the PV array after supplying the load. Between 2 and 4 p.m., the highest use of the diesel generator is presented to charge the battery, this is because, in these hours, the
of the BESS is at its lowest levels.
Figure 15 shows the average SoC of the BESS. For the two given solutions, it is shown that the battery charging process mainly occurs between 7 a.m. and 5 p.m. This is due to the solar resource’s availability for charging. The green and orange lines show that the charging and discharging processes do not occur simultaneously.
Figure 15a indicates the hourly average for the whole year. The blue line is the behavior of the SoC during the 24 h. The green line shows the energy used (PV energy + diesel energy) to charge the BESS. The orange line indicates the energy used from the BESS to supply the load. The charging and discharging process meets the maximum energy per hour (Emax). The dashed region denotes the range (in kWh) of the BESS capacity with its maximum and minimum SoC(t), considering the DODmax parameter of the BESS. The process starts when energy is available from the diesel generator and PV Array. Meanwhile,
Figure 15b shows that the BESS is only charged when energy is available from the PV array. In
Figure 15a, the maximum size of the BESS is 40 kWh, while in
Figure 15b, it is 100 kWh. This is because
Figure 15a illustrates a solution that uses a backup diesel generator. This means that the solar and BESS system is smaller and not oversized. In
Figure 15b, the size of the BESS significantly increases due to the need to meet the load supply. Likewise, the size of the PV system also increases. Therefore, when diesel generation is not used as a backup, the BESS and solar systems are oversized.
Figure 16 corresponds to the charging and discharging Process of the BESS in a day for PV-BESS-DG and PV-BESS configurations. At hour 8, the BESS is loaded by the PV system and the diesel generator. At hour 10, there is no charging or discharging process. This is because the diesel generator and the PV system supply the load. At hours 11, 12 and 13, the highest energy supplied by the system to charge the BESS is observed. At hours 14 and 15, it is necessary to use the BESS to feed the load because the production of the PV system is reduced. At hours 16, 17, 18 and 19, the BESS is in the process of charging, taking advantage of the energy remaining in the diesel generator after feeding the load.
In
Figure 16b, between 7 and 13 h, there is excess solar energy production; therefore, the BESS is charged. When the solar energy production is low, the BESS feeds the load in all hours, from 14 to 6.
Figure 16a,b show that, in both options, the optimization model ensures that the process of charging and discharging the BESS does not occur at the same time. For the PV-BAT-DG solution, it is observed that, at hours 11, 12, and 13, a charging process was initiated; therefore, the battery did not supply energy to the user (discharge process). At hours 14 and 15, the opposite occurred when the discharge process was initiated. The same behavior is observed in the PV-BESS solution. In solution 1, a system with a backup diesel generator decreases the need for PV systems; therefore, BESS and the PV system have lower capacity. This lowers the cost of the system. In the absence of a diesel generator, the PV system and BESS need to be significantly increased in size. This means that, during hours with high solar radiation, there is excess generation. When there is excess solar energy, it is not necessary to use the BESS; thus, the BESS is charged during the hours with solar production.
6. Conclusions
This paper presented a methodology that can be used by decision-makers for the optimal sizing of islanded MGs. This methodology considers a deterministic optimization model and the tax benefits that the Colombian government offers to new projects that include renewable energy. The optimization model considers the technical constraints of BESS, such as the maximum cycles allowed for charging and discharging. The reliability of the system was included as a constraint on the optimization model and the energy supplied to the load was considered as a variable with a high cost in the objective function (penalization).
Two cases were selected from the simulations in the Python programming language: The first one considered PV panels, a BESS and a diesel generator, while the second one considered PV panels and a BESS without a diesel generator. The second case presented the highest cost since it requires more PV and BESS, with the latter being the most expensive devices of the MG. The results showed that the service of the user can be improved using the proposed methodology.
The total energy, by source, was related to ASC and LCOE. It was observed that the energy delivered by the PV array is higher with respect to other resources. In fact, the selected solutions provide 19 and 21 hours, respectively, without having energy that is not served to the load.
It was found that the LCOE was lower when considering the tax benefits. The meteorological data and the load profile are decisive in the sizing process of each case. This methodology can be used for sizing an islanded microgrid. Nonetheless, certain information must be available, such as the hourly load profile of the users, meteorological data, technical data of the system assets and the tax-benefits rules.
The main limitation of the proposed approach lies on the fact that it is restricted to a specific topology of the MG. Future work will include more versatile MG topologies, as well as other features, such as the effect of demand response.